Skip to content

Shingdhol, Raigarh

Deedo IDDL-RAI-SHINGDHOL

10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4
Registrations4
Completion still due22 past their date
Median extension4 months75% of registrations extended
Regulatory cases0none on MahaRERA's lists

10 in 10 registrations run late here

4 MahaRERA registrations in Shingdhol

2 extended, not yet due2 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Shingdhol

4 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Victoria Hills Phase 3Greencity IndiaDue Sep 2028, extended 4 mo——
Victoria Hills Phase - 2Asfak Sharakat Choudhari5 mo late——
Beverly HillsRudram Infra Projects Private LimitedDue Apr 2027, extended 4 mo——
Victoria HillsAsfak Sharakat Choudhari1 yr 8 mo late——
Shingdhol market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Asfak Sharakat Choudhari2 projects
  2. Asfak Sharakat Choudhari1 project
  3. Greencity India1 project
  4. Rudram Infra Projects Private Limited1 project

Shingdhol, in questions

How many projects in Shingdhol run late?

10 in 10 MahaRERA registrations (4 of 4): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Shingdhol by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology