Skip to content
Deedo home
Menu

Shiv Utsav

Certificate Signed

Pashane, Raigarh 421503 |Promoter: Maruti Enterpises

Residential / Group HousingRERAP52000007812
18 Aug 2017Registered with MahaRERA
14 Mar 2024Promised completion
13 Mar 2025Revised completionPushed back 1 year
9Buildings
255Units registered163 booked (64%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
9
Unit types
1BHK, 1RK, Shop, 2BHK, 1 BHK, 2 BHK255 units in all
Address
150/12/A/3 And 150/12/B And 151/5 PPIN 421503
Designated bank account
21
Developed in phases
Yes

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.11026, 73.32960
Shiv Utsav is at latitude 19.11026, longitude 73.32960.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 1 year

The latest completion date on record passed 1 year and 7 months ago.

Registered
18 Aug 2017
Promised
14 Mar 2024
Revised
13 Mar 2025

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200000781218 Aug 201714 Mar 202413 Mar 2025Maruti EnterpisesProject page

9 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Wing A638
Wing B628
Wing C628
Wing D627
Wing E627
Wing F627
Wing G627
Wing H628
Wing I625

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

163 of 255 units booked (64%), as the promoter reported to MahaRERA

1BHK · 156 units1RK · 8 unitsShop · 10 units2BHK · 68 units1 BHK · 9 units2 BHK · 4 units
BuildingTypeCarpet areaUnitsBooked
Wing A1BHK23.17 sq m · 249 sq ft40
Wing A1BHK25.52 sq m · 275 sq ft40
Wing A1BHK25.98 sq m · 280 sq ft80
Wing A1BHK26.1 sq m · 281 sq ft40
Wing A1RK23.97 sq m · 258 sq ft80
Wing AShop10.81 sq m · 116 sq ft20
Wing AShop14.16 sq m · 152 sq ft60
Wing AShop18.01 sq m · 194 sq ft20
Show all 78 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Wing B1BHK23.99 sq m · 258 sq ft22
Wing B1BHK26.01 sq m · 280 sq ft71
Wing B1BHK26.42 sq m · 284 sq ft10
Wing B1BHK26.68 sq m · 287 sq ft33
Wing B1BHK26.69 sq m · 287 sq ft11
Wing B1BHK26.7 sq m · 287 sq ft33
Wing B1BHK26.99 sq m · 291 sq ft11
Wing B1BHK30.39 sq m · 327 sq ft21
Wing B1BHK36.27 sq m · 390 sq ft11
Wing B2BHK31.62 sq m · 340 sq ft11
Wing B2BHK34.51 sq m · 371 sq ft22
Wing B2BHK37.87 sq m · 408 sq ft44
Wing C1BHK23.99 sq m · 258 sq ft44
Wing C1BHK26.01 sq m · 280 sq ft44
Wing C1BHK26.42 sq m · 284 sq ft10
Wing C1BHK26.68 sq m · 287 sq ft65
Wing C1BHK26.69 sq m · 287 sq ft11
Wing C1BHK26.97 sq m · 290 sq ft11
Wing C2BHK30.39 sq m · 327 sq ft22
Wing C2BHK34.51 sq m · 371 sq ft33
Wing C2BHK36.27 sq m · 390 sq ft22
Wing C2BHK37.87 sq m · 408 sq ft44
Wing D1BHK23.99 sq m · 258 sq ft33
Wing D1BHK26.01 sq m · 280 sq ft22
Wing D1BHK26.42 sq m · 284 sq ft10
Wing D1BHK26.68 sq m · 287 sq ft22
Wing D1BHK26.7 sq m · 287 sq ft42
Wing D1BHK37.87 sq m · 408 sq ft33
Wing D2BHK30.39 sq m · 327 sq ft11
Wing D2BHK31.62 sq m · 340 sq ft11
Wing D2BHK34.51 sq m · 371 sq ft88
Wing D2BHK34.61 sq m · 373 sq ft11
Wing D2BHK52.47 sq m · 565 sq ft11
Wing E1 BHK26.42 sq m · 284 sq ft10
Wing E1BHK23.99 sq m · 258 sq ft22
Wing E1BHK26.01 sq m · 280 sq ft22
Wing E1BHK26.68 sq m · 287 sq ft11
Wing E2 BHK37.87 sq m · 408 sq ft41
Wing E2BHK30.39 sq m · 327 sq ft22
Wing E2BHK31.62 sq m · 340 sq ft22
Wing E2BHK34.51 sq m · 371 sq ft99
Wing E2BHK36.27 sq m · 390 sq ft44
Wing F1BHK23.99 sq m · 258 sq ft43
Wing F1BHK26.01 sq m · 280 sq ft88
Wing F1BHK26.42 sq m · 284 sq ft10
Wing F1BHK26.68 sq m · 287 sq ft43
Wing F1BHK26.69 sq m · 287 sq ft43
Wing F2BHK30.39 sq m · 327 sq ft21
Wing F2BHK37.87 sq m · 408 sq ft43
Wing G1BHK23.99 sq m · 258 sq ft43
Wing G1BHK26.01 sq m · 280 sq ft99
Wing G1BHK26.42 sq m · 284 sq ft10
Wing G1BHK26.68 sq m · 287 sq ft44
Wing G1BHK26.7 sq m · 287 sq ft33
Wing G1BHK30.39 sq m · 327 sq ft21
Wing G2BHK37.87 sq m · 408 sq ft43
Wing H1BHK23.99 sq m · 258 sq ft41
Wing H1BHK26.01 sq m · 280 sq ft95
Wing H1BHK26.42 sq m · 284 sq ft10
Wing H1BHK26.68 sq m · 287 sq ft41
Wing H1BHK26.69 sq m · 287 sq ft43
Wing H2BHK30.39 sq m · 327 sq ft20
Wing H2BHK37.87 sq m · 408 sq ft42
Wing I1 BHK26.68 sq m · 287 sq ft43
Wing I1 BHK26.69 sq m · 287 sq ft44
Wing I1BHK23.99 sq m · 258 sq ft72
Wing I1BHK26.01 sq m · 280 sq ft44
Wing I1BHK26.42 sq m · 284 sq ft10
Wing I2BHK30.39 sq m · 327 sq ft21
Wing I2BHK37.87 sq m · 408 sq ft30

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

2 documents held by Deedo, 60 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardPAN.pdf · uploaded 3 Aug 2017Source

Legal

  • Declaration Form BDeclaration Form B_Promoter.pdf · uploaded 3 Aug 2017Source
  • Legal Title reportTitle certificate.pdf · uploaded 3 Aug 2017Source
  • Legal Title reportSale Deed Index II 55 5 Guntha.pdf · uploaded 3 Aug 2017Source
  • Declaration Form BDeclaration Form B OC date 130325.pdf · uploaded 30 Jan 2024Source

Migrated

  • 1 PAN CardPAN.pdf · uploaded 3 Aug 2017Source
Show all 62 documentsShow fewer documents

Migrated

  • 1 Copy of the legal title reportTitle certificate.pdf · uploaded 3 Aug 2017Source
  • 2 Copy of the legal title reportSale Deed Index II 55 5 Guntha.pdf · uploaded 3 Aug 2017Source
  • 1 Details of encumbrancesEncrambrance Certificate_Promoter.pdf · uploaded 3 Aug 2017Source
  • 1 Copy of Layout Approval (in case of layout)Layout plan Shiv Utsav.pdf · uploaded 3 Aug 2017Source
  • 1 Building Plan Approval (IOD)Layout plan Shiv Utsav.pdf · uploaded 3 Aug 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentcc maruti ent-ilovepdf-compressed.pdf · uploaded 3 Aug 2017Source
  • 1 Declaration in FORM BDeclaration Form B_Promoter.pdf · uploaded 3 Aug 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate2.pdf · uploaded 3 Aug 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form2_Engineers Certificate.pdf · uploaded 3 Aug 2017Source
  • 1 Certificates of CA (Form 3)CA Certificate Final.pdf · uploaded 3 Aug 2017Source
  • 1 Proforma of Allotment letterFLAT SALE AGREEMENT.pdf · uploaded 3 Aug 2017Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ilovepdf_jpg_to_pdf (1)-ilovepdf-compressed (2).pdf · uploaded 27 Apr 2018Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ilovepdf_jpg_to_pdf (1)-ilovepdf-compressed (2).pdf · uploaded 27 Apr 2018Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARTICTURE CERTIFICATE.pdf · uploaded 27 Apr 2018Source
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARTICTURE CERTIFICATE.pdf · uploaded 27 Apr 2018Source
  • 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARTICTURE CERTIFICATE.pdf · uploaded 27 Apr 2018Source
  • 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARTICTURE CERTIFICATE.pdf · uploaded 27 Apr 2018Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEER CERTIFICATE.pdf · uploaded 27 Apr 2018Source
  • 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARTICTURE CERTIFICATE.pdf · uploaded 28 Apr 2018Source
  • 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARTICTURE CERTIFICATE.pdf · uploaded 28 Apr 2018Source
  • 1 Certificates of CA (Form 5)PROJECT SHIV UTSAV.pdf · uploaded 15 Oct 2018Source
  • 10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)architecture certificate.pdf · uploaded 1 Feb 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5_Maruti Enterprises.pdf · uploaded 25 Dec 2019Source
  • 11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)MARUTI ENT.pdf · uploaded 9 Jan 2020Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2 310721compressed.pdf · uploaded 22 Sep 2021Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC B C Wing 270520.pdf · uploaded 22 Sep 2021Source
  • 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC DE.pdf · uploaded 22 Sep 2021Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)Society certificate B C D E F G.pdf · uploaded 16 Aug 2023Source
  • 12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 dt 31122023.pdf · uploaded 23 Jan 2024Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Maruti Enterprises Signed.pdf · uploaded 23 Jan 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 2A 2019.pdf · uploaded 23 Jan 2024Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 2A 2020.pdf · uploaded 23 Jan 2024Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A 2020.pdf · uploaded 23 Jan 2024Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A 2021.pdf · uploaded 23 Jan 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A 2022.pdf · uploaded 23 Jan 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A 2023.pdf · uploaded 23 Jan 2024Source
  • 2 Certificates of CA (Form 3)FORM 3 uploaded 311223.pdf · uploaded 23 Jan 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM-5 FY 2019-20.pdf · uploaded 23 Jan 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM-5 FY 2020-21.pdf · uploaded 23 Jan 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 FY 2021 22 uploaded.pdf · uploaded 23 Jan 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM-5 FY 2022-23.pdf · uploaded 23 Jan 2024Source
  • 1 Proforma of Agreement for saleFLAT SALE AGREEMENT.pdf · uploaded 23 Jan 2024Source
  • 1 Declaration about Commencement CertificateDeclaration about commencement certificate.pdf · uploaded 30 Jan 2024Source
  • 2 Declaration in FORM BDeclaration Form B OC date 130325.pdf · uploaded 30 Jan 2024Source
  • 1 Disclosure of sold/ booked inventoryInventory sold unsold 311223 Final.pdf · uploaded 30 Jan 2024Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Maruti Enterprises 26 04 2024 Signed.pdf · uploaded 25 Jun 2024Source
  • 13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 Maruti Enterprises Dt 26 04 2024 Signed 11zon.pdf · uploaded 1 Jul 2024Source
  • 2 Architect’s Certificate on Completion of Project (Form 4)Form 4 all wings.pdf · uploaded 3 Dec 2024Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)Form 4 All Wings.pdf · uploaded 24 Jan 2025Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC wing H I and A 290824.pdf · uploaded 24 Jan 2025Source

Technical

  • DocumentLayout plan Shiv Utsav.pdf · uploaded 3 Aug 2017Source
  • DocumentLayout plan Shiv Utsav.pdf · uploaded 3 Aug 2017Source

Technical (Architect)

  • DocumentFORM 1 Maruti Enterprises Dt 26 04 2024 Signed 11zon.pdf · uploaded 1 Jul 2024Source

Technical (Engineer)

  • DocumentForm 2 Maruti Enterprises 26 04 2024 Signed.pdf · uploaded 25 Jun 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Pashane, Karjat taluka

Survey, CTS, gat or plot numbers

150/12/A/3150/12/B151/5 P

Boundaries

North
1
South
15 Mt Wide Proposed Road
East
Sr No 162
West
1

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectDestination Architecture Interior Service—
EngineerK R Patel And Associates—
OtherKiran Banote—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology