9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects143
Registrations143
Completion still due12617 past their date
Median extension4 months74% of registrations extended
Regulatory cases0none on MahaRERA's lists

9 in 10 registrations run late here

143 MahaRERA registrations in Dapoli

22 not yet due104 extended, not yet due17 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Dapoli

143 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Venkatesha HeightsManoj Jaysing DongareDue Apr 2027, extended 4 mo—48%
Tejas VaishnaviTejas Sangram PatilDue Feb 2029, extended 4 mo——
Pushpak PrideAdmire InfraDue Dec 2028—2%
Hari PriyaShree Priyakanthji Realtors LLPDue Oct 2027, extended 4 mo—7%
PushprajBluescape Builders And DevelopersCompleted—38%
Matrix LandmarkMatrixinfraDue Apr 2029, extended 4 mo—27%
Bhaveshwar OneShiv InfratechDue Apr 2028, extended 4 mo—16%
Infragate PalaceSharda InfraDue Apr 2027, extended 4 mo—58%
Amrut DharaShree Ganesh EnterprisesDue Apr 2029, extended 4 mo——
Amrut VishvaAnaahat EnterpriseDue Apr 2028, extended 4 mo——
Hari Vitthal Complex 1Nagesh Annasaheb SurvaseCompleted——
The Domus 26 EastAramus Ventures LLPDue Apr 2029, extended 4 mo—62%
Ashtavinayak MiracleS G GroupDue Apr 2029, extended 4 mo——
Majestic KrishnaKrishna Builders and DevelopersCompleted——
Kavya HillsB N DevelopersDue Apr 2030, extended 4 mo—21%
The IvyEstrela EstatesDue Apr 2027, extended 4 mo—25%
Siddhivinayak SparshAjay Ananta PatilDue Jul 2027, extended 4 mo—31%
Siddhivinayak HarmonyRiu Homes Private LimitedDue Mar 2030—23%
Venkatesha GraceAvinash Dagdu JagdaleDue Apr 2028, extended 4 mo—25%
Aryan CornerG R K Infra DevelopmentsDue Aug 2027, extended 4 mo——
Siddhivinayak AarambhRiu Homes Private LimitedDue Mar 2030—21%
Atharva SankalpSankalp GroupDue Dec 2026——
DivineDevkrupa Lifestyle LLPDue Apr 2028, extended 4 mo—32%
Rishikesh HomeRishikesh InfraDue Dec 2026——
Thakur NeelkamalThakur Realtors Private LimitedDue Apr 2029, extended 4 mo——
Dapoli market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Riu Homes Private Limited4 projects
  2. Prime Abhishek Buildcon3 projects
  3. Shree Ganesh Enterprises3 projects
  4. Bhagwati Signature Llp2 projects
  5. G R K Infra Developments2 projects
  6. Gyana Enterprises2 projects
  7. Nagesh Annasaheb Survase2 projects
  8. Sankalp Group2 projects
  9. Savitri Builders and Developer2 projects
  10. S G Group2 projects

Dapoli, in questions

How many projects in Dapoli run late?

9 in 10 MahaRERA registrations (121 of 143): their completion date was extended or has passed, data through 22 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Dapoli by Deedo. Medians on fewer than 3 deeds are not shown.

Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology