Deedo IDDP-RAI-YTHVIt is due for completion in Dec 2026, with no extension on record; no MahaRERA orders on record; 80% of its units are booked.
Dapoli, Raigarh 410206 · by Rishikesh Infra
Buying a flat here?
See every deed registered on it.
It is due for completion in Dec 2026, with no extension on record
- This projectRegistered 21 Aug 2023, completion promised 31 Dec 2026.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52000052386
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000052386 | 21 Aug 2023 | 31 Dec 2026 | 31 Dec 2026 | Rishikesh Infra | Project page |
Documents81
1 document held by Deedo, 80 filings listed on MahaRERA's project page
Finance
Legal
Show all 81 documentsShow fewer documents
Migrated
- 1 Building Plan Approval / NA Order for plotted developmentCC DWG.pdf · uploaded 18 Apr 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentCC COPY.pdf · uploaded 18 Apr 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1com.pdf · uploaded 18 Apr 2023Source
- 1 a Details of encumbrances concerned to Finance1 No Encumbrances Certificate to finance- SB.pdf · uploaded 30 May 2023Source
- 2 a Details of encumbrances concerned to Finance2 No Encumbrances Certificate to Legal- SB.pdf · uploaded 30 May 2023Source
- 1 b Details of encumbrances concerned to Legal1 No Encumbrances Certificate to finance- SB.pdf · uploaded 30 May 2023Source
- 2 b Details of encumbrances concerned to Legal2 No Encumbrances Certificate to Legal- SB.pdf · uploaded 30 May 2023Source
- 1 Copy of Layout Approval (in case of layout)Disclosur about layout_compressed.pdf · uploaded 30 May 2023Source
- 1 Declaration about Commencement Certificate3 Declaration about CC SB.pdf · uploaded 30 May 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 30 May 2023Source
- 1 Disclosure of sold/ booked inventory5 Sold unsold declaration -SB.pdf · uploaded 30 May 2023Source
- 1 CERSAI detailsCRESAI.pdf · uploaded 30 May 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosur other project Ramesh_compre.pdf · uploaded 2 Jun 2023Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsDisclosur other projectpravin dhanji_compressed.pdf · uploaded 2 Jun 2023Source
- 1 Deviation Report with respect to Allotment letterno devication certificate.pdf · uploaded 2 Jun 2023Source
- 1 Deviation Report with respect to model copy of Agreement10 No Deviation in Agreement SB.pdf · uploaded 2 Jun 2023Source
- 1 Declaration in FORM Bform B updated.pdf · uploaded 13 Jun 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 sign.pdf · uploaded 13 Jun 2023Source
- 1 Proforma of Allotment letterProforma of Allotment letter Rishikesh Home.pdf · uploaded 13 Jun 2023Source
- 1 Proforma of Agreement for saleProforma agreement for sale 30 06 2023.pdf · uploaded 30 Jun 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the same11 separate bank account- Form A RI.pdf · uploaded 30 Jun 2023Source
- 2 CERSAI detailsCERSAI - SB.pdf · uploaded 15 Jul 2023Source
- 1 Other – FinanceNo Encumbrances Certificate to finance- SB.pdf · uploaded 15 Jul 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 RI.pdf · uploaded 7 Feb 2024Source
- 2 Disclosure of sold/ booked inventorySold unsold inventory.pdf · uploaded 7 Feb 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 dec 23.pdf · uploaded 10 Feb 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 20 Feb 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)1 Form 1 ARCHITECT'S CERTIFICATE.pdf · uploaded 25 Apr 2024Source
- 3 Disclosure of sold/ booked inventory5 Sold unsold declaration -SB.pdf · uploaded 25 Apr 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)2 Form 3 CA certificate - RH Q4 UPLOAD.pdf · uploaded 29 Apr 2024Source
- 4 Disclosure of sold/ booked inventorySold Unsold Inventory.pdf · uploaded 22 Jul 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 ARCHITECT'S CERTIFICATE.pdf · uploaded 23 Jul 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)PLOT NO 406 SECFTOR NO 03 PUSHPAK DAPOLI FORM 2 RERA.pdf · uploaded 6 Aug 2024Source
- 3 Disclosure of Interest in Other Real Estate OrganizationsForm 3 CA certificate - RH Q1 signed1.pdf · uploaded 6 Aug 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5.pdf · uploaded 14 Oct 2024Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 Signed.pdf · uploaded 14 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Signed.pdf · uploaded 17 Oct 2024Source
- 2 Disclosure of sold/ booked inventorySold Unsold declaration.pdf · uploaded 17 Oct 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 CA certificate - RH Q2 Signed.pdf · uploaded 25 Nov 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 for Upload_compressed.pdf · uploaded 13 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryRL SOLD UNSOLD.pdf · uploaded 24 Jan 2025Source
- 1 Copy of the legal title report9 Title Search_compressed.pdf · uploaded 25 Jan 2025Source
- 1 Copy of Layout Approval (in case of layout)2 Drawing Copy.pdf · uploaded 25 Jan 2025Source
- 1 Proforma of Allotment letterProforma Allotment Letter RH.pdf · uploaded 25 Jan 2025Source
- 1 Commencement Certificates / NA Order for plotted development1 New CC.pdf · uploaded 25 Jan 2025Source
- 1 Declaration about Commencement Certificate5 Declaration for CC 1.pdf · uploaded 25 Jan 2025Source
- 1 Deviation Report with respect to model copy of AgreementDeviation Report.pdf · uploaded 25 Jan 2025Source
- 1 Proforma of Agreement for saleRera Agr Sale new rera updation P 406.pdf · uploaded 25 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Signed.pdf · uploaded 11 Apr 2025Source
- 1 Disclosure of sold/ booked inventorySold Unsold declaration (1).pdf · uploaded 16 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 CA certificate - RH Q4 Signed.pdf · uploaded 22 Apr 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 CA certificate - RH Q4 Signed.pdf · uploaded 22 Apr 2025Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 19 Jul 2025Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 19 Jul 2025Source
- Withdrawal Update Form 3Form3 Signed.pdf · uploaded 19 Jul 2025Source
- Form 5 (FY 2024-2025)Form 5 Rishikesh Infra - for upload.pdf · uploaded 17 Sep 2025Source
- Withdrawal Update Form 1Form 1 for Upload.pdf · uploaded 17 Oct 2025Source
- Withdrawal Update Form 2Form 2 for Upload.pdf · uploaded 17 Oct 2025Source
- Withdrawal Update Form 3Form 3 signed for upload.pdf · uploaded 17 Oct 2025Source
- Withdrawal Update Form 1NEW FORMAT FORM 1 to upload.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 2Form 2 RI 25-26.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 3Form3 FY 25-26 Q3 RH signed.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 1RERA FORM 1 to upload.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 22 RERA 31-03-2026 to upload.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 3Form 3 CA certificate - RH Q4 Signed.pdf · uploaded 20 Apr 2026Source
- Form 5 (FY 2025-2026)Form 5 - Rishikesh Infra signed.pdf · uploaded 26 Sep 2026Source
Technical
Technical (Architect)
Technical (Engineer)
- Document2 RERA 31-03-2026 to upload.pdf · uploaded 20 Apr 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel PLOT NO. 406, SEC 03
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- —45 units in all
- Address
- Plot No. 406, Sec 03, Dapoli, PushpakPIN 410206
- Village
- Dapoli, Panvel taluka
- Location
- 17.76770, 73.19101
- Land area for this project
- 570 sq m (6,134 sq ft)
- Permissible built-up area
- 1,906 sq m (20,517 sq ft)
- Sanctioned built-up area
- 1,906 sq m (20,517 sq ft)
- Recreational open space
- 0 sq m (0 sq ft)
- Designated bank account
- 109
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
PLOT NO. 406, SEC 03
Boundaries
- North
- Plot No 403 402
- South
- 15 M Wide Road
- East
- Plot No 407
- West
- Plot No 405
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking45 units
45 units registered
| Type | Carpet area | Units |
|---|---|---|
| — | — | 45 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals5
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Destination Architecture Interior Designs | — |
| Chartered accountant | A. T. Upadhye & Co. | — |
| Chartered accountant | Deepesh Shah & Associates | — |
| Engineer | S.r.consultants | — |
| Other | Ankit D Godhani | — |
Source: MahaRERA project page. Contact details are not shown.