Adai, Raigarh

Deedo IDDL-RAI-ADAI

10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects17
Registrations18some projects hold several
Completion still due711 past their date
Median extension4 months61% of registrations extended
Regulatory cases0none on MahaRERA's lists

10 in 10 registrations run late here

18 MahaRERA registrations in Adai

7 extended, not yet due11 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Adai

17 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Satyajyot NxtExcel RealityDue Apr 2030, extended 4 mo——
SSV EliteSsv BuildersDue Jul 2027, extended 4 mo——
MangalmurtiShree Ganesh DevelopersDue Jul 2028, extended 4 mo——
Alliance CornerAlliance Vision Services LLPDue Apr 2028, extended 4 mo——
Balaji Pride - Phase IEmkayen Realty Pvt Ltd.Due Jul 2027, extended 4 mo—45%
All 17 projects →
Adai market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. J B Infra Projects3 projects
  2. Prayag Properties2 projects
  3. Alliance Vision Services LLP1 project
  4. Anant Realty1 project
  5. Balaji Homes1 project
  6. Dattatreya Balaram Kurangale1 project
  7. Emkayen Realty Pvt Ltd1 project
  8. Excel Reality1 project
  9. Kaizen India Realty1 project
  10. Shree Ganesh Developers1 project

Adai, in questions

How many projects in Adai run late?

10 in 10 MahaRERA registrations (18 of 18): their completion date was extended or has passed, data through 29 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Adai by Deedo. Medians on fewer than 3 deeds are not shown.

Data through29 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology