Skip to content
Residential / Group Housing · 1 building · 37 unitsRERA P52000079915

Mangalmurti

Deedo IDDP-RAI-NBCA

Completion was pushed back 4 months, to Jul 2028; no MahaRERA orders on record; 0% of its units are booked.

Adai, Raigarh 410206 · by Shree Ganesh Developers

DeliveryExtended 4 moPromised Mar 2028 · now due Jul 2028RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 37 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Jul 2028

  • This projectRegistered 29 Mar 2025, completion promised 30 Mar 2028, revised to 30 Jul 2028.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000079915
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200007991529 Mar 202530 Mar 202830 Jul 2028Shree Ganesh DevelopersProject page
Documents70

1 document held by Deedo, 69 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardShree Ganesh Developers PAN CARD (2).pdf · uploaded 19 Feb 2025Source
  • Other – FinanceDeclaration of land owner.pdf · uploaded 12 Mar 2025Source
  • Other – FinanceDeclartion For Land Cost.pdf · uploaded 13 Mar 2025Source
  • Other – FinanceLandowners Declaration.pdf · uploaded 22 Mar 2025Source

Legal

  • Legal Title reportTitle Search Report Mangalmurti.pdf · uploaded 19 Feb 2025Source
  • Declaration Form BForm B Promoter Manglmurti.pdf · uploaded 19 Feb 2025Source

Migrated

  • 1 PAN CardShree Ganesh Developers PAN CARD (2).pdf · uploaded 19 Feb 2025Source
Show all 70 documentsShow fewer documents

Migrated

  • 1 Copy of the legal title reportTitle Search Report Mangalmurti.pdf · uploaded 19 Feb 2025Source
  • 1 Declaration in FORM BForm B Promoter Manglmurti.pdf · uploaded 19 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Mangalmurti.pdf · uploaded 19 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Mangalmurti.pdf · uploaded 19 Feb 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC Mangalmurti.pdf · uploaded 19 Feb 2025Source
  • 1 Building Plan Approval / NA Order for plotted developmentLayout and Building Drawing Mangalmurti.pdf · uploaded 19 Feb 2025Source
  • 1 Declaration about Commencement CertificateCC declaration Mangalmurti.pdf · uploaded 19 Feb 2025Source
  • 1 CERSAI detailsCERSAI Report Mangalmurti.pdf · uploaded 19 Feb 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Format B Mangalmurti.pdf · uploaded 19 Feb 2025Source
  • 1 a Details of encumbrances concerned to Financelegal encumbrances.pdf · uploaded 11 Mar 2025Source
  • 1 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 11 Mar 2025Source
  • 1 Proforma of Allotment letterAllotment Letter - Mangal Murti.pdf · uploaded 11 Mar 2025Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)Format A.pdf · uploaded 11 Mar 2025Source
  • 1 Deviation Report with respect to Allotment letterDeviation Report of Allotment letter.pdf · uploaded 11 Mar 2025Source
  • 1 b Details of encumbrances concerned to Legallegal encumbrances.pdf · uploaded 11 Mar 2025Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation Report of AFS 1.pdf · uploaded 11 Mar 2025Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of interest in other org of kurangale.pdf · uploaded 11 Mar 2025Source
  • 1 Other – FinanceDeclaration of land owner.pdf · uploaded 12 Mar 2025Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of interest sunita jadhav.pdf · uploaded 12 Mar 2025Source
  • 2 Other – FinanceDeclartion For Land Cost.pdf · uploaded 13 Mar 2025Source
  • 1 Other – TechnicalAnnexure A.pdf · uploaded 17 Mar 2025Source
  • 1 Disclosure for secured/unsecured finance availed for the projectDisclosure of secured unsecured.pdf · uploaded 17 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Reviesd CA Mangalmurti.pdf · uploaded 22 Mar 2025Source
  • 3 Other – FinanceLandowners Declaration.pdf · uploaded 22 Mar 2025Source
  • 1 Proforma of Agreement for saleRevised AFS.pdf · uploaded 22 Mar 2025Source
  • 2 a Details of encumbrances concerned to Financeencumbrances concerned to Finance.pdf · uploaded 25 Mar 2025Source
  • 2 b Details of encumbrances concerned to Legalencumbrances concerned to Finance.pdf · uploaded 25 Mar 2025Source
  • 2 Deviation Report with respect to model copy of Agreement2 Deviation Report with respect to model copy of Agreement (4) (1).pdf · uploaded 26 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Mangalmurti March 2025.pdf · uploaded 10 May 2025Source
  • 1 Disclosure of sold/ booked inventorySold Unsold Mangalmurti March 2025.pdf · uploaded 10 May 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Mangalmurti March 2025.pdf · uploaded 12 May 2025Source
  • Form 1Form 1 Mangalmurti March 2025.pdf · uploaded 25 Jul 2025Source
  • Form 2Form 2 Mangalmurti March 2025.pdf · uploaded 25 Jul 2025Source
  • Form 3Form 3 Mangalmurti March 2025.pdf · uploaded 25 Jul 2025Source
  • Disclosure of Sold and Booked InventorySold Unsold Mangalmurti March 2025.pdf · uploaded 25 Jul 2025Source
  • Form 1Form1 Mangalmurti June 2025 .pdf · uploaded 28 Jul 2025Source
  • Form 2Form 2 Mangalmurti June 2025 final.pdf · uploaded 28 Jul 2025Source
  • Form 3Form 3 Mangalmurti June 2025.pdf · uploaded 28 Jul 2025Source
  • Disclosure of Sold and Booked InventoryDisclosure of Sold Unsold Mangalmurti June 2025 .pdf · uploaded 28 Jul 2025Source
  • Withdrawal Update Form 1Mangalmurti Form 1 sept 2025.pdf · uploaded 20 Oct 2025Source
  • Withdrawal Update Form 1Mangalmurti Form 1 sept 2025.pdf · uploaded 20 Oct 2025Source
  • Withdrawal Update Form 2Form 2 Mangalmurti.pdf · uploaded 20 Oct 2025Source
  • Withdrawal Update Form 2Form 2 Sept 2025.pdf · uploaded 20 Oct 2025Source
  • Withdrawal Update Form 3Mangalmurti Form 3 Sept 2025.pdf · uploaded 20 Oct 2025Source
  • Withdrawal Update Form 3Mangalmurti Form 3 Sept 2025.pdf · uploaded 20 Oct 2025Source
  • Withdrawal Update Form 1Mangalmurthi Q3 Form 1.pdf · uploaded 21 Jan 2026Source
  • Withdrawal Update Form 2Mangalmurthi Form 2.pdf · uploaded 21 Jan 2026Source
  • Withdrawal Update Form 3Mangalmurthi Form 3.pdf · uploaded 21 Jan 2026Source
  • Withdrawal Update Form 1Mangalmurthi Form 1 Architect Certficate Q4 March 2026.pdf · uploaded 14 Apr 2026Source
  • Withdrawal Update Form 2Mangalmurthi Form 2 Engineer Certificate Q4 March 2026.pdf · uploaded 14 Apr 2026Source
  • Withdrawal Update Form 3Mangalmurthi Form 3 CA Certificate Q4 March 2026.pdf · uploaded 14 Apr 2026Source
  • Withdrawal Update Form 1form 1 june 2026.pdf · uploaded 14 Jul 2026Source
  • Withdrawal Update Form 2form 2 jun2026-27.pdf · uploaded 14 Jul 2026Source
  • Withdrawal Update Form 3form 3 jun2026-27.pdf · uploaded 14 Jul 2026Source
  • Form 2A (FY 2024-2025)form 2A2024-25.pdf · uploaded 18 Jul 2026Source
  • Form 2A (FY 2025-2026)form2 A 2025-26.pdf · uploaded 18 Jul 2026Source

Technical

  • DocumentLayout and Building Drawing Mangalmurti.pdf · uploaded 19 Feb 2025Source
  • DocumentLayout.pdf · uploaded 11 Mar 2025Source
  • Other – TechnicalAnnexure A.pdf · uploaded 17 Mar 2025Source

Technical (Architect)

  • DocumentForm 1 Mangalmurti March 2025.pdf · uploaded 12 May 2025Source
  • Documentform 1 june 2026.pdf · uploaded 13 Jul 2026Source

Technical (Engineer)

  • Documentform 2 jun2026-27.pdf · uploaded 13 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Survey No. 147/4

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 1BHK Landowner, 3BHK Landowner37 units in all
Address
Survey No. 147/4, Adai, AdaiPIN 410206
Village
Adai, Panvel taluka
Land area for this project
1,000 sq m (10,764 sq ft)
Permissible built-up area
1,600 sq m (17,222 sq ft)
Sanctioned built-up area
1,590 sq m (17,114 sq ft)
Recreational open space
250 sq m (2,692 sq ft)
Designated bank account
82
Developed in phases
No

Survey, CTS, gat or plot numbers

Survey No. 147/4

Land as published on MahaRERA's project page

Survey No. 147/4

Boundaries

North
Survey No 147-2
South
Survey No 147-5
East
Survey No147-3
West
9 M wide road and Survey no 146

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking37 units

0 of 37 units booked (0%), as the promoter reported to MahaRERA

1BHK · 20 units1BHK Landowner · 15 units3BHK Landowner · 2 units
TypeCarpet areaUnitsBooked
1BHK29.62 sq m · 319 sq ft30
1BHK29.83 sq m · 321 sq ft30
1BHK29.92 sq m · 322 sq ft30
1BHK30.03 sq m · 323 sq ft30
1BHK30.19 sq m · 325 sq ft30
1BHK30.62 sq m · 330 sq ft20
1BHK31.08 sq m · 335 sq ft20
1BHK31.92 sq m · 344 sq ft10
Show all 15 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
1BHK Landowner29.62 sq m · 319 sq ft20
1BHK Landowner29.83 sq m · 321 sq ft20
1BHK Landowner29.92 sq m · 322 sq ft20
1BHK Landowner30.62 sq m · 330 sq ft30
1BHK Landowner31.08 sq m · 335 sq ft30
1BHK Landowner31.92 sq m · 344 sq ft30
3BHK Landowner63.46 sq m · 683 sq ft20

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMs Sheetal Architect—
Chartered accountantMs CAP & CO—
EngineerMs Shravani Consultants Through Bahubali Dhamane—
EngineerSwapnil Namdev Mhatre—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Adai

All 17 projects in Adai · Compare Mangalmurti with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology