9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects314
Registrations334some projects hold several
Completion still due107227 past their date
Median extension4 months36% of registrations extended
Regulatory cases4on 4 projects

0 deeds a month, 0% of them rentals

Registered sales and rentals, the 24 months to November 2026

Registered sales and rentals by month
MonthSalesRentals
December 202400
January 202500
February 202500
March 202500
April 202500
May 202500
June 202500
July 202500
August 202500
September 202500
October 202500
November 202500
December 202500
January 202600
February 202600
March 202600
April 202600
May 202600
June 202600
July 202600
August 202600
September 202600
October 202610
November 202600

1 sale and 0 rentals in the last 12 months · Source: IGR Maharashtra Index II, registered sale and leave-and-licence deeds

9 in 10 registrations run late here

334 MahaRERA registrations in Wakad

1 completed37 not yet due70 extended, not yet due226 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Wakad

314 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Westgate Business ParkBb Square LLPDue Apr 2030——
P.k.canopusP K GroupDue Jun 2029——
Runaa SaukhyamRunaa HomesDue Jul 2029, extended 4 mo——
Divine Reves, Wing ADivine Homes DevelopersDue Apr 2029, extended 4 mo——
Kohinoor Regalia TowersGodiva Buildcon Private LimitedDue Oct 2030, extended 4 mo——
Pashankar WavesPashankar BuildconDue Dec 2030——
Platinum 9 World TowerPlatinum Associates LLPDue Apr 2032, extended 4 mo——
Pune Wakad ProjectLodha Developers LimitedDue Jun 2031——
Wakad Central ParkShree Venkateshwara GroupDue Apr 2028, extended 4 mo——
Sky SanctumMohar Lifespaces LLPDue Apr 2029, extended 4 mo——
A R MiradorAtlas Royal LivingDue Oct 2029——
AR AmoraA R LivingDue Apr 2027, extended 4 mo——
Anshul Casa K BuildingAnshul Siddhi Promoters And Builders LLPDue Aug 2031, extended 4 mo——
41 CommuneThree Dots RealtyDue Apr 2028, extended 4 mo——
Prime PinnacleViraj Enterprises Through Proprietor Nilesh Shankar WaghmareDue Sep 2027——
Rajveer GarimaWaghere AssociatesDue Apr 2032, extended 4 mo——
Top Towers - BRaga DevelopersDue Nov 2027, extended 4 mo——
Royal AceFive Star Construction CompanyCompleted——
Anp BizsquareFive Star Vighnesh Associates (Aop)Due Nov 2026, extended 4 mo——
Prime NestPro Prime Build LLPDue Oct 2027, extended 4 mo—4%
Kings County Phase - IKing's Marque GroupDue Apr 2028, extended 4 mo—21%
Shubh Swarovski Wing AShubh DevelopersDue Feb 2029, extended 4 mo——
Weone 153Grd Infraprojects Private LimitedDue Apr 2027, extended 4 mo—21%
Kamalraj Athens AKamalraj EstateCompleted—64%
Anshul Casa J BuildingAnshul Siddhi Promoters & Builders LLPDue Aug 2030, extended 4 mo—50%
Wakad market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Five Star Construction Company6 projects
  2. Vikas Vilas Bhalgat6 projects
  3. Kumar Construction And Properties Pvt Ltd5 projects
  4. Vilas Javdekar Eco Shelters Private Limited5 projects
  5. Vilas Javdekar Lifestyle Developers Pvt. Ltd5 projects
  6. Five Star Construction Company4 projects
  7. Paranjape Schemes (Construction) Ltd4 projects
  8. Shiv Developers4 projects
  9. Sunguard Builders Llp4 projects
  10. Grd Infraprojects Private Limited3 projects

Wakad, in questions

How many projects in Wakad run late?

9 in 10 MahaRERA registrations (296 of 334): their completion date was extended or has passed, data through 23 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Wakad by Deedo. Medians on fewer than 3 deeds are not shown.

Latest deal · Resale · Nov 2026

₹50–75 L

Data through22 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology