Residential / Group Housing · 2 buildings · 88 unitsRERA P52100014002 +1

Uttam Townscapes

Deedo IDDP-PUN-7R8W

MahaRERA shows it completed, after its date was pushed back 2 years; no MahaRERA orders on record; 99% of its units are booked.

Vishrantwadi, Pune 411006 · by Fortune Developers And Infrastructures · 33% of its projects kept the RERA date

DeliveryCompletedCompletion / occupancy certificate on MahaRERA · after a 2 yrs extensionRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales99% booked87 of 88 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed, after its date was pushed back 2 years

  • P52100014002Registered 7 Nov 2017, completion promised 31 Dec 2019, revised to 30 Dec 2021.
  • P52100002613Registered 26 Apr 2018, completion promised 31 Aug 2018.

1 extension certificate on record.

2 registrations · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrations2
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000140027 Nov 201731 Dec 201930 Dec 2021Fortune Developers And InfrastructuresProject page
P5210000261326 Apr 201831 Aug 201831 Aug 2018Fortune Developers And InfrastructuresProject page
Documents109

3 documents held by Deedo, 106 filings listed on MahaRERA's project page

Registration certificate (2)

  • Registration certificateP52100014002 · 7 Nov 2017ViewSource
  • Registration certificateP52100002613 · 26 Apr 2018ViewSource

Extension certificate

  • Extension certificateP52100014002 · 9 Sep 2021ViewSource

Finance

  • PAN CardP52100002613 · PAN Card FORTUNE DEVELOPERS.pdf · uploaded 17 Jul 2017Source
  • PAN CardP52100014002 · PAN Card.pdf · uploaded 24 Oct 2017Source

Legal

  • Legal Title reportP52100002613 · legal title report.pdf · uploaded 17 Jul 2017Source
  • Declaration Form BP52100002613 · Declaration in FORM B 1.pdf · uploaded 26 Jul 2017Source
  • Declaration Form BP52100014002 · Declaration in FORM B.pdf · uploaded 24 Oct 2017Source
Show all 109 documentsShow fewer documents

Legal

  • Legal Title reportP52100014002 · Copy of the legal title report.pdf · uploaded 24 Oct 2017Source
  • OtherP52100002613 · Engineers Certificate.pdf · uploaded 25 Dec 2017Source
  • Other – LegalP52100014002 · UT -E3 BUIDING LEGAL.pdf · uploaded 19 Jul 2024Source

Migrated

  • 1 PAN CardP52100002613 · PAN Card FORTUNE DEVELOPERS.pdf · uploaded 17 Jul 2017Source
  • 1 Copy of the legal title reportP52100002613 · legal title report.pdf · uploaded 17 Jul 2017Source
  • 1 Details of encumbrancesP52100002613 · Details of encumbrances.pdf · uploaded 26 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)P52100002613 · Copy of Layout Approval (in case of layout).pdf · uploaded 26 Jul 2017Source
  • 1 Building Plan Approval (IOD)P52100002613 · Building Plan Approval (IOD) 1st2nd.pdf · uploaded 26 Jul 2017Source
  • 2 Building Plan Approval (IOD)P52100002613 · Building Plan 4th.pdf · uploaded 26 Jul 2017Source
  • 3 Building Plan Approval (IOD)P52100002613 · Building Plan Approval (IOD) 8th.pdf · uploaded 26 Jul 2017Source
  • 4 Building Plan Approval (IOD)P52100002613 · Building Plan Approval (IOD) E.pdf · uploaded 26 Jul 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52100002613 · Commencement Certificates 1.pdf · uploaded 26 Jul 2017Source
  • 1 Declaration in FORM BP52100002613 · Declaration in FORM B 1.pdf · uploaded 26 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100002613 · Certificates of Architect (Form 1)(Mandatory for only ongoing project.pdf · uploaded 26 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100002613 · Certificates of Engineer (Form 2)(Mandatory 2.pdf · uploaded 26 Jul 2017Source
  • 1 Certificates of CA (Form 3)P52100002613 · Certificates of CA (Form 3).pdf · uploaded 26 Jul 2017Source
  • 1 Proforma of Allotment letterP52100002613 · Proforma of the allotment letter and agreement for sale.pdf · uploaded 26 Jul 2017Source
  • 1 PAN CardP52100014002 · PAN Card.pdf · uploaded 24 Oct 2017Source
  • 1 Copy of the legal title reportP52100014002 · Copy of the legal title report.pdf · uploaded 24 Oct 2017Source
  • 1 Details of encumbrancesP52100014002 · Details of encumbrances.pdf · uploaded 24 Oct 2017Source
  • 1 Copy of Layout Approval (in case of layout)P52100014002 · Copy of Layout Approval (in case of layout)-ilovepdf-compressed.pdf · uploaded 24 Oct 2017Source
  • 1 Building Plan Approval (IOD)P52100014002 · Building Plan Approval (IOD) 1 TH , 2ND-ilovepdf-compressed.pdf · uploaded 24 Oct 2017Source
  • 2 Building Plan Approval (IOD)P52100014002 · Building Plan Approval (IOD) 4TH ,3TH-ilovepdf-compressed.pdf · uploaded 24 Oct 2017Source
  • 3 Building Plan Approval (IOD)P52100014002 · Building Plan Approval (IOD) 8 TH-ilovepdf-compressed.pdf · uploaded 24 Oct 2017Source
  • 4 Building Plan Approval (IOD)P52100014002 · Building Plan Approval (IOD)-ilovepdf-compressed.pdf · uploaded 24 Oct 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52100014002 · Commencement Certificates-ilovepdf-compressed.pdf · uploaded 24 Oct 2017Source
  • 1 Declaration in FORM BP52100014002 · Declaration in FORM B.pdf · uploaded 24 Oct 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100014002 · Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf · uploaded 24 Oct 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100014002 · Certificates of Engineer (Form 2)(Mandatory for only ongoing project).pdf · uploaded 24 Oct 2017Source
  • 1 Certificates of CA (Form 3)P52100014002 · Certificates of CA (Form 3).pdf · uploaded 24 Oct 2017Source
  • 1 Proforma of Allotment letterP52100014002 · Proforma of the allotment letter and agreement for sale.pdf · uploaded 24 Oct 2017Source
  • 2 Details of encumbrancesP52100002613 · Declaration in FORM B.pdf · uploaded 25 Dec 2017Source
  • 3 Details of encumbrancesP52100002613 · Mortgage Deed (Bajaj Details of encumbrances-2-4 (1).pdf · uploaded 25 Dec 2017Source
  • 1 Certificates of CA (Form 5)P52100002613 · Certificates of CA.pdf · uploaded 25 Dec 2017Source
  • 2 Proforma of Allotment letterP52100002613 · Proforma of the allotment letter and agreement for sale (1).pdf · uploaded 25 Dec 2017Source
  • 1 OtherP52100002613 · Engineers Certificate.pdf · uploaded 25 Dec 2017Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100002613 · Engineer Certificate.pdf · uploaded 23 Mar 2018Source
  • 2 Certificates of CA (Form 5)P52100002613 · CA RERA Certificate-JAN-18 (1).pdf · uploaded 23 Mar 2018Source
  • 3 Proforma of Allotment letterP52100002613 · Proforma of the allotment letter and agreement for sale.pdf · uploaded 24 Mar 2018Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100014002 · Certificates of Engineer.pdf · uploaded 19 May 2018Source
  • 1 Certificates of CA (Form 5)P52100014002 · Certificates of CA.pdf · uploaded 19 May 2018Source
  • 2 Proforma of Allotment letterP52100014002 · Proforma of the allotment letter and agreement for sale.pdf · uploaded 19 May 2018Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100002613 · Architect certificates - E2.pdf · uploaded 22 May 2018Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100002613 · Certificates of Engineer.pdf · uploaded 22 May 2018Source
  • 2 Certificates of CA (Form 3)P52100002613 · Certificates of CA.pdf · uploaded 22 May 2018Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100014002 · Certificates of Engineer.pdf · uploaded 25 May 2018Source
  • 2 Certificates of CA (Form 5)P52100014002 · CERTIFICATE OF CA.pdf · uploaded 25 May 2018Source
  • 1 Status of ConveyanceP52100014002 · SEIAA-STATEMENT-0000000879 (1).pdf · uploaded 16 Aug 2018Source
  • 1 Status of ConveyanceP52100002613 · SEIAA-STATEMENT-0000000879 (1).pdf · uploaded 16 Aug 2018Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100002613 · Certificates of Engineer.pdf · uploaded 31 Aug 2018Source
  • 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100002613 · Certificates of Engineer.pdf · uploaded 31 Aug 2018Source
  • 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100002613 · Certificates of Engineer (Form 2).pdf · uploaded 31 Aug 2018Source
  • 4 Proforma of Allotment letterP52100002613 · Proforma of the allotment letter and agreement for sale.pdf · uploaded 31 Aug 2018Source
  • 3 Certificates of CA (Form 5)P52100014002 · E3 RERA CERTIFICATE (1).pdf · uploaded 15 Oct 2018Source
  • 3 Certificates of CA (Form 5)P52100002613 · E2 Rera certificate (1).pdf · uploaded 15 Oct 2018Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100014002 · Certificates of Engineer.pdf · uploaded 17 Nov 2018Source
  • 2 Certificates of CA (Form 3)P52100014002 · Certificates of CA (Form 3).pdf · uploaded 17 Nov 2018Source
  • 3 Certificates of CA (Form 3)P52100002613 · Certificates of CA (Form 3).pdf · uploaded 17 Nov 2018Source
  • 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100014002 · Certificates of Engineer (Form 2)(Mandatory for only ongoing project).pdf · uploaded 4 Mar 2019Source
  • 3 Certificates of CA (Form 3)P52100014002 · Certificates of CA (Form 3).PDF · uploaded 4 Mar 2019Source
  • 4 Certificates of CA (Form 3)P52100014002 · Certificates of Engineer (Form 2)(Mandatory for only ongoing project).pdf · uploaded 12 Jun 2019Source
  • 5 Certificates of CA (Form 3)P52100014002 · Certificates of CA (Form 3).pdf · uploaded 12 Jun 2019Source
  • 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100014002 · Certificates of Engineer (Form 2)(Mandatory for only ongoing project).pdf · uploaded 30 Sep 2019Source
  • 6 Certificates of CA (Form 3)P52100014002 · Certificates of CA (Form 3).PDF · uploaded 30 Sep 2019Source
  • 4 Certificates of CA (Form 5)P52100014002 · Certificates of CA (Form 5) WING E3.pdf · uploaded 30 Sep 2019Source
  • 4 Certificates of CA (Form 5)P52100002613 · Certificates of CA (Form 5).pdf · uploaded 30 Sep 2019Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100014002 · Completion Certificate.pdf · uploaded 20 Nov 2019Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100014002 · Certificates of Architect.pdf · uploaded 20 Jan 2020Source
  • 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100014002 · Certificates of Engineer.pdf · uploaded 20 Jan 2020Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)P52100014002 · Engineers Certificate on Quality Assurance.pdf · uploaded 20 Jan 2020Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100014002 · Certificates of Architect.pdf · uploaded 19 Mar 2020Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)P52100014002 · Engineers Certificate on Quality Assurance.pdf · uploaded 19 Mar 2020Source
  • 8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100014002 · Certificates of Engineer (Form 2).pdf · uploaded 26 Sep 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)P52100014002 · FDI E3 RERA Form 5 FY 19-20.PDF · uploaded 15 Jan 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)P52100002613 · FDI E3 RERA Form 5 FY 19-20.PDF · uploaded 15 Jan 2021Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)P52100002613 · FDI E2 RERA Form 5 FY 19-20 (1).PDF · uploaded 29 Jan 2021Source
  • 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100014002 · Utam Townscape E3 Building Completion Balance 1 Flat.pdf · uploaded 2 Aug 2021Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)P52100014002 · Uttam E3.pdf · uploaded 2 Aug 2021Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)P52100002613 · Uttam E2.pdf · uploaded 2 Aug 2021Source
  • 6 Architect’s Certificate on Completion of Project (Form 4)P52100014002 · Wing_E3_compressed.pdf · uploaded 3 Aug 2021Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100002613 · Utam Townscape_E2_Building Completion (1).pdf · uploaded 3 Aug 2021Source
  • 5 Architect’s Certificate on Completion of Project (Form 4)P52100002613 · Wing_E2_compressed (1).pdf · uploaded 3 Aug 2021Source
  • 2 Status of ConveyanceP52100014002 · Status Conveyance E3.pdf · uploaded 31 Oct 2022Source
  • 2 Status of ConveyanceP52100002613 · 1 Status of Conveyance.pdf · uploaded 31 Oct 2022Source
  • 3 Status of ConveyanceP52100014002 · Declaration_FDI E3 uttam 4002.pdf · uploaded 17 Apr 2024Source
  • 3 Status of ConveyanceP52100002613 · Declaration_FDI E2 uttam.pdf · uploaded 17 Apr 2024Source
  • 1 Other – LegalP52100014002 · UT -E3 BUIDING LEGAL.pdf · uploaded 19 Jul 2024Source

Technical

  • DocumentP52100002613 · Building Plan 4th.pdf · uploaded 26 Jul 2017Source
  • DocumentP52100002613 · Building Plan Approval (IOD) 8th.pdf · uploaded 26 Jul 2017Source
  • DocumentP52100002613 · Building Plan Approval (IOD) 1st2nd.pdf · uploaded 26 Jul 2017Source
  • DocumentP52100002613 · Building Plan Approval (IOD) E.pdf · uploaded 26 Jul 2017Source
  • DocumentP52100002613 · Copy of Layout Approval (in case of layout).pdf · uploaded 26 Jul 2017Source
  • DocumentP52100014002 · Building Plan Approval (IOD) 1 TH , 2ND-ilovepdf-compressed.pdf · uploaded 24 Oct 2017Source
  • DocumentP52100014002 · Building Plan Approval (IOD) 4TH ,3TH-ilovepdf-compressed.pdf · uploaded 24 Oct 2017Source
  • DocumentP52100014002 · Building Plan Approval (IOD) 8 TH-ilovepdf-compressed.pdf · uploaded 24 Oct 2017Source
  • DocumentP52100014002 · Building Plan Approval (IOD)-ilovepdf-compressed.pdf · uploaded 24 Oct 2017Source
  • DocumentP52100014002 · Copy of Layout Approval (in case of layout)-ilovepdf-compressed.pdf · uploaded 24 Oct 2017Source

Technical (Architect)

  • DocumentP52100002613 · Architect certificates - E2.pdf · uploaded 22 May 2018Source
  • DocumentP52100014002 · Certificates of Architect.pdf · uploaded 19 Mar 2020Source

Technical (Engineer)

  • DocumentP52100002613 · Certificates of Engineer (Form 2).pdf · uploaded 31 Aug 2018Source
  • DocumentP52100014002 · Certificates of Engineer (Form 2).pdf · uploaded 26 Sep 2020Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 2760, 2760

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Phases
1
Unit types
2BHK, 2 BHK88 units in all
Address
2760, Pune, VishrantwadiPIN 400053
Village
Pune (M Corp.), Pune City taluka
Land area for this project
2,388 sq m (25,708 sq ft)
Permissible built-up area
3,188 sq m (34,310 sq ft)
Sanctioned built-up area
3,188 sq m (34,310 sq ft)
Recreational open space
2,916 sq m (31,392 sq ft)
Designated bank account
88
Developed in phases
No

Survey, CTS, gat or plot numbers

27602760

Land as published on MahaRERA's project page

2760

Boundaries

North
Wing F1
South
Wing E2
East
DPRoad but as per notification dt 17 2 18resi zone
West
Central Open Space

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking88 units

87 of 88 units booked (99%), as the promoter reported to MahaRERA

2BHK · 44 units2 BHK · 44 units
RERABuildingTypeCarpet areaUnitsBooked
P52100002613E2 Wing2BHK66.17 sq m · 712 sq ft4241
P52100002613E2 Wing2BHK71.38 sq m · 768 sq ft11
P52100002613E2 Wing2BHK71.52 sq m · 770 sq ft11
P52100014002Wing E32 BHK66.17 sq m · 712 sq ft4242
P52100014002Wing E32 BHK71.52 sq m · 770 sq ft22

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals12

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.RERA
ArchitectPandit Joshi & Associates—P52100014002
ArchitectPandit Joshi & Associates—P52100002613
EngineerSpectrum Consultants—P52100002613
EngineerSpectrum Consultants—P52100014002
OtherApex Consultants—P52100002613
OtherApex Consultants—P52100014002
OtherEmpower Designs Pvt Ltd—P52100002613
OtherEmpower Designs Pvt Ltd—P52100014002
Show all 12 professionalsShow fewer professionals
RoleNameRegistration no.RERA
OtherNeelima Bhosekar—P52100014002
OtherNilima Bhosekar—P52100002613
Registered real estate agentAmit Satpal Gogia—P52100002613
Registered real estate agentVignette Realtors Private Limited—P52100002613

Source: MahaRERA project page. Contact details are not shown.

Other projects in Vishrantwadi

All 3 projects in Vishrantwadi · Compare Uttam Townscapes with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology