RERA projects in Vishrantwadi
3 projects under 4 MahaRERA registrations, registered 2017–2024. 25% have a completion date extended beyond the one promised.
Locality
3RERA projects
4Registrationssome projects hold several
0Completion still due4 past their completion date
24 monthsMedian extension beyond promised date25% of registrations extended
0Regulatory casesnone on MahaRERA's lists
4Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 1 |
| 2018 | 1 |
| 2019 | 1 |
| 2020 | 0 |
| 2021 | 0 |
| 2022 | 0 |
| 2023 | 0 |
| 2024 | 1 |
Projects in Vishrantwadi
3 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Bramha ResidencyD B Realty | P52100055771 | 16 Apr 2024 | 31 Dec 2025 | 31 Dec 2025 | Promised date passed | 0 |
| Tirupati Campus Phase - VIIVenkatesh Constructions | P52100023292 | 9 Dec 2019 | 30 Dec 2023 | 30 Dec 2023 | Promised date passed | 0 |
| Uttam TownscapesFortune Developers And Infrastructures | P52100002613, P52100014002 | 7 Nov 2017 | 31 Dec 2019 | 30 Dec 2021 | Extended 24 mo | 0 |
Other localities in Haveli
Most active promoters
By projects registered here, as named on MahaRERA.
- D B Realty1 project
- Fortune Developers And Infrastructures1 project
- Venkatesh Constructions1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology