Fortune Developers And Infrastructures

Of 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 43 mo late — longer than Maharashtra's 4 mo.

Projects23 RERA registrations
Kept RERA date33%Maharashtra: 73%
Median delay43 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 3 ran past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Uttam TownscapesP52100014002VishrantwadiCertificate Signed31 Dec 201930 Dec 2021+24 mo
Uttam TownscapesP52100002613VishrantwadiCertificate Signed31 Aug 201831 Aug 2018On date
Uttam Townscape Life Hub A,a1,bP52100031569Pune (M Corp.)Certificate Signed30 Oct 202331 Dec 2028+62 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology