Gini Belvista
Deedo IDDP-PUN-G630Completion was pushed back 6 months to Dec 2024, and that date has passed too; no MahaRERA orders on record.
Pune (Cb), Pune 411015 · by Gini Citicorp Realty Llp · 50% of its projects kept the RERA date
Buying a flat here?
See every deed registered on it.
Completion was pushed back 6 months to Dec 2024, and that date has passed too
- P52100018898Registered 11 Dec 2018, completion promised 30 Dec 2023.
- P52100027381Registered 6 Dec 2020, completion promised 30 Jun 2024, revised to 31 Dec 2024, and still not shown completed today.
- P52100032590Registered 14 Jan 2022, completion promised 31 Dec 2025.
1 extension certificate on record.
3 registrations · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
- Primary sale · Oct 2026
- Resale · Sep 2026
- Resale · Aug 2026
- Resale · Aug 2026
- Primary sale · Jul 2026
- Primary sale · Jul 2026
- Primary sale · Jul 2026
- Resale · Jun 2026
- Resale · Jun 2026
- Resale · Feb 2026
| Month | Flat | Kind | Area | Price | Record |
|---|---|---|---|---|---|
| Oct 2026 | Wing A · 104 | Primary sale | 396 sq ft | View Primary sale, Oct 2026 | |
| Sep 2026 | Co-operative · 901Y | Resale | 482 sq ft | View Resale, Sep 2026 | |
| Aug 2026 | F · 408 | Resale | 482 sq ft | View Resale, Aug 2026 | |
| Aug 2026 | F · 401 | Resale | 482 sq ft | View Resale, Aug 2026 | |
| Jul 2026 | F · 408 | Primary sale | 482 sq ft | View Primary sale, Jul 2026 | |
| Jul 2026 | F · 901 | Primary sale | 482 sq ft | View Primary sale, Jul 2026 | |
| Jul 2026 | F · 401 | Primary sale | 482 sq ft | View Primary sale, Jul 2026 | |
| Jun 2026 | Co | Resale | 624 sq ft | View Resale, Jun 2026 | |
| Jun 2026 | Co | Resale | 624 sq ft | View Resale, Jun 2026 | |
| Feb 2026 | B · 112 | Resale | 311 sq ft | View Resale, Feb 2026 |
26 buildings
Open a building to see every flat, floor by floor.
- 1bSize not on record100% booked
- 2bSize not on record100% booked
- 3bSize not on record100% booked
- 4bSize not on record100% booked
- 5bSize not on record100% booked
- 6bSize not on record100% booked
- 7bSize not on record100% booked
- 8bSize not on record100% booked
- 9bSize not on record100% booked
- A13 floors · 101 units91% booked
- B13 floors · 41 units100% booked
- Building (P52100027381)Size not on record98% booked
Show all 26 buildingsShow fewer buildings
- CBuilt13 floors · 103 units9% booked
- C WingSize not on record100% booked
- D14 floors · 79 units100% booked
- E14 floors · 31 units100% booked
- F14 floors · 79 units100% booked
- GBuilt12 floors · 38 units
- G WingSize not on record100% booked
- Wing ASize not on record
- Wing BSize not on record
- Wing CSize not on record
- Wing DSize not on record100% booked
- Wing ESize not on record
- Wing FSize not on record
- Wing GSize not on record
Floors and units from the registration certificate annexures and MahaRERA's project page. Construction % is the average of the developer's own declared activity progress to MahaRERA, not an inspection.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrations3
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100018898 | 11 Dec 2018 | 30 Dec 2023 | 30 Dec 2023 | Gini Citicorp Realty LLP | Project page |
| P52100027381 | 6 Dec 2020 | 30 Jun 2024 | 31 Dec 2024 | Gini Citicorp Realty LLP | Project page |
| P52100032590 | 14 Jan 2022 | 31 Dec 2025 | 31 Dec 2025 | Gini Citicorp Realty LLP | Project page |
Documents368
40 documents held by Deedo, 328 filings listed on MahaRERA's project page
Registration certificate (3)
Building plan (3)
Show all 368 documentsShow fewer documents
Form 1 (7)
Other (13)
- OtherP52100032590 · 13 Aug 2022ViewSource
- OtherP52100032590 · 28 Jan 2023ViewSource
- OtherP52100032590 · 29 Jun 2023ViewSource
- OtherP52100032590 · 3 Feb 2024ViewSource
- OtherP52100032590 · Date not statedViewSource
- OtherP52100027381 · Date not statedView
- OtherP52100032590 · Date not statedView
- OtherP52100032590 · Date not statedViewSource
- OtherP52100032590 · Date not statedViewSource
- OtherP52100032590 · Date not statedViewSource
- OtherP52100032590 · Date not statedViewSource
- OtherP52100032590 · Date not statedViewSource
- OtherP52100032590 · Date not statedViewSource
Form 2 (5)
Form 5 (3)
Occupancy / completion certificate
Document library
- Commencement Certificates / NA Order for plotted developmentP52100032590 · CC.pdf · uploaded 29 Oct 2021View
- Proforma of Allotment letterP52100032590 · PH-III AGREEMENT DRAFT.pdf · uploaded 2 Nov 2021View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100032590 · Belvista 3 Eng Cert_compressed.pdf · uploaded 2 Nov 2021View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100032590 · Form 1 Architect certificate.pdf · uploaded 2 Nov 2021View
- Copy of the legal title reportP52100032590 · Phase 3 Title Report.pdf · uploaded 2 Nov 2021View
- Declaration in FORM BP52100032590 · Form B Gini.pdf · uploaded 25 Nov 2021View
- Copy of Layout Approval (in case of layout)P52100032590 · OLD LAYOUT download.pdf · uploaded 25 Nov 2021View
- Copy of Layout Approval (in case of layout)P52100032590 · 01-01 layout .pdf · uploaded 25 Nov 2021View
- Building Plan Approval / NA Order for plotted developmentP52100032590 · 07-14 C wing Ground Floor .pdf · uploaded 25 Nov 2021View
- Building Plan Approval / NA Order for plotted developmentP52100032590 · 08-14 C Wing 1st Floor .pdf · uploaded 25 Nov 2021View
- Building Plan Approval / NA Order for plotted developmentP52100032590 · 09-14 C wing 2nd Floor .pdf · uploaded 25 Nov 2021View
- Building Plan Approval / NA Order for plotted developmentP52100032590 · 10-14 C WIng odd floors .pdf · uploaded 25 Nov 2021View
- Building Plan Approval / NA Order for plotted developmentP52100032590 · 11-14 C Wing 4 AND 6 Floors .pdf · uploaded 25 Nov 2021View
- Building Plan Approval / NA Order for plotted developmentP52100032590 · 12-14 C Wing 8th Floor .pdf · uploaded 25 Nov 2021View
- Building Plan Approval / NA Order for plotted developmentP52100032590 · 13-14 C Wing Terrace .pdf · uploaded 25 Nov 2021View
- Details of encumbrancesP52100032590 · No Enc.pdf · uploaded 25 Nov 2021View
- Declaration about Commencement CertificateP52100032590 · Comm dec.pdf · uploaded 25 Nov 2021View
- Proforma of Allotment letterP52100032590 · allotment.pdf · uploaded 7 Dec 2021View
- CERSAI detailsP52100032590 · CERSAI_Search_Report_200226377055_For_Asset_Based_Search_22_12_2021_12_50_18_036.pdf · uploaded 24 Dec 2021View
- Commencement Certificates / NA Order for plotted developmentP52100032590 · CC 4148_compressed.pdf · uploaded 6 May 2022View
- Building Plan Approval / NA Order for plotted developmentP52100032590 · G Bldg 1-8th Floor_compressed.pdf · uploaded 6 May 2022View
- Copy of Layout Approval (in case of layout)P52100032590 · Layout _compressed.pdf · uploaded 6 May 2022View
- Disclosure of sold/ booked inventoryP52100032590 · RBelvista Ph 3 Disclosure of inventory form 3.pdf · uploaded 13 Aug 2022View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100032590 · RArch Cert.pdf · uploaded 13 Aug 2022View
- Disclosure of sold/ booked inventoryP52100032590 · RBelvista Ph 3 Disclosure of inventory form 3.pdf · uploaded 13 Aug 2022View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100032590 · Arch Cert Ph 3.pdf · uploaded 27 Sep 2022View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100032590 · Arch Cert Ph 3.pdf · uploaded 27 Sep 2022View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100032590 · Eng Cert Ph 3.pdf · uploaded 27 Sep 2022View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100032590 · Eng Cert Ph 3.pdf · uploaded 27 Sep 2022View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100032590 · ENG CERT P3.pdf · uploaded 28 Sep 2022View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100032590 · ARCH CERT PH 3.pdf · uploaded 28 Sep 2022View
- Disclosure of sold/ booked inventoryP52100032590 · BOOKED INVENTORY (BELVISTA PHASE-3).pdf · uploaded 20 Oct 2022View
- Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)P52100032590 · ANNUAL REPORT 21-22 _CA CERTIFICATE_RERA _ BELVISTA PHASE 3.pdf · uploaded 17 Jan 2023View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100032590 · 2 ENGINEERS CERTIFICATE GB-PHASE-03.pdf · uploaded 18 Jan 2023View
- Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)P52100032590 · 2 ENGINEERS CERTIFICATE GB-PHASE-03.pdf · uploaded 18 Jan 2023View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100032590 · 2 ARCHITECTS CERTIFICATE GB-PHASE-03.pdf · uploaded 18 Jan 2023View
- Disclosure of sold/ booked inventoryP52100032590 · GB PH 3 DISCLOSURE OF INVENTORY.pdf · uploaded 28 Jan 2023View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100032590 · ARCHITECTS CERTIFICATE (GB PH-3).pdf · uploaded 11 Feb 2023View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100032590 · ENGINEERS CERTIFICATE (GB PH-3).pdf · uploaded 11 Feb 2023View
- Disclosure of Interest in Other Real Estate OrganizationsP52100032590 · DISCLOSURE OF SOLD -GB PH 03.pdf · uploaded 20 Apr 2023View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100032590 · GB 03 ARCH MARCH 23.pdf · uploaded 16 May 2023View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100032590 · GB 03 ENG MARCH 23.pdf · uploaded 16 May 2023View
- Disclosure of sold/ booked inventoryP52100032590 · GetUserDocumentFileContent (1).pdf · uploaded 29 Jun 2023View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100032590 · GB 03 ARCH .pdf · uploaded 10 Aug 2023View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100032590 · GB 03 ENG .pdf · uploaded 10 Aug 2023View
- Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)P52100032590 · FORM 5 22-23 (GB-PH-03).pdf · uploaded 27 Jan 2024View
- Disclosure of sold/ booked inventoryP52100032590 · DISCLOSURE OF SOLD BOOKED INVENTORY GINI BELVISTA PH-3_30-06-2023.pdf · uploaded 3 Feb 2024View
- Disclosure of sold/ booked inventoryP52100032590 · DISCLOSURE OF INVENTORY (GB PH-03) Sep 23.pdf · uploaded 3 Feb 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100032590 · GB 03 ARCH SEP 23.pdf · uploaded 3 Feb 2024View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100032590 · GB 03 ENG SEP 23.pdf · uploaded 3 Feb 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100032590 · GB03 ARCH CERT DEC23.pdf · uploaded 3 Feb 2024View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100032590 · GB03 ENG CERT DEC23.pdf · uploaded 3 Feb 2024View
- Disclosure of sold/ booked inventoryP52100032590 · GB03 DISC INVENTORYDec23.pdf · uploaded 3 Feb 2024View
- Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)P52100032590 · Form II A - Gini Belvista Phase-3 -31032023.pdf · uploaded 20 Apr 2024View
- Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P52100032590 · FORM II A - Belvista Phase-3 -31032024.pdf · uploaded 2 May 2024View
- Disclosure of sold/ booked inventoryP52100032590 · GB 03 Q4 23-24 SOLD-UNSOLD.pdf · uploaded 3 May 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100032590 · GB 03 Q4 23-24 ARCH.pdf · uploaded 3 May 2024View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100032590 · GB 03 Q4 23-24 ENG.pdf · uploaded 3 May 2024View
- Disclosure of sold/ booked inventoryP52100032590 · GB 03 SOLD UNSOLDpdf.pdf · uploaded 6 Jul 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100032590 · Gini belvista phase 3.pdf · uploaded 9 Jul 2024View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100032590 · Belvista phase 3.pdf · uploaded 9 Jul 2024View
- Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P52100032590 · Form 2A FY 23-24 signed.pdf · uploaded 17 Jul 2024View
- Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100032590 · Belvista Final OC.pdf · uploaded 10 Oct 2024View
- Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P52100032590 · GB03 FORM 5 23-24.pdf · uploaded 9 Nov 2024View
- Architect’s Certificate on Completion of Project (Form 4)P52100032590 · GB 03 FORM 4.pdf · uploaded 12 Nov 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100032590 · GB03 Form 1 Sep 2024.pdf · uploaded 13 Nov 2024View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100032590 · GB 03 Form 2 Sep 2024.pdf · uploaded 13 Nov 2024View
- Disclosure of sold/ booked inventoryP52100032590 · GB 03 Sold Unsold Sep 24.pdf · uploaded 13 Nov 2024View
Promoter documents
Technical documents
- Layout ApprovalP52100032590 · OLD LAYOUT download.pdfView
- Layout ApprovalP52100032590 · 01-01 layout .pdfView
- Building Plan ApprovalP52100032590 · 07-14 C wing Ground Floor .pdfView
- Building Plan ApprovalP52100032590 · 08-14 C Wing 1st Floor .pdfView
- Building Plan ApprovalP52100032590 · 09-14 C wing 2nd Floor .pdfView
- Building Plan ApprovalP52100032590 · 10-14 C WIng odd floors .pdfView
- Building Plan ApprovalP52100032590 · 11-14 C Wing 4 AND 6 Floors .pdfView
- Building Plan ApprovalP52100032590 · 12-14 C Wing 8th Floor .pdfView
- Building Plan ApprovalP52100032590 · 13-14 C Wing Terrace .pdfView
- Building Plan ApprovalP52100032590 · G Bldg 1-8th Floor_compressed.pdfView
- Layout ApprovalP52100032590 · Layout _compressed.pdfView
Proforma allotment letter
- Proforma allotment letterP52100032590 · PH-III AGREEMENT DRAFT.pdfView
Finance
Legal
- OtherP52100018898 · Belvista EC Order-compressed.pdf · uploaded 28 Nov 2018Source
- Declaration Form BP52100018898 · B Form LLP Belvista.pdf · uploaded 3 Dec 2018Source
- Legal Title reportP52100018898 · Search 04-12-2018.pdf · uploaded 4 Dec 2018Source
- Legal Title reportP52100027381 · BELVISTA SEARCH REPORT2.pdf · uploaded 6 Nov 2020Source
- Declaration Form BP52100027381 · FORM B.pdf · uploaded 24 Nov 2020Source
- OtherP52100027381 · EC.pdf · uploaded 2 Dec 2020Source
- Declaration Form BP52100027381 · Form B.pdf · uploaded 9 Jul 2024Source
Migrated
- 1 PAN CardP52100018898 · LLP pancard.pdf · uploaded 20 Nov 2018Source
- 1 Proforma of Allotment letterP52100018898 · Allotment Letter.pdf · uploaded 20 Nov 2018Source
- 1 Details of encumbrancesP52100018898 · No Enc Cert Belvista.pdf · uploaded 27 Nov 2018Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100018898 · Eng Certificate Gini Belvista.pdf · uploaded 27 Nov 2018Source
- 1 Copy of Layout Approval (in case of layout)P52100018898 · Old Layout Colour.pdf · uploaded 28 Nov 2018Source
- 1 Building Plan Approval (IOD)P52100018898 · A Second and Fourth Floor.pdf · uploaded 28 Nov 2018Source
- 2 Building Plan Approval (IOD)P52100018898 · A Basement Floor.pdf · uploaded 28 Nov 2018Source
- 3 Building Plan Approval (IOD)P52100018898 · A Eighth Floor.pdf · uploaded 28 Nov 2018Source
- 4 Building Plan Approval (IOD)P52100018898 · A Fifth Seventh Ninth Floor.pdf · uploaded 28 Nov 2018Source
- 5 Building Plan Approval (IOD)P52100018898 · A First Floor_A.pdf · uploaded 28 Nov 2018Source
- 6 Building Plan Approval (IOD)P52100018898 · A Ground Floor.pdf · uploaded 28 Nov 2018Source
- 7 Building Plan Approval (IOD)P52100018898 · A Sixth Floor.pdf · uploaded 28 Nov 2018Source
- 8 Building Plan Approval (IOD)P52100018898 · A Third Floor.pdf · uploaded 28 Nov 2018Source
- 9 Building Plan Approval (IOD)P52100018898 · ClubHouse.pdf · uploaded 28 Nov 2018Source
- 10 Building Plan Approval (IOD)P52100018898 · E 2-4-6-3-5-7-9.pdf · uploaded 28 Nov 2018Source
- 11 Building Plan Approval (IOD)P52100018898 · E Basement Ground First.pdf · uploaded 28 Nov 2018Source
- 12 Building Plan Approval (IOD)P52100018898 · E Eighth Floor.pdf · uploaded 28 Nov 2018Source
- 13 Building Plan Approval (IOD)P52100018898 · F 1st Floor.pdf · uploaded 28 Nov 2018Source
- 14 Building Plan Approval (IOD)P52100018898 · F 2-4-6.pdf · uploaded 28 Nov 2018Source
- 15 Building Plan Approval (IOD)P52100018898 · F 3-5-7-9.pdf · uploaded 28 Nov 2018Source
- 16 Building Plan Approval (IOD)P52100018898 · F 8th.pdf · uploaded 28 Nov 2018Source
- 17 Building Plan Approval (IOD)P52100018898 · F Ground and Basement.pdf · uploaded 28 Nov 2018Source
- 18 Building Plan Approval (IOD)P52100018898 · Layout New.pdf · uploaded 28 Nov 2018Source
- 1 Commencement Certificates / NA Order for plotted developmentP52100018898 · CC.pdf · uploaded 28 Nov 2018Source
- 1 OtherP52100018898 · Belvista EC Order-compressed.pdf · uploaded 28 Nov 2018Source
- 1 Certificates of CA (Form 3)P52100018898 · Gini Belvista_Form 3_Certified.pdf · uploaded 29 Nov 2018Source
- 1 Declaration in FORM BP52100018898 · B Form LLP Belvista.pdf · uploaded 3 Dec 2018Source
- 1 Copy of the legal title reportP52100018898 · Search 04-12-2018.pdf · uploaded 4 Dec 2018Source
- 2 Proforma of Allotment letterP52100018898 · 04-12-2018 RERA GINI Belvista final.pdf · uploaded 4 Dec 2018Source
- 1 Form 2AP52100018898 · Form 2A Dec18.pdf · uploaded 9 Jan 2019Source
- 2 Form 2AP52100018898 · Form 2A Eng Quality Asuurance Cert Q1 19-20.pdf · uploaded 18 Jul 2019Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)P52100018898 · FORM 5 CA 1819.pdf · uploaded 23 Nov 2019Source
- 3 Form 2AP52100018898 · Form 2A Eng Quality Asuurance Cert Q3 19-20.pdf · uploaded 26 Feb 2020Source
- 4 Form 2AP52100018898 · Form 2A Eng Quality Asuurance Cert Q4 18-19.pdf · uploaded 27 Feb 2020Source
- 5 Form 2AP52100018898 · Form 2A Eng Quality Asuurance Cert Q2 19-20.pdf · uploaded 27 Feb 2020Source
- 1 PAN CardP52100027381 · LLP pancard.pdf · uploaded 28 Oct 2020Source
- 1 Details of encumbrancesP52100027381 · NoEncumbCert.pdf · uploaded 5 Nov 2020Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027381 · Belvists PhaseII Form2 Eng.pdf · uploaded 5 Nov 2020Source
- 1 Details of Restarting of Construction work post lockdownP52100018898 · Belvista Restart Letter.pdf · uploaded 5 Nov 2020Source
- 1 Copy of the legal title reportP52100027381 · BELVISTA SEARCH REPORT2.pdf · uploaded 6 Nov 2020Source
- 1 Proforma of Allotment letterP52100027381 · PH-II AGREEMENT DRAFT FOR RERA.pdf · uploaded 6 Nov 2020Source
- 2 Proforma of Allotment letterP52100027381 · Revised Allotment.pdf · uploaded 6 Nov 2020Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027381 · GINI Belvista II CA CERT.pdf · uploaded 11 Nov 2020Source
- 1 Declaration in FORM BP52100027381 · FORM B.pdf · uploaded 24 Nov 2020Source
- 1 Copy of Layout Approval (in case of layout)P52100027381 · LAYOUT P2.pdf · uploaded 28 Nov 2020Source
- 1 Building Plan Approval / NA Order for plotted developmentP52100027381 · 1-34.pdf · uploaded 2 Dec 2020Source
- 2 Building Plan Approval / NA Order for plotted developmentP52100027381 · 2-34.pdf · uploaded 2 Dec 2020Source
- 3 Building Plan Approval / NA Order for plotted developmentP52100027381 · 3-34.pdf · uploaded 2 Dec 2020Source
- 4 Building Plan Approval / NA Order for plotted developmentP52100027381 · 4-34.pdf · uploaded 2 Dec 2020Source
- 5 Building Plan Approval / NA Order for plotted developmentP52100027381 · 5-34.pdf · uploaded 2 Dec 2020Source
- 6 Building Plan Approval / NA Order for plotted developmentP52100027381 · 6-34.pdf · uploaded 2 Dec 2020Source
- 7 Building Plan Approval / NA Order for plotted developmentP52100027381 · 7-34.pdf · uploaded 2 Dec 2020Source
- 8 Building Plan Approval / NA Order for plotted developmentP52100027381 · 8-34.pdf · uploaded 2 Dec 2020Source
- 9 Building Plan Approval / NA Order for plotted developmentP52100027381 · 9-34.pdf · uploaded 2 Dec 2020Source
- 10 Building Plan Approval / NA Order for plotted developmentP52100027381 · 10-34.pdf · uploaded 2 Dec 2020Source
- 11 Building Plan Approval / NA Order for plotted developmentP52100027381 · 11-34.pdf · uploaded 2 Dec 2020Source
- 12 Building Plan Approval / NA Order for plotted developmentP52100027381 · 12-34.pdf · uploaded 2 Dec 2020Source
- 13 Building Plan Approval / NA Order for plotted developmentP52100027381 · 13-34.pdf · uploaded 2 Dec 2020Source
- 14 Building Plan Approval / NA Order for plotted developmentP52100027381 · 14-34.pdf · uploaded 2 Dec 2020Source
- 15 Building Plan Approval / NA Order for plotted developmentP52100027381 · 15-34.pdf · uploaded 2 Dec 2020Source
- 16 Building Plan Approval / NA Order for plotted developmentP52100027381 · 16-34.pdf · uploaded 2 Dec 2020Source
- 17 Building Plan Approval / NA Order for plotted developmentP52100027381 · 17-34.pdf · uploaded 2 Dec 2020Source
- 18 Building Plan Approval / NA Order for plotted developmentP52100027381 · 18-34.pdf · uploaded 2 Dec 2020Source
- 19 Building Plan Approval / NA Order for plotted developmentP52100027381 · 19-34.pdf · uploaded 2 Dec 2020Source
- 20 Building Plan Approval / NA Order for plotted developmentP52100027381 · 20-34.pdf · uploaded 2 Dec 2020Source
- 21 Building Plan Approval / NA Order for plotted developmentP52100027381 · 21-34.pdf · uploaded 2 Dec 2020Source
- 22 Building Plan Approval / NA Order for plotted developmentP52100027381 · 22-34.pdf · uploaded 2 Dec 2020Source
- 23 Building Plan Approval / NA Order for plotted developmentP52100027381 · 23-34.pdf · uploaded 2 Dec 2020Source
- 24 Building Plan Approval / NA Order for plotted developmentP52100027381 · 24-34.pdf · uploaded 2 Dec 2020Source
- 25 Building Plan Approval / NA Order for plotted developmentP52100027381 · 25-34.pdf · uploaded 2 Dec 2020Source
- 26 Building Plan Approval / NA Order for plotted developmentP52100027381 · 26-34.pdf · uploaded 2 Dec 2020Source
- 27 Building Plan Approval / NA Order for plotted developmentP52100027381 · 27-34.pdf · uploaded 2 Dec 2020Source
- 28 Building Plan Approval / NA Order for plotted developmentP52100027381 · 28-34.pdf · uploaded 2 Dec 2020Source
- 29 Building Plan Approval / NA Order for plotted developmentP52100027381 · 29-34.pdf · uploaded 2 Dec 2020Source
- 30 Building Plan Approval / NA Order for plotted developmentP52100027381 · 30-34.pdf · uploaded 2 Dec 2020Source
- 31 Building Plan Approval / NA Order for plotted developmentP52100027381 · 31-34.pdf · uploaded 2 Dec 2020Source
- 32 Building Plan Approval / NA Order for plotted developmentP52100027381 · 32-34.pdf · uploaded 2 Dec 2020Source
- 33 Building Plan Approval / NA Order for plotted developmentP52100027381 · 33-34.pdf · uploaded 2 Dec 2020Source
- 34 Building Plan Approval / NA Order for plotted developmentP52100027381 · 34-34.pdf · uploaded 2 Dec 2020Source
- 1 Commencement Certificates / NA Order for plotted developmentP52100027381 · SKM_C25820120217250.pdf · uploaded 2 Dec 2020Source
- 1 OtherP52100027381 · EC.pdf · uploaded 2 Dec 2020Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P52100018898 · Eng Cert Form II PhaseI 310321.pdf · uploaded 21 Jun 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)P52100018898 · ANNAL REPORT 19-20.pdf · uploaded 14 Jul 2021Source
- 1 Disclosure of sold/ booked inventoryP52100027381 · Belvista Ph-II Disclouser of inventory form 3.pdf · uploaded 19 Jul 2021View
- 1 Disclosure of sold/ booked inventoryP52100018898 · Belvista Disclouser of inventory form 3.pdf · uploaded 19 Jul 2021Source
- 2 Disclosure of sold/ booked inventoryP52100027381 · OCT 2021 DISCLOSURE INVENTORY PH I PH II.pdf · uploaded 7 Oct 2021Source
- 2 Disclosure of sold/ booked inventoryP52100018898 · Oct 2021 PH I PDF.pdf · uploaded 7 Oct 2021Source
- 35 Building Plan Approval / NA Order for plotted developmentP52100027381 · 01-14 Layout .pdf · uploaded 25 Nov 2021Source
- 36 Building Plan Approval / NA Order for plotted developmentP52100027381 · 03-14 B wing Ground AND 1st Floor .pdf · uploaded 25 Nov 2021Source
- 37 Building Plan Approval / NA Order for plotted developmentP52100027381 · 04-14 B wing Odd AND Even .pdf · uploaded 25 Nov 2021Source
- 38 Building Plan Approval / NA Order for plotted developmentP52100027381 · 05-14 b wing 8th Floor .pdf · uploaded 25 Nov 2021Source
- 2 Commencement Certificates / NA Order for plotted developmentP52100027381 · CC.pdf · uploaded 25 Nov 2021Source
- 3 Disclosure of sold/ booked inventoryP52100027381 · DEC 2021 PH II PDF.pdf · uploaded 4 Jan 2022Source
- 3 Disclosure of sold/ booked inventoryP52100018898 · DEC 2021 PH I PDF.pdf · uploaded 4 Jan 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027381 · RArch cert.pdf · uploaded 13 Aug 2022Source
- 4 Disclosure of sold/ booked inventoryP52100027381 · RBelvista Ph 2 Disclosure of inventory form 3.pdf · uploaded 13 Aug 2022Source
- 5 Disclosure of sold/ booked inventoryP52100027381 · RBelvista Ph 2 Disclosure of inventory form 3.pdf · uploaded 13 Aug 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)P52100018898 · GINI BELVISTA.pdf · uploaded 29 Aug 2022Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027381 · Arch Cert Ph 2.pdf · uploaded 27 Sep 2022Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027381 · Arch Cert Ph 2.pdf · uploaded 27 Sep 2022Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027381 · Eng Cert Ph2.pdf · uploaded 27 Sep 2022Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P52100027381 · Eng Cert Ph 2.pdf · uploaded 27 Sep 2022Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027381 · CA Cert Ph 2.pdf · uploaded 27 Sep 2022Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027381 · CA Cert Ph 2_compressed.pdf · uploaded 27 Sep 2022Source
- 6 Disclosure of sold/ booked inventoryP52100027381 · BOOKED INVENTORY (BELVISTA PHASE II).pdf · uploaded 20 Oct 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)P52100027381 · ANNUAL REPORT 21-22 _CA CERTIFICATE_RERA _ BELVISTA PHASE II.pdf · uploaded 17 Jan 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)P52100018898 · ANNUAL REPORT 21-22 _CA CERTIFICATE_RERA _ BELVISTA PHASE I.pdf · uploaded 17 Jan 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027381 · ARCHITECT CERTIFICATE.pdf · uploaded 18 Jan 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027381 · ENGINEERS CERTIFICATE.pdf · uploaded 18 Jan 2023Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027381 · CHARTERED ACCOUNTANTS CERTIFICATE.pdf · uploaded 18 Jan 2023Source
- 2 Certificates of CA (Form 3)P52100018898 · FORM 3 CA CERT 310719.pdf · uploaded 18 Jan 2023Source
- 3 Certificates of CA (Form 3)P52100018898 · 3 - Rera Certificate.pdf · uploaded 18 Jan 2023Source
- 4 Certificates of CA (Form 3)P52100018898 · 4 - Rera Certificate.pdf · uploaded 18 Jan 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)P52100027381 · Form 5_RERA Belvista Phase -II_FY20-21.pdf · uploaded 21 Jan 2023Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)P52100018898 · Form 5_RERA Belvista Phase -I_FY20-21.pdf · uploaded 21 Jan 2023Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027381 · ARCHITECTS CERTIFICATE GB-PH-II.pdf · uploaded 27 Jan 2023Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027381 · ENGINEERS CERTIFICATE GB-PH-II.pdf · uploaded 27 Jan 2023Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027381 · CHARTERED ACCOUNTANTS CERTIFICATE GB-PH-II.pdf · uploaded 27 Jan 2023Source
- 7 Disclosure of sold/ booked inventoryP52100027381 · DEC 2021 PH II PDF.pdf · uploaded 28 Jan 2023Source
- 8 Disclosure of sold/ booked inventoryP52100027381 · DEC 2021 PH II PDF.pdf · uploaded 28 Jan 2023Source
- 9 Disclosure of sold/ booked inventoryP52100027381 · GB PH-II DISCLOSURE OF INVENTORY .pdf · uploaded 28 Jan 2023Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100018898 · COMPLETION OC.pdf · uploaded 28 Jan 2023Source
- 4 Architect’s Certificate on Completion of Project (Form 4)P52100018898 · FORM 4 ARCH COMPLETION.pdf · uploaded 10 Mar 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100018898 · 210222.pdf · uploaded 13 Mar 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100018898 · 300522.pdf · uploaded 13 Mar 2023Source
- 10 Disclosure of sold/ booked inventoryP52100027381 · DISCLOSURE OF SOLD -GB PH II.pdf · uploaded 20 Apr 2023Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027381 · GB 02 ARCH MARCH 23.pdf · uploaded 16 May 2023Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027381 · GB O2 ENG MARCH23.pdf · uploaded 16 May 2023Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027381 · GB 02 CA MARCH 23_compressed.pdf · uploaded 16 May 2023Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)P52100018898 · PPhase 1 Society registration certificate .pdf · uploaded 17 Jan 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)P52100027381 · FORM 5 22-23 (GB-PH-II).pdf · uploaded 27 Jan 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)P52100018898 · FORM 5 22-23 (GB-PH-01).pdf · uploaded 27 Jan 2024Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027381 · GB02 ARCH CERT SEP 23.pdf · uploaded 3 Feb 2024Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027381 · GB02 ARCH CERT DEC23.pdf · uploaded 3 Feb 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027381 · GB02 ENG CERT SEP 23.pdf · uploaded 3 Feb 2024Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027381 · GB02 ENG CERT DEC 23.pdf · uploaded 3 Feb 2024Source
- 11 Disclosure of sold/ booked inventoryP52100027381 · DISCLOSURE OF SOLD BOOKED INVENTORY GBelvista PH-2_30-06-2023.pdf · uploaded 3 Feb 2024Source
- 12 Disclosure of sold/ booked inventoryP52100027381 · DISCLOSURE OF INVENTORY (GB PH-II) Sep23.pdf · uploaded 3 Feb 2024Source
- 13 Disclosure of sold/ booked inventoryP52100027381 · GB02 DISC INVENTORY DEC23.pdf · uploaded 3 Feb 2024Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027381 · GB02 CA CERT SEP 23_compressed (1).pdf · uploaded 3 Feb 2024Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027381 · GB02 CA CERT DEC 23_compressed Signed.pdf · uploaded 3 Feb 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)P52100027381 · Form II A - Gini Belvista phase-2 -31032023.pdf · uploaded 20 Apr 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P52100027381 · FORM II A - Belvista Phase-2 -31032024.pdf · uploaded 2 May 2024Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027381 · GB 02 Q4 23-24 ENG.pdf · uploaded 4 May 2024Source
- 14 Disclosure of sold/ booked inventoryP52100027381 · GB 02 Q4 23-24 SOLD-UNSOLD.pdf · uploaded 4 May 2024Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027381 · GB 02 Q4 23-24 CA_compressed.pdf · uploaded 4 May 2024Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027381 · GB 02 Q4 23-24 ARCH New.pdf · uploaded 23 May 2024Source
- 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027381 · form 3 june 2024_compressed.pdf · uploaded 4 Jul 2024Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027381 · Form2 Belvista ph2- 30062024.pdf · uploaded 6 Jul 2024Source
- 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027381 · GB02 Form 2 Jun24.pdf · uploaded 6 Jul 2024Source
- 15 Disclosure of sold/ booked inventoryP52100027381 · sold unsold.pdf · uploaded 6 Jul 2024Source
- 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027381 · GB 02 CA CERT Q1 24-25 Compressed.pdf · uploaded 6 Jul 2024Source
- 2 Declaration in FORM BP52100027381 · Form B.pdf · uploaded 9 Jul 2024Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027381 · GB02 FORM 1 JUNE 24.pdf · uploaded 15 Jul 2024Source
- 2 Copy of Layout Approval (in case of layout)P52100027381 · 1-34_2_11zon.pdf · uploaded 18 Jul 2024Source
- 3 Copy of Layout Approval (in case of layout)P52100027381 · 01-01 layout _1_11zon.pdf · uploaded 18 Jul 2024Source
- 4 Copy of Layout Approval (in case of layout)P52100027381 · HPSCANNER7274_3_11zon.pdf · uploaded 18 Jul 2024Source
- 5 Copy of Layout Approval (in case of layout)P52100027381 · 11zon_rotated-PDF.pdf · uploaded 18 Jul 2024Source
- 1 Declaration about Commencement CertificateP52100027381 · Declaration of cc.pdf · uploaded 18 Jul 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027381 · GB 02 Form 1 Sep 24.pdf · uploaded 13 Nov 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027381 · GB 02 Form 3 Sep 24.pdf · uploaded 13 Nov 2024Source
- 1 Disclosure of sold/ booked inventoryP52100027381 · GB 02 Sold Unsold Sep 24.pdf · uploaded 13 Nov 2024View
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100018898 · GV01 Form 1 Sep 2024.pdf · uploaded 13 Nov 2024Source
- 1 Certificates of CA (Form 3)P52100018898 · GV01 Form 3 Sep 2024.pdf · uploaded 13 Nov 2024Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100018898 · GV01 Form 2 Sep 24.pdf · uploaded 13 Nov 2024Source
- 1 Disclosure of sold/ booked inventoryP52100018898 · GV 01 Sold Unsold Sep 24.pdf · uploaded 13 Nov 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P52100027381 · GB02 FORM 5 23-24.pdf · uploaded 10 Feb 2025Source
Technical
- DocumentP52100018898 · Old Layout Colour.pdf · uploaded 28 Nov 2018Source
- DocumentP52100018898 · A Second and Fourth Floor.pdf · uploaded 28 Nov 2018Source
- DocumentP52100018898 · A Basement Floor.pdf · uploaded 28 Nov 2018Source
- DocumentP52100018898 · A Eighth Floor.pdf · uploaded 28 Nov 2018Source
- DocumentP52100018898 · A Fifth Seventh Ninth Floor.pdf · uploaded 28 Nov 2018Source
- DocumentP52100018898 · A First Floor_A.pdf · uploaded 28 Nov 2018Source
- DocumentP52100018898 · A Ground Floor.pdf · uploaded 28 Nov 2018Source
- DocumentP52100018898 · A Sixth Floor.pdf · uploaded 28 Nov 2018Source
- DocumentP52100018898 · A Third Floor.pdf · uploaded 28 Nov 2018Source
- DocumentP52100018898 · ClubHouse.pdf · uploaded 28 Nov 2018Source
- DocumentP52100018898 · E 2-4-6-3-5-7-9.pdf · uploaded 28 Nov 2018Source
- DocumentP52100018898 · E Basement Ground First.pdf · uploaded 28 Nov 2018Source
- DocumentP52100018898 · E Eighth Floor.pdf · uploaded 28 Nov 2018Source
- DocumentP52100018898 · F 1st Floor.pdf · uploaded 28 Nov 2018Source
- DocumentP52100018898 · F 2-4-6.pdf · uploaded 28 Nov 2018Source
- DocumentP52100018898 · F 3-5-7-9.pdf · uploaded 28 Nov 2018Source
- DocumentP52100018898 · F 8th.pdf · uploaded 28 Nov 2018Source
- DocumentP52100018898 · F Ground and Basement.pdf · uploaded 28 Nov 2018Source
- DocumentP52100018898 · Layout New.pdf · uploaded 28 Nov 2018Source
- DocumentP52100027381 · LAYOUT P2.pdf · uploaded 28 Nov 2020Source
- DocumentP52100027381 · 1-34.pdf · uploaded 2 Dec 2020Source
- DocumentP52100027381 · 2-34.pdf · uploaded 2 Dec 2020Source
- DocumentP52100027381 · 3-34.pdf · uploaded 2 Dec 2020Source
- DocumentP52100027381 · 4-34.pdf · uploaded 2 Dec 2020Source
- DocumentP52100027381 · 5-34.pdf · uploaded 2 Dec 2020Source
- DocumentP52100027381 · 6-34.pdf · uploaded 2 Dec 2020Source
- DocumentP52100027381 · 7-34.pdf · uploaded 2 Dec 2020Source
- DocumentP52100027381 · 8-34.pdf · uploaded 2 Dec 2020Source
- DocumentP52100027381 · 9-34.pdf · uploaded 2 Dec 2020Source
- DocumentP52100027381 · 10-34.pdf · uploaded 2 Dec 2020Source
- DocumentP52100027381 · 11-34.pdf · uploaded 2 Dec 2020Source
- DocumentP52100027381 · 12-34.pdf · uploaded 2 Dec 2020Source
- DocumentP52100027381 · 13-34.pdf · uploaded 2 Dec 2020Source
- DocumentP52100027381 · 14-34.pdf · uploaded 2 Dec 2020Source
- DocumentP52100027381 · 15-34.pdf · uploaded 2 Dec 2020Source
- DocumentP52100027381 · 16-34.pdf · uploaded 2 Dec 2020Source
- DocumentP52100027381 · 17-34.pdf · uploaded 2 Dec 2020Source
- DocumentP52100027381 · 18-34.pdf · uploaded 2 Dec 2020Source
- DocumentP52100027381 · 19-34.pdf · uploaded 2 Dec 2020Source
- DocumentP52100027381 · 20-34.pdf · uploaded 2 Dec 2020Source
- DocumentP52100027381 · 21-34.pdf · uploaded 2 Dec 2020Source
- DocumentP52100027381 · 22-34.pdf · uploaded 2 Dec 2020Source
- DocumentP52100027381 · 23-34.pdf · uploaded 2 Dec 2020Source
- DocumentP52100027381 · 24-34.pdf · uploaded 2 Dec 2020Source
- DocumentP52100027381 · 25-34.pdf · uploaded 2 Dec 2020Source
- DocumentP52100027381 · 26-34.pdf · uploaded 2 Dec 2020Source
- DocumentP52100027381 · 27-34.pdf · uploaded 2 Dec 2020Source
- DocumentP52100027381 · 28-34.pdf · uploaded 2 Dec 2020Source
- DocumentP52100027381 · 29-34.pdf · uploaded 2 Dec 2020Source
- DocumentP52100027381 · 30-34.pdf · uploaded 2 Dec 2020Source
- DocumentP52100027381 · 31-34.pdf · uploaded 2 Dec 2020Source
- DocumentP52100027381 · 32-34.pdf · uploaded 2 Dec 2020Source
- DocumentP52100027381 · 33-34.pdf · uploaded 2 Dec 2020Source
- DocumentP52100027381 · 34-34.pdf · uploaded 2 Dec 2020Source
- DocumentP52100027381 · 01-14 Layout .pdf · uploaded 25 Nov 2021Source
- DocumentP52100027381 · 03-14 B wing Ground AND 1st Floor .pdf · uploaded 25 Nov 2021Source
- DocumentP52100027381 · 04-14 B wing Odd AND Even .pdf · uploaded 25 Nov 2021Source
- DocumentP52100027381 · 05-14 b wing 8th Floor .pdf · uploaded 25 Nov 2021Source
- DocumentP52100027381 · 1-34_2_11zon.pdf · uploaded 18 Jul 2024Source
- DocumentP52100027381 · 01-01 layout _1_11zon.pdf · uploaded 18 Jul 2024Source
- DocumentP52100027381 · HPSCANNER7274_3_11zon.pdf · uploaded 18 Jul 2024Source
- DocumentP52100027381 · 11zon_rotated-PDF.pdf · uploaded 18 Jul 2024Source
- OthersP52100027381 · Belvista Final OC.pdf · uploaded 19 Sep 2024Source
Technical (Architect)
- DocumentP52100027381 · Form1 - Bevista Phase 3.pdf · uploaded 18 Sep 2024Source
- DocumentP52100018898 · Form 1 Belvista.pdf · uploaded 24 Sep 2024Source
- DocumentP52100027381 · GB 02 Form 1 Sep 24.pdf · uploaded 13 Nov 2024Source
- DocumentP52100018898 · GV01 Form 1 Sep 2024.pdf · uploaded 13 Nov 2024Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel S NO 11/1 PART, S NO 11/1 PART
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Phases
- 3
- Unit types
- 2.5 BHK, 2BHK, Shop, 3BHK, 2.5BHK, 2BHK TYPE 1, 2BHK TYPE 2472 units in all
- Address
- S No 11/1 Part, Near Porwal Road, Parande ParkPIN 411015
- Village
- Dhanori
- Location
- 18.60972, 73.90333
- Land area for this project
- 6,825 sq m (73,460 sq ft)
- Permissible built-up area
- 15,045 sq m (1,61,940 sq ft)
- Sanctioned built-up area
- 15,045 sq m (1,61,940 sq ft)
- Recreational open space
- 2,020 sq m (21,744 sq ft)
- Designated bank account
- 109
- Developed in phases
- Yes
- Also registered as
- Gini Belvista - Phase I, Gini Belvista - Phase II, Gini Belvista Phase 3, Gini Belavhista, गिनी बेलव्हिस्टा
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
S NO 11/1 PART
Boundaries
- North
- 18 Mtr Dp Road
- South
- S No 11 Part
- East
- S No 10
- West
- 18 Mtr Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking472 units · 107 parking spaces
331 of 472 units booked (70%), as the promoter reported to MahaRERA
| RERA | Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|---|
| P52100018898 | A | 2.5 BHK | 73.01 sq m · 786 sq ft | 15 | 15 |
| P52100018898 | A | 2BHK | 51.02 sq m · 549 sq ft | 35 | 35 |
| P52100018898 | A | 2BHK | 57.97 sq m · 624 sq ft | 35 | 35 |
| P52100018898 | A | Shop | 25.39 sq m · 273 sq ft | 2 | 2 |
| P52100018898 | A | Shop | 30.2 sq m · 325 sq ft | 4 | 3 |
| P52100018898 | A | Shop | 35.86 sq m · 386 sq ft | 2 | 1 |
| P52100018898 | A | Shop | 36.76 sq m · 396 sq ft | 2 | 0 |
| P52100018898 | A | Shop | 38.27 sq m · 412 sq ft | 2 | 1 |
Show all 41 unit rowsShow fewer unit rows
| RERA | Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|---|
| P52100018898 | A | Shop | 43.03 sq m · 463 sq ft | 2 | 0 |
| P52100018898 | A | Shop | 45.3 sq m · 488 sq ft | 2 | 0 |
| P52100027381 | B | 2BHK | 57.97 sq m · 624 sq ft | 33 | 33 |
| P52100027381 | B | Shop | 35.49 sq m · 382 sq ft | 4 | 4 |
| P52100027381 | B | Shop | 39.03 sq m · 420 sq ft | 4 | 4 |
| P52100032590 | C | 2BHK | 51.02 sq m · 549 sq ft | 35 | — |
| P52100032590 | C | 2BHK | 57.96 sq m · 624 sq ft | 35 | — |
| P52100032590 | C | 3BHK | 73.01 sq m · 786 sq ft | 15 | — |
| P52100027381 | C | Shop | 27.63 sq m · 297 sq ft | 2 | 1 |
| P52100027381 | C | Shop | 30.2 sq m · 325 sq ft | 6 | 4 |
| P52100027381 | C | Shop | 35.49 sq m · 382 sq ft | 2 | 1 |
| P52100027381 | C | Shop | 36.76 sq m · 396 sq ft | 1 | 0 |
| P52100027381 | C | Shop | 39.03 sq m · 420 sq ft | 2 | 1 |
| P52100027381 | C | Shop | 43.42 sq m · 467 sq ft | 2 | 1 |
| P52100027381 | C | Shop | 44.55 sq m · 480 sq ft | 2 | 0 |
| P52100027381 | C | Shop | 51.02 sq m · 549 sq ft | 1 | 1 |
| P52100027381 | D | 2.5BHK | 51.02 sq m · 549 sq ft | 7 | 7 |
| P52100027381 | D | 2.5BHK | 73.01 sq m · 786 sq ft | 8 | 8 |
| P52100027381 | D | 2BHK | 51.02 sq m · 549 sq ft | 24 | 24 |
| P52100027381 | D | 2BHK | 57.97 sq m · 624 sq ft | 30 | 30 |
| P52100027381 | D | 2BHK | 73.01 sq m · 786 sq ft | 10 | 10 |
| P52100018898 | E | 2BHK | 57.97 sq m · 624 sq ft | 31 | 31 |
| P52100018898 | F | 2.5BHK | 73.01 sq m · 786 sq ft | 15 | 15 |
| P52100018898 | F | 2BHK TYPE 1 | 51.02 sq m · 549 sq ft | 32 | 32 |
| P52100018898 | F | 2BHK TYPE 2 | 57.97 sq m · 624 sq ft | 32 | 32 |
| P52100032590 | G | 3BHK | 74.36 sq m · 800 sq ft | 16 | — |
| P52100032590 | G | 3BHK | 75.28 sq m · 810 sq ft | 16 | — |
| P52100032590 | G | Shop | 42.81 sq m · 461 sq ft | 1 | — |
| P52100032590 | G | Shop | 61.45 sq m · 661 sq ft | 1 | — |
| P52100032590 | G | Shop | 65.32 sq m · 703 sq ft | 1 | — |
| P52100032590 | G | Shop | 69.35 sq m · 746 sq ft | 1 | — |
| P52100032590 | G | Shop | 70.93 sq m · 763 sq ft | 1 | — |
| P52100032590 | G | Shop | 94.68 sq m · 1,019 sq ft | 1 | — |
Parking
| Building | Type | Two-wheeler | Four-wheeler | Bus | Visitor | Total |
|---|---|---|---|---|---|---|
| C | Closed/Covered | 0 | 0 | 0 | 0 | 85 |
| C | Open Space | 0 | 0 | 0 | 0 | 0 |
| G | Closed/Covered | 0 | 0 | 0 | 0 | 22 |
| G | Open Space | 0 | 0 | 0 | 0 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Construction progress3 buildings and areas
Work completed, as the promoter reported it to MahaRERA (Form 1)
C
Show all 11 activitiesShow fewer activities
G
Show all 11 activitiesShow fewer activities
Common areas and amenities
Show all 15 activitiesShow fewer activities
Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.
Other projects in Pune (Cb)
- Casa SaptakRERA PR1260002601278
- The OasisRERA P52100079748
- Shree AartiRERA P52100077623
- Kumar Samruddhi A6 and A7 Building₹7,880 a sq ft
- Sparkle Splendor₹7,210 a sq ft
- Kumar Primrose C BuildingRERA P52100030114
- NakshatraRERA P52100029163
- Jewel SquareRERA P52100025970
All 21 projects in Pune (Cb) · Compare Gini Belvista with another project
Gini Belvista in numbers
Registered deals, summarised
Deedo has 1,110 registered documents at Gini Belvista, from Feb 2019 to Oct 2026: 516 sales, 307 leave and licence agreements, 273 mortgages. The median registered sale since Feb 2019 works out to about ₹7,900 per sq ft, at a median of ₹45 L a deal; 6% of sales were resales.
- What is the price per sq ft at Gini Belvista?
- The median registered sale since Feb 2019 works out to about ₹7,900 per sq ft, at a median of ₹45 L a deal; 6% of sales were resales.
- How many properties have been sold at Gini Belvista?
- 516 sales are registered at Gini Belvista, 32 of them resales.
- Are properties at Gini Belvista rented out?
- Yes: 307 leave and licence agreements are registered at Gini Belvista, at a median rent since Feb 2019 of about ₹20,000 a month with a deposit of about ₹40,000.
- Where does this data come from?
- The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at Gini Belvista by Deedo, last updated with deals registered in Oct 2026.
Latest deal · Primary sale · Oct 2026