Company or firm · first RERA registration 2017
Gini Citicorp Realty Llp
Deedo IDDD-ZPM1Of 4 registrations whose promised date has arrived, 2 kept it (50%). The rest ran a median 4 mo late.
Projects68 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay4 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
5 registrations of 8 ran past the RERA date
Months late against the original RERA promise, per registration
8 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Gini Viviana F Bldg Phase 2P52100000983 | Baner | Certificate Signed | 31 Mar 2018 | 31 Mar 2019 | +12 mo |
| Gini BelvistaP52100018898 | Dhanori | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| Gini BelvistaP52100027381 | Dhanori | Certificate Signed | 30 Jun 2024 | 31 Dec 2024 | +28 mo* |
| Gini BelvistaP52100032590 | Dhanori | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | On date |
| Gini Vivante Phase 01P52100034447 | Haveli | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
| Gini VibranceP52100048895 | Kivale | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
| Gini Vivante Phase 02P52100050601 | Kiwale | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
| Gini Vivante Phase 03P52100078531 | Kiwale | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology