RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52100027381

Gini Belvista · Pune (Cb), Pune · Gini Citicorp Realty Llp

Promised for 30 Jun 2024, extended once to 31 Dec 2024 — and that date has passed without the project marked complete on MahaRERA.

2 years and 5 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Jun 2024 to 31 Dec 2024 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 Dec 2024, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 3

Registration certificate8 Sep 2021View
Extension certificate29 Jul 2024View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P52100027381

Is Gini Belvista delayed?

Yes. MahaRERA records a promised completion of 30 Jun 2024, revised to 31 Dec 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100027381. The completion date moved from 30 Jun 2024 to 31 Dec 2024.

Who is the promoter?

MahaRERA records Gini Citicorp Realty Llp as the promoter of P52100027381.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100027381.