The Oasis
Deedo IDDP-PUN-WESACompletion was pushed back 4 months to Jul 2026, and that date has passed too; no MahaRERA orders on record; 0% of its units are booked.
Pune (Cb), Pune 411001 · by Mahavir Investments
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months to Jul 2026, and that date has passed too
- This projectRegistered 24 Mar 2025, completion promised 31 Mar 2026, revised to 31 Jul 2026, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100079748
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100079748 | 24 Mar 2025 | 31 Mar 2026 | 31 Jul 2026 | Mahavir Investments | Project page |
Documents41
1 document held by Deedo, 40 filings listed on MahaRERA's project page
Finance
- PAN Cardpan card mahavir investment.pdf · uploaded 23 Dec 2024Source
Legal
- Legal Title reportTitle Sachapir.pdf · uploaded 25 Dec 2024Source
- Declaration Form BAffidavit mahavir investments.pdf · uploaded 26 Dec 2024Source
- Other – LegalDeclaration cum undertaking Annexure A.pdf · uploaded 17 Jan 2025Source
- Other – LegalGLR Sachapir.pdf · uploaded 30 Jan 2025Source
- Other – Legalsale deed 1 to 49_11zon.pdf · uploaded 3 Feb 2025Source
- Other – Legalsale deed mahaveer Investment_11zon (5).pdf · uploaded 18 Mar 2025Source
Show all 41 documentsShow fewer documents
Legal
- Other – Legalindex 2 mahaveer Investment (1).pdf · uploaded 18 Mar 2025Source
Migrated
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 FOR RERA REGISTRATION.pdf · uploaded 12 Nov 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 FOR RERA REGISTRATION.pdf · uploaded 19 Nov 2024Source
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 27 Nov 2024Source
- 1 PAN Cardpan card mahavir investment.pdf · uploaded 23 Dec 2024Source
- 1 a Details of encumbrances concerned to FinanceDetails of encumbrances.pdf · uploaded 23 Dec 2024Source
- 1 Declaration about Commencement CertificateDeclaration about Commencment certificate.pdf · uploaded 23 Dec 2024Source
- 1 b Details of encumbrances concerned to LegalDetails of encumbrances.pdf · uploaded 23 Dec 2024Source
- 1 Copy of the legal title reportTitle Sachapir.pdf · uploaded 25 Dec 2024Source
- 1 Proforma of Allotment letterRERA Allotment letter final.pdf · uploaded 26 Dec 2024Source
- 1 Declaration in FORM BAffidavit mahavir investments.pdf · uploaded 26 Dec 2024Source
- 1 Deviation Report with respect to Allotment letterallotment deviation.pdf · uploaded 26 Dec 2024Source
- 1 Deviation Report with respect to model copy of Agreementagreement deviation (2).pdf · uploaded 26 Dec 2024Source
- 1 Disclosure of Interest in Other Real Estate Organizationsannexure A(Disclosure of interest in other real estate organization)Sunil -2.pdf · uploaded 26 Dec 2024Source
- 2 Disclosure of Interest in Other Real Estate Organizations(annexure) A (disclosure of interest in other real estate organisation).pdf · uploaded 26 Dec 2024Source
- 1 Copy of Layout Approval (in case of layout)SANCTION SHEET.pdf · uploaded 30 Dec 2024Source
- 1 Building Plan Approval / NA Order for plotted developmentSANCTION SHEET.pdf · uploaded 30 Dec 2024Source
- 1 CERSAI details1 CERSAI details.pdf · uploaded 9 Jan 2025Source
- 1 Disclosure for secured/unsecured finance availed for the project1 Disclosure for secured_unsecured finance availed for the project.pdf · uploaded 9 Jan 2025Source
- 1 Other – LegalDeclaration cum undertaking Annexure A.pdf · uploaded 17 Jan 2025Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)Format A Declaration about RERA Designated Bank Account.pdf · uploaded 17 Jan 2025Source
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)declaration about rera designated bank account format B.pdf · uploaded 17 Jan 2025Source
- 1 Proforma of Agreement for saleRERA AGREEMENT.pdf · uploaded 27 Jan 2025Source
- 2 Other – LegalGLR Sachapir.pdf · uploaded 30 Jan 2025Source
- 3 Other – Legalsale deed 1 to 49_11zon.pdf · uploaded 3 Feb 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Mahvir Investment - Form 3.pdf · uploaded 27 Feb 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Mahvir Investment - Form 3.pdf · uploaded 27 Feb 2025Source
- 5 Other – Legalindex 2 mahaveer Investment (1).pdf · uploaded 18 Mar 2025Source
- 4 Other – Legalsale deed mahaveer Investment_11zon (5).pdf · uploaded 18 Mar 2025Source
Technical
Technical (Architect)
- DocumentFORM 1 FOR RERA REGISTRATION.pdf · uploaded 12 Nov 2024Source
Technical (Engineer)
- DocumentFORM 2 FOR RERA REGISTRATION.pdf · uploaded 19 Nov 2024Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 390/ 914
As registered with MahaRERA and published on its project page
- Project type
- Commercial
- Status on MahaRERA
- Certificate Signed
- Unit types
- Office space, Shop14 units in all
- Address
- 390/ 914, Sachapir Street, CampPIN 411001
- Village
- Pune (CB), Pune City taluka
- Land area for this project
- 1,248 sq m (13,432 sq ft)
- Permissible built-up area
- 1,237 sq m (13,310 sq ft)
- Sanctioned built-up area
- 1,237 sq m (13,310 sq ft)
- Recreational open space
- 0 sq m (0 sq ft)
- Designated bank account
- 85
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
390/ 914
Boundaries
- North
- Dp Road
- South
- Nala
- East
- Sm Chowksi School
- West
- Andhra Bank
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking14 units
0 of 14 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Office space | 52.25 sq m · 562 sq ft | 1 | 0 |
| Office space | 61.63 sq m · 663 sq ft | 2 | 0 |
| Office space | 61.69 sq m · 664 sq ft | 1 | 0 |
| Office space | 61.91 sq m · 666 sq ft | 1 | 0 |
| Office space | 73 sq m · 786 sq ft | 1 | 0 |
| Office space | 77.33 sq m · 832 sq ft | 2 | 0 |
| Office space | 77.82 sq m · 838 sq ft | 1 | 0 |
| Office space | 83 sq m · 893 sq ft | 1 | 0 |
Show all 12 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Office space | 104 sq m · 1,119 sq ft | 1 | 0 |
| Shop | 227.49 sq m · 2,449 sq ft | 1 | 0 |
| Shop | 303.37 sq m · 3,265 sq ft | 1 | 0 |
| Shop | 310.31 sq m · 3,340 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals5
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Zakir Hiroli | — |
| Chartered accountant | Payal Agarwal | — |
| Engineer | Nandkumar Patil | — |
| Other | Adv Jayesh H Jain | — |
| Other | ADV ROSHNI PRAVIN OSWAL Pravin Oswal | — |
Source: MahaRERA project page. Contact details are not shown.