Residential / Group Housing · 4 buildings · 11 unitsRERA P52100049485

Siddhi Apartment

Deedo IDDP-PUN-TQ3F

Its promised completion date, Jul 2024, has passed and MahaRERA does not show it completed; no MahaRERA orders on record.

Pimple Nilakh, Pune 411027 · Property rates in Pimple Nilakh · by Mak Developers

Delivery2 yrs 4 mo past duePromised Jul 2024 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readPrice₹6,740 /sq ft29.8% below Pimple Nilakh · 111 registered sales

Buying a flat here?

See every deed registered on it.

Its promised completion date, Jul 2024, has passed and MahaRERA does not show it completed

  • This projectRegistered 15 Feb 2023, completion promised 31 Jul 2024, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

All 918 deeds →
Latest registered deeds in this project
MonthFlatKindAreaPriceRecord
Jul 2026Main building · 202Resale500 sq ftView Resale, Jul 2026
Jun 2026Main building · 201Primary sale883 sq ftView Primary sale, Jun 2026
Jun 2026Main building · 202Primary sale500 sq ftView Primary sale, Jun 2026
May 2026Main building · 202Primary sale646 sq ftView Primary sale, May 2026
Feb 2026Unit 301Resale876 sq ftView Resale, Feb 2026
Feb 2026Main building · 202Primary sale—View Primary sale, Feb 2026
Feb 2026Main building · 302Primary sale646 sq ftView Primary sale, Feb 2026
Feb 2026Main building · 102Primary sale646 sq ftView Primary sale, Feb 2026
Sep 2025Unit 202Primary sale495 sq ftView Primary sale, Sep 2025
Aug 2025Main building · 402Primary sale646 sq ftView Primary sale, Aug 2025

4 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100049485
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210004948515 Feb 202331 Jul 202431 Jul 2024Mak DevelopersProject page
Documents41

2 documents held by Deedo, 39 filings listed on MahaRERA's project page

Registration certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardDamji V Makwana Pan Card.pdf · uploaded 10 Dec 2022Source
  • PAN CardEncumbrance letter (2).pdf · uploaded 13 Feb 2023Source

Legal

  • Legal Title reportFormat A (4).pdf · uploaded 10 Dec 2022Source
  • Declaration Form BForm B.pdf · uploaded 10 Dec 2022Source
  • Legal Title reports no 29 - Search And Title_compressed.pdf · uploaded 10 Dec 2022Source

Migrated

  • 1 PAN CardDamji V Makwana Pan Card.pdf · uploaded 10 Dec 2022Source
Show all 41 documentsShow fewer documents

Migrated

  • 1 Copy of the legal title reportFormat A (4).pdf · uploaded 10 Dec 2022Source
  • 2 Copy of the legal title reports no 29 - Search And Title_compressed.pdf · uploaded 10 Dec 2022Source
  • 1 a Details of encumbrances concerned to FinanceEncumbrance letter.pdf · uploaded 10 Dec 2022Source
  • 1 b Details of encumbrances concerned to LegalEncumbrance letter.pdf · uploaded 10 Dec 2022Source
  • 1 Copy of Layout Approval (in case of layout)HPSC0833 (1)_compressed (1).pdf · uploaded 10 Dec 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentHPSC0833 (1)_compressed (1).pdf · uploaded 10 Dec 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentSKMBT_C36022110213290_compressed.pdf · uploaded 10 Dec 2022Source
  • 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 10 Dec 2022Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 10 Dec 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 (2).pdf · uploaded 10 Dec 2022Source
  • 1 CERSAI detailsCERSAI_Search_Report_200254457031_For_Asset_Based_Search_10_12_2022_16_25_31_667.pdf · uploaded 10 Dec 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Revise form 3_compressed (1).pdf · uploaded 10 Dec 2022Source
  • 1 Proforma of Allotment letterModel form of Allotment letter.pdf · uploaded 10 Dec 2022Source
  • 1 Proforma of Agreement for saleAS PER JAIN - Agree Makwana Pimple Nilakh 29 Rera Std (2).pdf · uploaded 10 Dec 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A Bank.pdf · uploaded 10 Dec 2022Source
  • 1 Deviation Report with respect to Allotment letterDeviation of Allotment letter.pdf · uploaded 10 Dec 2022Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation of Agreement to sale.pdf · uploaded 10 Dec 2022Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A.pdf · uploaded 11 Jan 2023Source
  • 2 PAN CardEncumbrance letter (2).pdf · uploaded 13 Feb 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect Certificate.pdf · uploaded 31 May 2023Source
  • 1 Disclosure of sold/ booked inventorySOLD unsold.pdf · uploaded 31 May 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)F1 june 2023.pdf · uploaded 17 Jun 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Siddhi Apartment F2.pdf · uploaded 20 Jun 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)RERA FORM-3 (SIDDHI APARTMENT)_compressed.pdf · uploaded 24 Jun 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A.pdf · uploaded 4 Jul 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)qu sep siddhi apt 23.pdf · uploaded 9 Oct 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)SIDDHI APARTMENT-1_compressed.pdf · uploaded 25 Oct 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)IMG_20231010_114722 (2).pdf · uploaded 1 Nov 2023Source
  • 2 Disclosure of sold/ booked inventorySold Unsold.pdf · uploaded 2 Nov 2023View

Technical

  • DocumentHPSC0833 (1)_compressed (1).pdf · uploaded 10 Dec 2022Source
  • DocumentHPSC0833 (1)_compressed (1).pdf · uploaded 10 Dec 2022Source

Technical (Architect)

  • DocumentIMG_20231010_114722 (2).pdf · uploaded 1 Nov 2023Source

Technical (Engineer)

  • Documentqu sep siddhi apt 23.pdf · uploaded 9 Oct 2023Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Sr No 29/1/1/1/2/2/1 (P)

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
2BHK11 units in all
Address
Sr No 29/1/1/1/2/2/1 (P), Pimple Nilakh, Pimple NilakhPIN 411027
Village
Pimple Nilakh, Haveli taluka
Land area for this project
400 sq m (4,306 sq ft)
Permissible built-up area
640 sq m (6,887 sq ft)
Sanctioned built-up area
640 sq m (6,887 sq ft)
Designated bank account
190
Developed in phases
No
Also registered as
सिद्धी अपार्टमेंट, वैष्णवी अपार्टमेंट, Manasi, Manasi Apartment, Manasi Apartments, Siddhi, Vaishnavi Apartment, Mansi, Mansi Apartment, Tanush Apartment, Madhura Apartment, Midas Apartment, Midas Apt, Riddhi Apartment, Suryoday Apartment, Suryoday Apartments, Suryoday, Smruddhi Apartment, Ridhi Apartment, Aksha Apartment, Punyodaya Apartment, Punyodaya, Aditya, Aditya Apartment

Survey, CTS, gat or plot numbers

Sr No 29/1/1/1/2/2/1 (P)

Land as published on MahaRERA's project page

Sr No 29/1/1/1/2/2/1 (P)

Boundaries

North
Gopal Krishna Society
South
Property of Mr Sahebrao Sopanrao Nandgudfe
East
Defense Military Road
West
Internal 6 M Wide Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking11 units

0 of 11 units booked (0%), as the promoter reported to MahaRERA

2BHK · 11 units
TypeCarpet areaUnitsBooked
2BHK33.58 sq m · 361 sq ft100
2BHK44.72 sq m · 481 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAr N D Joshi—
Chartered accountantCA Pravin Pise & Associates—
EngineerMr Umesh Jadhav—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Pimple Nilakh

All 1,039 projects in Pimple Nilakh · Compare Siddhi Apartment with another project

Siddhi Apartment in numbers

Registered deals, summarised

Deedo has 917 registered documents at Siddhi Apartment, from Jan 2015 to Oct 2026: 111 sales, 644 leave and licence agreements, 56 mortgages. The median registered sale since Jan 2015 works out to about ₹6,700 per sq ft, at a median of ₹37 L a deal; 32% of sales were resales.

What is the price per sq ft at Siddhi Apartment?
The median registered sale since Jan 2015 works out to about ₹6,700 per sq ft, at a median of ₹37 L a deal; 32% of sales were resales.
How many properties have been sold at Siddhi Apartment?
111 sales are registered at Siddhi Apartment, 35 of them resales.
Are properties at Siddhi Apartment rented out?
Yes: 644 leave and licence agreements are registered at Siddhi Apartment, at a median rent since Jan 2015 of about ₹16,000 a month with a deposit of about ₹40,000.
Where does this data come from?
The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at Siddhi Apartment by Deedo, last updated with deals registered in Oct 2026.

Latest deal · Resale · Jul 2026

₹25–50 L