Charuhas
Deedo IDDP-PUN-SKHHCompletion was pushed back 9 months to May 2025, and that date has passed too; no MahaRERA orders on record.
Kothrud, Pune 411038 · Property rates in Kothrud · by Joshi Buildcon Landmarks · 0% of its projects kept the RERA date
Buying a flat here?
See every deed registered on it.
Completion was pushed back 9 months to May 2025, and that date has passed too
- This projectRegistered 11 Oct 2021, completion promised 31 Aug 2024, revised to 31 May 2025, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
- Resale · May 2026
- Primary sale · Jan 2026
- Primary sale · Dec 2025
- Primary sale · Jul 2025
- Primary sale · Jun 2025No amount
- Primary sale · Jun 2025No amount
- Primary sale · Apr 2025
- Primary sale · Apr 2025
- Primary sale · Mar 2025
- Primary sale · Mar 2025
| Month | Flat | Kind | Area | Price | Record |
|---|---|---|---|---|---|
| May 2026 | Unit 501 | Resale | 728 sq ft | View Resale, May 2026 | |
| Jan 2026 | Unit 1202 | Primary sale | 728 sq ft | View Primary sale, Jan 2026 | |
| Dec 2025 | Unit 1201 | Primary sale | 728 sq ft | View Primary sale, Dec 2025 | |
| Jul 2025 | Unit 1101 | Primary sale | 728 sq ft | View Primary sale, Jul 2025 | |
| Jun 2025 | Unit 65 | Primary sale | 930 sq ft | View Primary sale, Jun 2025 | |
| Jun 2025 | Unit 65 | Primary sale | 890 sq ft | View Primary sale, Jun 2025 | |
| Apr 2025 | Unit 1001 | Primary sale | 728 sq ft | View Primary sale, Apr 2025 | |
| Apr 2025 | Unit 1002 | Primary sale | 728 sq ft | View Primary sale, Apr 2025 | |
| Mar 2025 | Unit 801 | Primary sale | 728 sq ft | View Primary sale, Mar 2025 | |
| Mar 2025 | Unit 603 | Primary sale | 1,185 sq ft | View Primary sale, Mar 2025 |
2 buildings
Open a building to see every flat, floor by floor.
- Main buildingSize not on record81% booked
- Charuhas Co Operative Society12 floors · 47 units74% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100031203
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100031203 | 11 Oct 2021 | 31 Aug 2024 | 31 May 2025 | Joshi Buildcon Landmarks | Project page |
Documents84
3 documents held by Deedo, 81 filings listed on MahaRERA's project page
Other
- OtherDate not statedView
Finance
Show all 84 documentsShow fewer documents
Legal
- Declaration Form BCharuhas RERA Affidavit.pdf · uploaded 5 Aug 2024Source
Migrated
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect's Certificate_CHARUHAS.PDF · uploaded 1 Sep 2021Source
- 1 PAN CardJoshi Buildcon Landmarks PAN.pdf · uploaded 2 Sep 2021Source
- 1 Details of encumbrancesCharuhas Encumbrances.pdf · uploaded 2 Sep 2021Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's Certificate _Charuhas.pdf · uploaded 2 Sep 2021Source
- 1 Proforma of Allotment letterAllotment Deed-draft-Charuhas.pdf · uploaded 2 Sep 2021Source
- 2 Proforma of Allotment letterExtra Area Agreement-draft-Charuhas.pdf · uploaded 2 Sep 2021Source
- 1 Copy of Layout Approval (in case of layout)Sanctioned Plans.pdf · uploaded 17 Sep 2021Source
- 1 Declaration in FORM BFORM B.pdf · uploaded 17 Sep 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 FINAL_Charuhas.pdf · uploaded 18 Sep 2021Source
- 1 Copy of the legal title reportTitle search report Charuhas.pdf · uploaded 29 Sep 2021Source
- 1 Commencement Certificates / NA Order for plotted developmentCHARUHAS COMMENCEMENT.pdf · uploaded 4 Oct 2021Source
- 1 Declaration about Commencement CertificateDeclaration _CC_ Charuhas.pdf · uploaded 4 Oct 2021Source
- 2 Copy of the legal title reportCHARUHAS_Title Search As per Format A_RERA.pdf · uploaded 5 Oct 2021Source
- 1 Building Plan Approval / NA Order for plotted development1 Copy of Layout Approval (in case of layout).pdf · uploaded 5 Oct 2021Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect's Certificate_CHARUHAS_24-01-2023.pdf · uploaded 21 Apr 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Enigineer’s Certificate_CHARUHAS_24-01-2023.pdf · uploaded 21 Apr 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Charuhas_Form 3_Signed_March 2022_compressed.pdf · uploaded 21 Apr 2023Source
- 1 Other – FinanceCharuhas_Form 3_Signed_March 2022_compressed.pdf · uploaded 21 Apr 2023Source
- 1 Other – TechnicalForm 1 Architect's Certificate_CHARUHAS_24-01-2023.pdf · uploaded 21 Apr 2023Source
- 2 Other – TechnicalForm 2 Enigineer’s Certificate_CHARUHAS_24-01-2023.pdf · uploaded 21 Apr 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Charuhas_Form 5_Signed_March 2022.pdf · uploaded 24 Apr 2023Source
- 3 Other – TechnicalLetter_MahaRERA_25-04-2023.pdf · uploaded 25 Apr 2023Source
- 1 Proforma of Agreement for saleAgreement for sale.pdf · uploaded 6 Jun 2023Source
- 2 a Details of encumbrances concerned to FinanceLegal encumbrance details.pdf · uploaded 9 Jun 2023Source
- 1 b Details of encumbrances concerned to LegalLegal encumbrance details.pdf · uploaded 9 Jun 2023Source
- 1 CERSAI detailsCERSAI declaration.pdf · uploaded 9 Jun 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsOther organization disclosure.pdf · uploaded 9 Jun 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank acc declaration.pdf · uploaded 9 Jun 2023Source
- 1 Deviation Report with respect to Allotment letterDeviation Allotment Letter.pdf · uploaded 9 Jun 2023Source
- 1 Deviation Report with respect to model copy of AgreementDeviations Agreement for Sale.pdf · uploaded 9 Jun 2023Source
- 1 Disclosure of sold/ booked inventorySold Inventory.pdf · uploaded 27 Jun 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Charuhas-Form 2A -110422.pdf · uploaded 1 Aug 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Charuhas - Form 2A-100423.pdf · uploaded 1 Aug 2023Source
- 2 Disclosure of sold/ booked inventoryCharuhas-Disclosure of Sold booked inventary.pdf · uploaded 11 Aug 2023Source
- 3 Disclosure of sold/ booked inventorySold Inventory-Charuhas-Dec 23.pdf · uploaded 5 Dec 2023Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)Society Reg Certificate.pdf · uploaded 2 Jan 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 -Charuhas.pdf · uploaded 19 Mar 2024Source
- 4 Disclosure of sold/ booked inventorysold inventory charuhas Apr 24.pdf · uploaded 10 May 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A Charuhas.pdf · uploaded 17 May 2024Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Charuhas (2A).pdf · uploaded 21 May 2024Source
- 5 Disclosure of sold/ booked inventorySold-unsold flats.pdf · uploaded 2 Jul 2024Source
- 4 Other – TechnicalAnnexure A.pdf · uploaded 2 Jul 2024Source
- 2 Commencement Certificates / NA Order for plotted developmentRevised_CC 2024.pdf · uploaded 1 Aug 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 2 Aug 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 2 Aug 2024Source
- 2 Declaration in FORM BCharuhas RERA Affidavit.pdf · uploaded 5 Aug 2024Source
- 2 Building Plan Approval / NA Order for plotted developmentScan_3982-01.pdf · uploaded 6 Aug 2024Source
- 3 Building Plan Approval / NA Order for plotted developmentScan_3982-02.pdf · uploaded 6 Aug 2024Source
- 4 Building Plan Approval / NA Order for plotted developmentScan_3982-03.pdf · uploaded 6 Aug 2024Source
- 5 Building Plan Approval / NA Order for plotted developmentScan_3982-04.pdf · uploaded 6 Aug 2024Source
- 6 Building Plan Approval / NA Order for plotted developmentScan_3982-05.pdf · uploaded 6 Aug 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CHARUHAS RERA FORM 3.pdf · uploaded 12 Aug 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Charuhas Form 5 .pdf · uploaded 12 Aug 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Charuhas.pdf · uploaded 13 Aug 2024Source
- Form 5 (FY 2022-2023)Charuhas Form 5 .pdf · uploaded 27 Sep 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 17 Oct 2024Source
- 1 Disclosure of sold/ booked inventorycharuhas sold unsold inventory .pdf · uploaded 28 Jan 2025Source
- Form 1Form 1 July 24.pdf · uploaded 29 Aug 2025Source
- Form 2Form 2 -Jul 24.pdf · uploaded 29 Aug 2025Source
- Form 3Form 3 July 24.pdf · uploaded 29 Aug 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of sold_ booked inventory July 24.pdf · uploaded 29 Aug 2025View
Technical
- DocumentSanctioned Plans.pdf · uploaded 17 Sep 2021Source
- Document1 Copy of Layout Approval (in case of layout).pdf · uploaded 5 Oct 2021Source
- Other – TechnicalForm 1 Architect's Certificate_CHARUHAS_24-01-2023.pdf · uploaded 21 Apr 2023Source
- Other – TechnicalForm 2 Enigineer’s Certificate_CHARUHAS_24-01-2023.pdf · uploaded 21 Apr 2023Source
- Other – TechnicalLetter_MahaRERA_25-04-2023.pdf · uploaded 25 Apr 2023Source
- Other – TechnicalAnnexure A.pdf · uploaded 2 Jul 2024Source
- DocumentScan_3982-01.pdf · uploaded 6 Aug 2024Source
- DocumentScan_3982-02.pdf · uploaded 6 Aug 2024Source
- DocumentScan_3982-03.pdf · uploaded 6 Aug 2024Source
- DocumentScan_3982-04.pdf · uploaded 6 Aug 2024Source
- DocumentScan_3982-05.pdf · uploaded 6 Aug 2024Source
Technical (Architect)
Technical (Engineer)
- DocumentForm 2 Charuhas.pdf · uploaded 27 Sep 2024Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 850
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, 3BHK, 4BHK47 units in all
- Address
- 850, Paud Road, KothrudPIN 411038
- Village
- Kothrud, Haveli taluka
- Location
- 18.52043, 73.85674
- Land area for this project
- 1,164 sq m (12,529 sq ft)
- Permissible built-up area
- 2,910 sq m (31,323 sq ft)
- Sanctioned built-up area
- 2,910 sq m (31,323 sq ft)
- Recreational open space
- 1,164 sq m (12,529 sq ft)
- Designated bank account
- 119
- Developed in phases
- No
- Also registered as
- मिळकतीमधील चारूहास, Milakatimadhil Charuhas
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
850
Boundaries
- North
- 15m Wide Road
- South
- 9m Wide Road
- East
- PUSHPANJALI CHS Ltd
- West
- SHIVANAND CHS Ltd
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking47 units
35 of 47 units booked (74%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 50.71 sq m · 546 sq ft | 1 | 1 |
| 2BHK | 66.97 sq m · 721 sq ft | 1 | 0 |
| 2BHK | 70.96 sq m · 764 sq ft | 6 | 6 |
| 2BHK | 70.96 sq m · 764 sq ft | 1 | 0 |
| 2BHK | 70.97 sq m · 764 sq ft | 1 | 1 |
| 2BHK | 70.98 sq m · 764 sq ft | 3 | 3 |
| 2BHK | 71.01 sq m · 764 sq ft | 1 | 1 |
| 2BHK | 71.44 sq m · 769 sq ft | 7 | 0 |
Show all 23 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 72.46 sq m · 780 sq ft | 1 | 1 |
| 2BHK | 74.31 sq m · 800 sq ft | 3 | 2 |
| 2BHK | 80.76 sq m · 869 sq ft | 1 | 1 |
| 2BHK | 84.54 sq m · 910 sq ft | 4 | 4 |
| 2BHK | 84.6 sq m · 911 sq ft | 1 | 1 |
| 3BHK | 92.9 sq m · 1,000 sq ft | 1 | 1 |
| 3BHK | 96.25 sq m · 1,036 sq ft | 2 | 1 |
| 3BHK | 96.52 sq m · 1,039 sq ft | 1 | 1 |
| 3BHK | 101.35 sq m · 1,091 sq ft | 2 | 2 |
| 3BHK | 101.36 sq m · 1,091 sq ft | 2 | 2 |
| 3BHK | 101.39 sq m · 1,091 sq ft | 2 | 2 |
| 3BHK | 107.02 sq m · 1,152 sq ft | 3 | 3 |
| 3BHK | 111.06 sq m · 1,195 sq ft | 1 | 0 |
| 3BHK | 114.92 sq m · 1,237 sq ft | 1 | 1 |
| 4BHK | 209.38 sq m · 2,254 sq ft | 1 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | A R Designs | — |
| Chartered accountant | Rohit R Shah & Co | — |
| Engineer | Amol Harivijay Joshi | — |
| Engineer | S W Mone | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Kothrud
- SuramyaRERA PR1260002602717
- 1st Avenue - VinaykunjRERA PR1261012602185
- Yash Aura₹8,350 a sq ft
- Aqura IndraprasthaRERA PM1260002601531
- GurusevaRERA PR1260002601254
- Shree Ganesh Park Chsl₹12,610 a sq ft
- Shri Dattakrupa₹13,760 a sq ft
- Lotus SevaRERA PM1260002600759
All 4,695 projects in Kothrud · Compare Charuhas with another project
Charuhas in numbers
Registered deals, summarised
Deedo has 90 registered documents at Charuhas, from Apr 2016 to Oct 2026: 48 sales, 15 leave and licence agreements, 14 mortgages. The median registered sale since Apr 2016 works out to about ₹16,200 per sq ft, at a median of ₹1.14 Cr a deal; 4% of sales were resales.
- What is the price per sq ft at Charuhas?
- The median registered sale since Apr 2016 works out to about ₹16,200 per sq ft, at a median of ₹1.14 Cr a deal; 4% of sales were resales.
- How many properties have been sold at Charuhas?
- 48 sales are registered at Charuhas, 2 of them resales.
- Are properties at Charuhas rented out?
- Yes: 15 leave and licence agreements are registered at Charuhas, at a median rent since Apr 2016 of about ₹30,000 a month with a deposit of about ₹1,00,000.
- Where does this data come from?
- The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at Charuhas by Deedo, last updated with deals registered in Oct 2026.
Latest deal · Resale · May 2026
₹1–1.5 Cr