Joshi Buildcon Landmarks
Company or firm · 7 projects · 7 MahaRERA registrations
7Projects7 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 3 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 5 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| CharuhasP52100031203 | Kothrud | 2021 | Certificate Signed | 31 Aug 2024 | 31 May 2025 | +9 months |
| SpectrumP52100032621 | Pune (M Corp.) | 2022 | Certificate Signed | 30 Jun 2024 | 31 May 2025 | +11 months |
| Geetanjali BP52100034370 | Parvati | 2022 | Certificate Signed | 31 Jan 2024 | 31 Dec 2024 | +11 months |
| DwarkakunjP52100054204 | Kothrud | 2024 | Certificate Signed | 31 Oct 2026 | 31 Oct 2026 | On date |
| RajhansP52100076697 | Kothrud | 2024 | Certificate Signed | 31 May 2027 | 30 Sep 2027 | +4 months |
| AashishP52100080289 | Kothrud | 2025 | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 months |
| ShivanandPR1260002501611 | Kothrud | 2025 | Not reported | 31 Dec 2028 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 11 months, for Spectrum (P52100032621).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology