Khed, Pune
Deedo IDDL-PUN-KHED7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects331
Registrations349some projects hold several
Completion still due125169 past their date
Median extension4 months51% of registrations extended
Regulatory cases8on 9 projects
7 in 10 registrations run late here
349 MahaRERA registrations in Khed and the places within it
34 not yet due91 extended, not yet due169 past even the latest date55 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Khed
331 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Sara City C4Jagrutsara Structures LLP | Due Apr 2028, extended 4 mo | — | 29% |
| Shiv Ekviramangesh vasant gundal | Completed | — | — |
| Sukhwani AspireBasant - Sukhwani | Completed | — | 63% |
| Dwarka HouseSandeep Sambhaji Godase | 4 yrs late | — | — |
| Malhar Srushti HomesSagar Kaluram Patole | 1 yr 4 mo late | — | 97% |
| Sara SwapnodayJagrutsara Structures LLP | 5 mo late | — | 16% |
| Aryaa Dream TownVini Builders And Developers | Due Dec 2026 | — | 43% |
| Gulmohar ParkG G Builders And Developers | Completed | — | 92% |
| Balaji ParadisePrakash Harishchandra Padwal | 3 yrs 8 mo late | — | — |
| Prk Market CityPrk Vhentures | Completed | — | — |
| Narke HeightsChordia Constructions & Developers | Completed | — | 65% |
| Aabhas Phase IIVednirmitee Realities | 2 yrs 1 mo late | — | 17% |
| Shiv ClassicShri Kulswamini Promoters | Due Dec 2026, extended 3 yrs 6 mo | — | 24% |
| Shri Gurudev Samrajya E WingVaishanavi Builders and Developers | Completed | — | — |
| Sopan SaiDattakrupa Developers | 1 yr 11 mo late | — | — |
| Shri Sai ParkSachin Bapurao Khupse | Due Apr 2028, extended 4 mo | — | 30% |
| Mauli ResidencyTanish Developers | Completed | — | 100% |
| Ashanand residency Building D and EAnand Deoram Tambe | Due Oct 2028, extended 4 mo | — | 19% |
| Escape City Ph 1Gajendra Patil , Pramod Patil , Vinod Patil | Completed | — | — |
| KalpataruNkg Constructions LLP | Due Apr 2027, extended 4 mo | — | — |
| Ghanwat SquareShivam Developers Pvt. Ltd. | Completed, extended 2 yrs 5 mo | — | 59% |
| The Grand CentralGrow More Buildcon | 1 yr 11 mo late | — | 70% |
| SwagatP. S. Associates | 3 yrs 8 mo late | — | 100% |
| Kalp Residency D WingKalp Buildtech | Completed | — | 100% |
| City PlazaBharat Builders and Developers | Completed | — | 98% |
Nearby: other talukas in Pune
Most active promoters
- Jagrutsara Structures Llp21 projects
- Sara Builders & Developers7 projects
- Anand Deoram Tambe4 projects
- Naiknavare Housing Developments Pvt. Ltd4 projects
- Shivam Developers Pvt. Ltd4 projects
- Shree Sai Associates4 projects
- Intercontinental Infrastructure Limited3 projects
- Mahendra Sayaji Pacharane3 projects
- Mangesh Vasant Gundal3 projects
- Maple Estates3 projects
Khed, in questions
How many projects in Khed run late?
7 in 10 MahaRERA registrations (260 of 349): their completion date was extended or has passed, data through 6 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Khed by Deedo. Medians on fewer than 3 deeds are not shown.
Data through6 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology