Kumar Parc Residences - B1

Completion due Oct 2030

Hadapsar, Pune 411028 |Promoter: Kumar Properties Infratech Developers Pvt Ltd

20 Oct 2025Registered with MahaRERA
17 Oct 2030Promised completion
2Buildings
230Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA

Buildings
2

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.51581, 73.92716
Kumar Parc Residences - B1 is at latitude 18.51581, longitude 73.92716.
MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 17 Oct 2030

Registered
20 Oct 2025
Promised
17 Oct 2030

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PR126404250129620 Oct 202517 Oct 2030—Kumar Properties Infratech Developers Pvt LtdProject page

2 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsFloors with CCUnits
B1 - Wing A2931115
B1 - Wing B2931115

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Documents

1 document held by Deedo

Registration certificate

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Hadapsar

Survey, CTS, gat or plot numbers

178/1B178/2A178/2B179/2/1A/2179/2/1A/2A179/2/1A/2B179/2/1B179/2/2179 Hissa No.178/1ASurvey no. 178

Source: registration certificates, as stated there.

SourcesMahaRERA project search · registration certificatesMethodology