Deedo IDDP-PUN-TNNRCompletion was pushed back 4 months, to Aug 2030; no MahaRERA orders on record; 0% of its units are booked.
Hadapsar, Pune 411028 · Property rates in Hadapsar · Promoter: Euphoric Developers LLP
Completion was pushed back 4 months, to Aug 2030
- This projectRegistered 18 Apr 2026, completion promised 30 Apr 2030, revised to 30 Aug 2030.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationPR1260002600219
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| PR1260002600219 | 18 Apr 2026 | 30 Apr 2030 | 30 Aug 2030 | Euphoric Developers LLP | Project page |
Documents24
1 document held by Deedo, 23 filings listed on MahaRERA's project page
Finance
Show all 24 documentsShow fewer documents
Legal
Migrated
- Withdrawal Update Form 1Form 1 - Euphoric Blossom as on June 2026.pdf · uploaded 3 Aug 2026Source
- Withdrawal Update Form 2Form 2 - Euphoric Blossom as on June 2026-DESKTOP-DA4SVTU.pdf · uploaded 3 Aug 2026Source
- Withdrawal Update Form 3Form 3 - Euphoric Blossom as on June 2026.pdf · uploaded 3 Aug 2026Source
Technical
- DocumentApproved Plan (9)-pages-1-compressed.pdf · uploaded 11 Mar 2026Source
- DocumentApproved Plan (9)-pages-2-compressed.pdf · uploaded 11 Mar 2026Source
- DocumentApproved Plan (9)-pages-3-compressed.pdf · uploaded 11 Mar 2026Source
- DocumentApproved Plan (9)-pages-4-compressed.pdf · uploaded 11 Mar 2026Source
- DocumentApproved Plan (9)-pages-5-compressed.pdf · uploaded 11 Mar 2026Source
- DocumentApproved Plan (9)-pages-6-compressed.pdf · uploaded 11 Mar 2026Source
- Otherscc verification (1).pdf · uploaded 13 Mar 2026Source
- DocumentDeclaration of Order 50 (1).pdf · uploaded 31 Mar 2026Source
Technical (Architect)
- DocumentForm 1 - Euphoric Blossom as on June 2026.pdf · uploaded 3 Aug 2026Source
Technical (Engineer)
- DocumentForm 2 - Euphoric Blossom as on June 2026-DESKTOP-DA4SVTU.pdf · uploaded 3 Aug 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsSurvey no 95 Final Plot no 26
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- —151 units in all
- Address
- HadapsarPIN 411028
- Village
- Hadapsar, Haveli taluka
- Location
- 18.49308, 73.92462
- Designated bank account
- 76
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Boundaries
- North
- Adj. F.P. No. 27
- South
- Adj. F.P. No. 25
- East
- 24 meter wide D.P.Road
- West
- Adj. F.P. No. 24
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking151 units
151 units registered
| Building | Type | Carpet area | Units |
|---|---|---|---|
| Wing A | — | — | 80 |
| Wing B | — | — | 71 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.