Kumar Properties Infratech Developers Pvt Ltd
Company or firm · 5 projects · 5 MahaRERA registrations
Projects55 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date—no proposed date has passed yet
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Kumar Parc residences - A1P52100032022 | Hadapsar | 2021 | Not reported | 30 Nov 2026 | — | On date |
| Kumar Parc Residences - C MhadaP52100047940 | Hadapsar | 2022 | Not reported | 30 Nov 2026 | — | On date |
| Kumar Parc Residences - B2P52100049839 | Hadapsar | 2023 | Not reported | 31 Dec 2027 | — | On date |
| Kumar Parc Residences - A2P52100055344 | Hadapsar | 2024 | Not reported | 25 May 2028 | — | On date |
| Kumar Parc Residences - B1PR1264042501296 | Hadapsar | 2025 | Not reported | 17 Oct 2030 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.