Dosti Greenscapes

Completion due Apr 2028

Hadapsar, Pune 411013 |Promoter: Dosti Realty Limited

6 Mar 2023Registered with MahaRERAFirst of 2 registrations
30 Apr 2028Promised completionLatest across registrations
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA

RERA registrations
2
Phases
2

Also registered as

Dosti Greenscapes - Phase 1Dosti Greenscapes - Phase 2
MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2027

P52100049942
Registered
6 Mar 2023
Promised
31 Dec 2027

Completion promised for 30 Apr 2028

P52100051041
Registered
22 May 2023
Promised
30 Apr 2028

2 RERA registrations

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000499426 Mar 202331 Dec 2027—Dosti Realty LimitedProject page
P5210005104122 May 202330 Apr 2028—Dosti Realty LimitedProject page

Documents

2 documents held by Deedo

Registration certificates

  • Registration certificateP52100049942 · 13 Apr 2023ViewSource
  • Registration certificateP52100051041 · 22 May 2023ViewSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Hadapsar

Survey, CTS, gat or plot numbers

112/1A/Plot No1 (pt)

Source: registration certificates, as stated there.

SourcesMahaRERA project search · registration certificatesMethodology