Dosti Realty Ltd

Deedo IDDD-WB2Q

Of 1 registration whose promised date has arrived, 1 kept it (100%).

Projects89 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record236registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

3 of 9 registrations with dates moved or missed their RERA date · months late against the original promise

9 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Dosti Imperia - Dosti MajestaP51700010988Thane (M Corp.)Certificate Signed31 Dec 201831 Dec 2018On date
Dosti Eastern Bay - Phase 1P51900025142Ward FnorthCertificate Signed30 Mar 202830 Mar 2028On date
Dosti Eastern Bay- Phase 2P51900030769Ward FnorthCertificate Signed30 Sep 202730 Sep 2027On date
Dosti Eastern Bay - Phase 3P51900032067Mumbai CityCertificate Signed30 Sep 202730 Sep 2027On date
Dosti GreenscapesP52100049942HadapsarCertificate Signed31 Dec 202731 Dec 2027On date
Dosti GreenscapesP52100051041HadapsarCertificate Signed30 Apr 202830 Aug 2028+4 mo
Dosti Greenscapes - Phase 3P52100077059HadapsarCertificate Signed31 Aug 202831 Dec 2028+4 mo
Dosti Greenscapes - Phase 4P52100077092HadapsarCertificate Signed31 Aug 202731 Dec 2027+4 mo
Dosti Greenscapes - Phase 5PM1264042601721HadapsarCertificate Signed30 Jun 203130 Jun 2031On date

Dosti Realty Ltd, in questions

Does Dosti Realty Ltd finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 1 kept it (100%). Across Maharashtra, 73% kept their date.

How many projects has Dosti Realty Ltd registered with MahaRERA?

8 projects under 9 MahaRERA registrations; 4 completed on MahaRERA.

Does Dosti Realty Ltd have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology