Aaiji Castle

Deedo IDDP-PUN-RG7W

Completion was pushed back 3 months to Mar 2025, and that date has passed too; no MahaRERA orders on record.

Dhanori, Pune 411015 · Property rates in Dhanori · by Aaiji Developers · 29% of its projects kept the RERA date

Delivery1 yr 11 mo latePromised Dec 2024 · revised Mar 2025 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readPrice₹11,110 /sq ft50.1% above Dhanori · 218 registered sales

Buying a flat here?

See every deed registered on it.

Completion was pushed back 3 months to Mar 2025, and that date has passed too

  • This projectRegistered 9 Aug 2023, completion promised 1 Dec 2024, revised to 31 Mar 2025, and still not shown completed today.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

All 309 deeds →
Latest registered deeds in this project
MonthFlatKindAreaPriceRecord
Oct 2026Aaiji Castle · 1407Primary sale1,076 sq ftView Primary sale, Oct 2026
Sep 2026Aaiji Castle · 104Primary sale904 sq ftView Primary sale, Sep 2026
Sep 2026Aaiji Castle · 103Primary sale903 sq ftView Primary sale, Sep 2026
Sep 2026Aaiji Castle · 904Primary sale904 sq ftView Primary sale, Sep 2026
Aug 2026Aaiji Castle · 1503Primary sale903 sq ftView Primary sale, Aug 2026
Jul 2026Aaiji Castle · 1103Primary sale904 sq ftView Primary sale, Jul 2026
Jul 2026Aaiji Castle · 1104Primary sale904 sq ftView Primary sale, Jul 2026
Jul 2026Aaiji Castle · 301Primary sale755 sq ftView Primary sale, Jul 2026
Jul 2026Aaiji Castle · 101Primary sale497 sq ftView Primary sale, Jul 2026
Jun 2026Aaiji Castle · 102Primary sale497 sq ftView Primary sale, Jun 2026

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100052317
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000523179 Aug 20231 Dec 202431 Mar 2025Aaiji DevelopersProject page
Documents89

2 documents held by Deedo, 87 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardAaiji Capital - AAIJI DEVELOPERS-PAN.pdf · uploaded 17 Nov 2022Source

Legal

  • Declaration Form BAFFIDAVIT DECLARATION.pdf · uploaded 18 May 2023Source
  • Legal Title reportLEGAL TITLE REPORT 23-5-23.pdf · uploaded 24 May 2023Source
  • Declaration Form BForm B (1).pdf · uploaded 24 Dec 2024Source

Migrated

  • 1 PAN CardAaiji Capital - AAIJI DEVELOPERS-PAN.pdf · uploaded 17 Nov 2022Source
  • 1 Copy of Layout Approval (in case of layout)PLAN COPY_11zon.pdf · uploaded 17 Nov 2022Source
Show all 89 documentsShow fewer documents

Migrated

  • 1 Building Plan Approval / NA Order for plotted developmentPLAN COPY_11zon.pdf · uploaded 17 Nov 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentCOMMENCMENT CERTIFICATE.pdf · uploaded 17 Nov 2022Source
  • 1 Proforma of Agreement for saleATS.pdf · uploaded 4 Feb 2023Source
  • 1 Proforma of Allotment letterAllotment_Letter (2).pdf · uploaded 4 Feb 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 17 Feb 2023Source
  • 1 a Details of encumbrances concerned to FinanceCONCERNED TO FINANCE.pdf · uploaded 18 May 2023Source
  • 2 a Details of encumbrances concerned to FinanceCONCERNED TO LEGAL.pdf · uploaded 18 May 2023Source
  • 1 b Details of encumbrances concerned to LegalCONCERNED TO FINANCE.pdf · uploaded 18 May 2023Source
  • 2 b Details of encumbrances concerned to LegalCONCERNED TO LEGAL.pdf · uploaded 18 May 2023Source
  • 1 Declaration in FORM BAFFIDAVIT DECLARATION.pdf · uploaded 18 May 2023Source
  • 1 CERSAI detailsCHARGE ON PROJECT.pdf · uploaded 18 May 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBANK ACCOUNT.pdf · uploaded 18 May 2023Source
  • 1 Deviation Report with respect to Allotment letterDEVIATION ALLOTMENT LETTER.pdf · uploaded 18 May 2023Source
  • 1 Deviation Report with respect to model copy of AgreementDEVIATION AGREEMENT SALE.pdf · uploaded 18 May 2023Source
  • 1 Copy of the legal title reportLEGAL TITLE REPORT 23-5-23.pdf · uploaded 24 May 2023Source
  • 1 Declaration about Commencement CertificateFormat D 03-07-2023.pdf · uploaded 4 Jul 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 03-07-2023.pdf · uploaded 4 Jul 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in Other Organisation - Hemat Choudhary.pdf · uploaded 4 Jul 2023Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in Other Organisation - Suresh Choudhary.pdf · uploaded 4 Jul 2023Source
  • 3 Disclosure of Interest in Other Real Estate OrganizationsAaiji Castle Application Preview.pdf · uploaded 11 Jul 2023Source
  • 1 Disclosure of sold/ booked inventoryUnit Sold and Unsold Sep 23.pdf · uploaded 20 Jan 2024Source
  • 2 Disclosure of sold/ booked inventoryUnit Sold and Unsold Dec 23.pdf · uploaded 20 Jan 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Aaiji Castle Architect Certificate Sep-23 Final.pdf · uploaded 20 Apr 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Aaiji Castle Architect Certificate Dec-23 Final.pdf · uploaded 20 Apr 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Aaiji Castle Engineers Certificate Sep -23 Revised Final .pdf · uploaded 20 Apr 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Aaiji Castle Engineers Certificate Dec -23 Revised Final pdf.pdf · uploaded 20 Apr 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Aaiji Castle From 3 Sep 2023.pdf · uploaded 20 Apr 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Aaiji Castle From 3 dec 2023.pdf · uploaded 20 Apr 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Aaiji Castle Arch Certificate March 2024 .pdf · uploaded 27 Apr 2024Source
  • 3 Disclosure of sold/ booked inventoryUnit Sold and Unsold Mar 24.pdf · uploaded 27 Apr 2024Source
  • 2 Building Plan Approval / NA Order for plotted developmentSanction Plan No 3267-2023 Dt 18-03-2024_11zon.pdf · uploaded 11 Jul 2024Source
  • 2 Commencement Certificates / NA Order for plotted developmentCC No 3267-2023 Dt 18-03-2024.pdf · uploaded 11 Jul 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Aaiji Castle From Mar 2024 .pdf · uploaded 2 Aug 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Aaiji Castle From 5 FY 2023-24 Dt 09-08-2024.pdf · uploaded 10 Aug 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Aaiji Castle Architect Certificate June - 24 .pdf · uploaded 13 Dec 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Aaiji Castle Architect Certificate SEP - 24.pdf · uploaded 13 Dec 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Aaiji Castle Form 3 30062024_Signed.pdf · uploaded 13 Dec 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Aaiji Castle Form 3 30092024_Signed.pdf · uploaded 13 Dec 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Aaiji Castle Form 2 30062024_Signed.pdf · uploaded 13 Dec 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Aaiji_castle form 2 30092024_Signed.pdf · uploaded 13 Dec 2024Source
  • 1 Declaration in FORM BForm B (1).pdf · uploaded 24 Dec 2024Source
  • 1 Other – Technical11zon_JPEG-to-PDF (1).pdf · uploaded 24 Dec 2024Source
  • 2 Other – Technical11zon_JPEG-to-PDF.pdf · uploaded 24 Dec 2024Source
  • 1 Disclosure of sold/ booked inventoryUnit Sold and Unsold jun 24.pdf · uploaded 9 Jan 2025Source
  • 2 Disclosure of sold/ booked inventoryUnit Sold and Unsold sep24.pdf · uploaded 9 Jan 2025Source
  • 3 Disclosure of sold/ booked inventoryUnit Sold and Unsold dec 24.pdf · uploaded 9 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Aaiji Castle From Dec 2024 .pdf · uploaded 17 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Aaiji Castle Architect Certificate Dec-24 _11zon.pdf · uploaded 11 Apr 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Aaiji Castle_Form 1.pdf · uploaded 11 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_Castle Dec24_11zon.pdf · uploaded 17 Apr 2025Source
  • 1 Disclosure of sold/ booked inventoryAaiji Castle RERA Sold and Unsold Mar-2025 .pdf · uploaded 17 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Aaiji Castle From Mar- 2025.pdf · uploaded 18 Apr 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate Form 2.pdf · uploaded 18 Apr 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A_Aaiji Castle.pdf · uploaded 23 Apr 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 24 Apr 2025Source
  • 1 Building Plan Approval / NA Order for plotted developmentSanction Plan No 4292-2025 Dt 26-03-2025_11zon.pdf · uploaded 26 Apr 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)QA Form2A 24-25.pdf · uploaded 29 Apr 2025Source
  • Form 1Aaiji Castle_Form 1 Dec-24.pdf · uploaded 28 May 2025Source
  • Form 2Aaiji Castle_Form 2_Dec 2024.pdf · uploaded 28 May 2025Source
  • Form 3CA Aaiji Castle Form 3 Dec 2024.pdf · uploaded 28 May 2025Source
  • Disclosure of Sold and Booked InventorySold Unsold dec 2024.pdf · uploaded 28 May 2025Source
  • Form 1Aaiji Castle_Form 1_March 2025.pdf · uploaded 28 May 2025Source
  • Form 2Aaiji Castle_Form 2_March 2025.pdf · uploaded 28 May 2025Source
  • Form 3CA Aaiji Castle Form 3 Mar- 2025.pdf · uploaded 28 May 2025Source
  • Disclosure of Sold and Booked InventorySold Unsold March 2025.pdf · uploaded 28 May 2025Source

Technical

  • DocumentPLAN COPY_11zon.pdf · uploaded 17 Nov 2022Source
  • DocumentPLAN COPY_11zon.pdf · uploaded 17 Nov 2022Source
  • DocumentSanction Plan No 3267-2023 Dt 18-03-2024_11zon.pdf · uploaded 11 Jul 2024Source
  • Other – Technical11zon_JPEG-to-PDF (1).pdf · uploaded 24 Dec 2024Source
  • Other – Technical11zon_JPEG-to-PDF.pdf · uploaded 24 Dec 2024Source
  • DocumentSanction Plan No 4292-2025 Dt 26-03-2025_11zon.pdf · uploaded 26 Apr 2025Source

Technical (Architect)

  • DocumentAaiji Castle Architect Certificate June - 24 .pdf · uploaded 13 Dec 2024Source
  • DocumentAaiji Castle Architect Certificate SEP - 24.pdf · uploaded 13 Dec 2024Source
  • DocumentAaiji Castle Architect Certificate Dec-24 _11zon.pdf · uploaded 11 Apr 2025Source
  • DocumentAaiji Castle_Form 1.pdf · uploaded 11 Apr 2025Source
  • DocumentAaiji Castle_FORM 1_June 2025.pdf · uploaded 27 Nov 2025Source

Technical (Engineer)

  • DocumentAaiji Castle Engineers Certificate Dec -23 Revised Final pdf.pdf · uploaded 28 Sep 2024Source
  • DocumentAaiji Castle Form 2 30062024_Signed.pdf · uploaded 13 Dec 2024Source
  • DocumentAaiji_castle form 2 30092024_Signed.pdf · uploaded 13 Dec 2024Source
  • DocumentForm 2_Castle Dec24_11zon.pdf · uploaded 17 Apr 2025Source
  • DocumentEngineers Certificate Form 2.pdf · uploaded 18 Apr 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 33/1A(P)/73

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
2BHK, Shop19 units in all
Address
33/1A(P)/73, 33/1A/73, DhanoriPIN 411015
Village
Dhanori
Land area for this project
487 sq m (5,242 sq ft)
Permissible built-up area
1,113 sq m (11,983 sq ft)
Sanctioned built-up area
855 sq m (9,204 sq ft)
Recreational open space
50 sq m (538 sq ft)
Designated bank account
85
Developed in phases
No
Also registered as
Aiji Kesal, आईजी कॅसल, Aiji Kristal Fej Tu Ya Prakalpatil Ving Bi Mhanajech Rubi Ya, Aiji Kristal Fej Tu Ya Prakalpatil Ving Si Mhanajech Safayar Ya, Aiji Kristal Fej Van Ya Prakalpatil Ving Di Mhada Ya, आईजी क्रिस्टल फेज टू या प्रकल्पातील विंग बी म्हणजेच रुबी या, आईजी क्रिस्टल फेज टू या प्रकल्पातील विंग सी म्हणजेच सफायर या, आईजी क्रिस्टल फेज वन या प्रकल्पातील विंग डी म्हाडा या, आईजी क्रस्टल फेज टू या प्रकल्पातील विंग बी म्हणजेच रुबी या, Aiji Krastal Fej Tu Ya Prakalpatil Ving Bi Mhanajech Rubi Ya, आईजी क्रस्टल या प्रकल्पातील बिंग ए म्हणजेच अंबर या, Aiji Krastal Ya Prakalpatil Bing E Mhanajech Anbar Ya, Aiji Krastal, आईजी क्रस्टल, Aiji Kristal, आईजी क्रिस्टल, Aiji Kristal Phase Tu Ya Prakalpatil Wing C Mhanajech Safayar Ya, Aiji Kristal Phase Tu Ya Prakalpatil Wing B Mhanajech Rubi Ya, Aiji Kristal Phase Van Ya Prakalpatil Wing D Mhada Ya, Aiji Krastal Phase Tu Ya Prakalpatil Wing B Mhanajech Rubi Ya

Survey, CTS, gat or plot numbers

33/1A(P)/73

Land as published on MahaRERA's project page

33/1A(P)/73

Boundaries

North
By Plot No 75 Mr Badave
South
By Road
East
By Plot No 74
West
By Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking19 units

3 of 19 units booked (16%), as the promoter reported to MahaRERA

2BHK · 18 unitsShop · 1 unit
TypeCarpet areaUnitsBooked
2BHK51.72 sq m · 557 sq ft61
2BHK56.91 sq m · 613 sq ft61
2BHK67.29 sq m · 724 sq ft61
Shop87.7 sq m · 944 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSomnath Kerur arch consultant and engineers—
Chartered accountantAnuj Sushil Agrawal—
Chartered accountantPatel & Sharma Chartered Accountants—
EngineerKahnu Katke—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Dhanori

All 2,604 projects in Dhanori · Compare Aaiji Castle with another project

Aaiji Castle in numbers

Registered deals, summarised

Deedo has 309 registered documents at Aaiji Castle, from Nov 2022 to Oct 2026: 218 sales, 9 leave and licence agreements, 71 mortgages. The median registered sale since Nov 2022 works out to about ₹11,100 per sq ft, at a median of ₹89 L a deal; 0% of sales were resales.

What is the price per sq ft at Aaiji Castle?
The median registered sale since Nov 2022 works out to about ₹11,100 per sq ft, at a median of ₹89 L a deal; 0% of sales were resales.
How many properties have been sold at Aaiji Castle?
218 sales are registered at Aaiji Castle, 1 of them a resale.
Are properties at Aaiji Castle rented out?
Yes: 9 leave and licence agreements are registered at Aaiji Castle, at a median rent since Nov 2022 of about ₹28,000 a month with a deposit of about ₹60,000.
Where does this data come from?
The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at Aaiji Castle by Deedo, last updated with deals registered in Oct 2026.

Latest deal · Primary sale · Oct 2026

₹1–1.5 Cr

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project page · registered documents (Index II)Data through is when MahaRERA's project page was last read.Report a problemMethodology