Aaiji Developers
Company or firm · 7 projects · 7 MahaRERA registrations
7Projects7 RERA registrations
0Completedas reported on MahaRERA project pages
86%Kept RERA date6 of 7 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Aaiji Dham Building BP52100019177 | Pune City | 2019 | Not reported | 30 Nov 2020 | — | On date |
| Aaiji Dham Building AP52100021607 | Pune City | 2019 | Not reported | 30 Nov 2020 | — | On date |
| AAIJI VivantaP52100034457 | Balewadi | 2022 | Not reported | 30 Jun 2024 | — | On date |
| Aaiji Crystal Phase IP52100046177 | Wagholi | 2022 | Not reported | 1 Oct 2026 | — | On date |
| Aaiji CapitalP52100046195 | Baner | 2022 | Not reported | 1 Dec 2024 | — | On date |
| Aaiji CastleP52100052317 | Dhanori | 2023 | Not reported | 1 Dec 2024 | 31 Mar 2025 | +3 months |
| Aaiji Crystal Phase IIP52100077661 | Haveli | 2024 | Not reported | 1 Oct 2026 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 6 of 7 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 3 months, for Aaiji Castle (P52100052317).
Regulatory cases across projects
- DeregisteredDeregistered: AAIJI CAPITAL · Aaiji Capital · P52100046195
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology