Aaiji Developers
Deedo IDDD-DNVYOf 7 registrations whose promised date has arrived, 2 kept it (29%). The rest ran a median 23 mo late.
Delivery record
5 of 7 registrations with dates moved or missed their RERA date · months late against the original promise
7 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Deregistered | Aaiji CapitalDeregistered: AAIJI CAPITAL | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Aaiji Dham Building BP52100019177 | Lohgaon | Certificate Signed | 30 Nov 2020 | 30 Nov 2020 | On date |
| Aaiji Dham Building AP52100021607 | Lohgaon | Certificate Signed | 30 Nov 2020 | 30 Nov 2020 | On date |
| AAIJI VivantaP52100034457 | Balewadi | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | +29 mo* |
| Aaiji Crystal Phase IP52100046177 | Wagholi | Certificate Signed | 1 Oct 2026 | 1 Oct 2026 | +1 mo* |
| Aaiji CapitalP52100046195 | Baner | Certificate Signed | 1 Dec 2024 | 1 Dec 2024 | +23 mo* |
| Aaiji CastleP52100052317 | Dhanori | Certificate Signed | 1 Dec 2024 | 31 Mar 2025 | +23 mo* |
| Aaiji Crystal Phase IIP52100077661 | Haveli | Certificate Signed | 1 Oct 2026 | 1 Feb 2027 | +4 mo |
Aaiji Developers, in questions
Does Aaiji Developers finish projects on time?
Of 7 MahaRERA registrations whose promised completion date has arrived, 2 kept it (29%). The rest ran a median 23 mo late. Across Maharashtra, 73% kept their date.
How many projects has Aaiji Developers registered with MahaRERA?
7 projects under 7 MahaRERA registrations; 2 completed on MahaRERA.
Does Aaiji Developers have MahaRERA regulatory cases?
1 regulatory case name its registrations.