Urban Homes
Completion due Nov 2026Charholi, Pune 412105 |Promoter: Lotus Properties
Project summary
As registered with MahaRERA
- RERA registrations
- 2
- Phases
- 2
Location
Coordinates as published by MahaRERA
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 30 Apr 2026
P52100047919The latest completion date on record passed 6 months ago.
- Registered
- 1 Dec 2022
- Promised
- 30 Apr 2026
Completion promised for 30 Nov 2026
P52100078270- Registered
- 4 Dec 2024
- Promised
- 30 Nov 2026
2 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100047919 | 1 Dec 2022 | 30 Apr 2026 | — | Lotus Properties | Project page |
| P52100078270 | 4 Dec 2024 | 30 Nov 2026 | — | Lotus Properties | Project page |
Documents
3 documents held by Deedo
Registration certificate (2)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Charholi
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.