Lotus Properties

Deedo IDDD-MQP2

Of 2 registrations whose promised date has arrived, 2 kept it (100%).

Projects23 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record1registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Urban HomesP52100047919CharholiCertificate Signed30 Apr 202630 Apr 2026On date
Urban Homes A WingP52100048902CharoliCertificate Signed31 Mar 202631 Mar 2026On date
Urban HomesP52100078270CharholiCertificate Signed30 Nov 202630 Mar 2027+4 mo

Lotus Properties, in questions

Does Lotus Properties finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 2 kept it (100%). Across Maharashtra, 73% kept their date.

How many projects has Lotus Properties registered with MahaRERA?

2 projects under 3 MahaRERA registrations; 2 completed on MahaRERA.

Does Lotus Properties have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology