5 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects58
Registrations59some projects hold several
Completion still due1825 past their date
Median extension4 months47% of registrations extended
Regulatory cases2on 2 projects
Bhor market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

6 in 10 registrations run late here

59 MahaRERA registrations in Bhor and the places within it

5 not yet due13 extended, not yet due25 past even the latest date16 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Bhor

58 projects registered with MahaRERA in this taluka and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Sahyadri HeightsDs Builders And DevelopersDue Nov 2028, extended 4 mo——
VillamentGangotree Homes And HolidaysDue Apr 2028, extended 4 mo—0%
Casuarina - Country HomesGangotree Homes And HolidaysDue Apr 2030, extended 4 mo——
IndustreeDhankawade Square Realtors LLPDue Jun 2028, extended 4 mo——
Athashri AnandaAnanda Senior Living Pvt. Ltd.Due Jun 2029, extended 4 mo—4%
Swapnalok Developers, Swapnalok Nagari Bhor,- Plots -Phase 2Swapnalok Developers1 yr 10 mo late——
More NivasKanta Bhiku More1 yr 9 mo late—0%
Samara HillsParanjape Schemes (Construction) LtdDue Oct 2028, extended 4 mo——
ShivshailyaSunetra Shirish Gokhale2 yrs 10 mo late——
Rajvishwa HeightsRaj Vishwa Developers1 yr 9 mo late—0%
Marigolds Valley-1Castle Dream Space1 yr 10 mo late——
Nine Jewels Hill ViewMilind Gulabrao Vatare3 yrs 10 mo late——
Rajmudra HeightsSudhir Sadashiv Dighe1 yr 10 mo late—0%
Parvati ApartmentSagar Shivram Shete1 mo late—31%
Akshara ComplexArvind Sopanrao Mohite2 yrs 9 mo late—0%
Swarada SankulShinde Patankar Associates4 yrs 2 mo late—63%
Swapnalok Nagari PlotsSwapnalok Developers7 yrs 7 mo late——
Ishaan Gharkul AIshaan Buildcon3 yrs 10 mo late—64%
ShivalayamJagtap Promoters And Builders2 yrs 10 mo late—0%
Swapnalok Nagari Commercial BuildingSwapnalok Developers2 yrs 4 mo late—29%
Prospera CountyMudraa Life Spaces Pvt LtdDue Feb 2027, extended 4 mo—6%
Pooja Heavan ParkPooja DevelopersDue Apr 2029, extended 4 mo——
ShreepadSachn Ashok Harnaskar5 yrs 9 mo late—88%
Bougain Villa - Cluster 1Synergy PropertiesDue Apr 2032, extended 4 mo—65%
Greystone ParkSiddheshwar Construction8 yrs 8 mo late—38%

Most active promoters

  1. Swapnalok Developers6 projects
  2. Synergy Properties3 projects
  3. Castle Dream Space2 projects
  4. Gangotree Homes And Holidays2 projects
  5. Paranjape Schemes (Construction) Ltd2 projects
  6. Ananda Senior Living Pvt. Ltd.1 project
  7. Arvind Sopanrao Mohite1 project
  8. Dhankawade Square Realtors LLP1 project
  9. Ds Builders And Developers1 project
  10. Ishaan Buildcon1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology