Bhor, Pune
Deedo IDDL-PUN-BHOR5 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects58
Registrations59some projects hold several
Completion still due1825 past their date
Median extension4 months47% of registrations extended
Regulatory cases2on 2 projects
6 in 10 registrations run late here
59 MahaRERA registrations in Bhor and the places within it
5 not yet due13 extended, not yet due25 past even the latest date16 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Bhor
58 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Sahyadri HeightsDs Builders And Developers | Due Nov 2028, extended 4 mo | — | — |
| VillamentGangotree Homes And Holidays | Due Apr 2028, extended 4 mo | — | 0% |
| Casuarina - Country HomesGangotree Homes And Holidays | Due Apr 2030, extended 4 mo | — | — |
| IndustreeDhankawade Square Realtors LLP | Due Jun 2028, extended 4 mo | — | — |
| Athashri AnandaAnanda Senior Living Pvt. Ltd. | Due Jun 2029, extended 4 mo | — | 4% |
| Swapnalok Developers, Swapnalok Nagari Bhor,- Plots -Phase 2Swapnalok Developers | 1 yr 10 mo late | — | — |
| More NivasKanta Bhiku More | 1 yr 9 mo late | — | 0% |
| Samara HillsParanjape Schemes (Construction) Ltd | Due Oct 2028, extended 4 mo | — | — |
| ShivshailyaSunetra Shirish Gokhale | 2 yrs 10 mo late | — | — |
| Rajvishwa HeightsRaj Vishwa Developers | 1 yr 9 mo late | — | 0% |
| Marigolds Valley-1Castle Dream Space | 1 yr 10 mo late | — | — |
| Nine Jewels Hill ViewMilind Gulabrao Vatare | 3 yrs 10 mo late | — | — |
| Rajmudra HeightsSudhir Sadashiv Dighe | 1 yr 10 mo late | — | 0% |
| Parvati ApartmentSagar Shivram Shete | 1 mo late | — | 31% |
| Akshara ComplexArvind Sopanrao Mohite | 2 yrs 9 mo late | — | 0% |
| Swarada SankulShinde Patankar Associates | 4 yrs 2 mo late | — | 63% |
| Swapnalok Nagari PlotsSwapnalok Developers | 7 yrs 7 mo late | — | — |
| Ishaan Gharkul AIshaan Buildcon | 3 yrs 10 mo late | — | 64% |
| ShivalayamJagtap Promoters And Builders | 2 yrs 10 mo late | — | 0% |
| Swapnalok Nagari Commercial BuildingSwapnalok Developers | 2 yrs 4 mo late | — | 29% |
| Prospera CountyMudraa Life Spaces Pvt Ltd | Due Feb 2027, extended 4 mo | — | 6% |
| Pooja Heavan ParkPooja Developers | Due Apr 2029, extended 4 mo | — | — |
| ShreepadSachn Ashok Harnaskar | 5 yrs 9 mo late | — | 88% |
| Bougain Villa - Cluster 1Synergy Properties | Due Apr 2032, extended 4 mo | — | 65% |
| Greystone ParkSiddheshwar Construction | 8 yrs 8 mo late | — | 38% |
Nearby: other talukas in Pune
Most active promoters
- Swapnalok Developers6 projects
- Synergy Properties3 projects
- Castle Dream Space2 projects
- Gangotree Homes And Holidays2 projects
- Paranjape Schemes (Construction) Ltd2 projects
- Ananda Senior Living Pvt. Ltd.1 project
- Arvind Sopanrao Mohite1 project
- Dhankawade Square Realtors LLP1 project
- Ds Builders And Developers1 project
- Ishaan Buildcon1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology