Project summary
As registered with MahaRERA and published on its project page
- Project type
- Plotted
- Status on MahaRERA
- Certificate Signed
- Address
- Gat No. 73, SHIND, BHORPIN 412203
- Designated bank account
- 220
- Developed in phases
- No
Location
Coordinates as published by MahaRERA
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 3 years
The latest completion date on record passed 10 months ago.
- Registered
- 24 Jan 2022
- Promised
- 31 Dec 2022
- Revised
- 31 Dec 2025
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100032732 | 24 Jan 2022 | 31 Dec 2022 | 31 Dec 2025 | Milind Gulabrao Vatare | Project page |
Documents
2 documents held by Deedo, 76 filings listed on MahaRERA's project page
Show all 78 documentsShow fewer documents
Migrated
- 1 Copy of the legal title report02 Search and Title.pdf · uploaded 8 Jan 2022Source
- 1 Details of encumbrancesDeclaration Applicant.pdf · uploaded 8 Jan 2022Source
- 2 Details of encumbrancesDeclartion Co applicant.pdf · uploaded 8 Jan 2022Source
- 1 Copy of Layout Approval (in case of layout)Blue Print.pdf · uploaded 8 Jan 2022Source
- 1 Declaration in FORM B08 FORM B APPLICANT.pdf · uploaded 8 Jan 2022Source
- 2 Declaration in FORM B09 FORM B COAPPLICANT_.pdf · uploaded 8 Jan 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)09 Architech certificate.pdf · uploaded 8 Jan 2022Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)10 Engineers certificate.pdf · uploaded 8 Jan 2022Source
- 1 Proforma of Allotment letterSaledeed draft (1) Shind Bhor.pdf · uploaded 8 Jan 2022Source
- 2 PAN CardPan Card Madm.pdf · uploaded 10 Jan 2022Source
- 1 Building Plan Approval / NA Order for plotted developmentभोर NA ऑर्डर_.pdf · uploaded 10 Jan 2022Source
- 1 Commencement Certificates / NA Order for plotted developmentभोर NA ऑर्डर_.pdf · uploaded 10 Jan 2022Source
- 1 Declaration about Commencement CertificateForm D.pdf · uploaded 10 Jan 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)MILIND GULABRAO VATARE CA Certificate.pdf · uploaded 10 Jan 2022Source
- 1 CERSAI detailsCERSAI_Debtor_Based_Search.pdf · uploaded 15 Jan 2022Source
- 2 CERSAI detailsCERSAI_Debtor_Based_Search.pdf · uploaded 15 Jan 2022Source
- 3 CERSAI detailsCERSAI_Undertaking.pdf · uploaded 15 Jan 2022Source
- 3 a Details of encumbrances concerned to Financelegal encumbrance .pdf · uploaded 7 Aug 2023Source
- 4 a Details of encumbrances concerned to FinanceFinance encumbrance.pdf · uploaded 7 Aug 2023Source
- 1 b Details of encumbrances concerned to Legallegal encumbrance .pdf · uploaded 7 Aug 2023Source
- 2 b Details of encumbrances concerned to LegalFinance encumbrance.pdf · uploaded 7 Aug 2023Source
- 2 Declaration about Commencement Certificate14 Declaration about Commencement ok.pdf · uploaded 7 Aug 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architecture certificate .pdf · uploaded 7 Aug 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 eng certificate ok.pdf · uploaded 7 Aug 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)2A 21-22.pdf · uploaded 7 Aug 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)2A 2022-23 Ok.pdf · uploaded 7 Aug 2023Source
- 4 CERSAI detailsCERSAI_Search_Report_200273635159_For_Asset_Based_Search_06_07_2023_15_39_04_645.pdf · uploaded 7 Aug 2023Source
- 1 Disclosure of sold/ booked inventorysold Unsold .pdf · uploaded 7 Aug 2023Source
- 5 CERSAI detailscersai Undertaking .pdf · uploaded 7 Aug 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the samerera Separate account declaration.pdf · uploaded 8 Aug 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE Signed.pdf · uploaded 12 Aug 2023Source
- Form 104 Form 1 Dec 24.pdf · uploaded 18 Jun 2025Source
- Form 204 Form 2 Dec 24.pdf · uploaded 18 Jun 2025Source
- Form 304 Form 3 Dec 24.pdf · uploaded 18 Jun 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of INventory.pdf · uploaded 18 Jun 2025Source
- OthersForm 2A M24.pdf · uploaded 18 Jun 2025Source
- Form 103 Form 1 Sep 24.pdf · uploaded 18 Jun 2025Source
- Form 203 Form 2 Sep 24.pdf · uploaded 18 Jun 2025Source
- Form 303 Form 3 Sep 24.pdf · uploaded 18 Jun 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of INventory.pdf · uploaded 18 Jun 2025Source
- Form 102 Form 1 Jun 24.pdf · uploaded 18 Jun 2025Source
- Form 202 Form 2 Jun 24.pdf · uploaded 18 Jun 2025Source
- Form 302 Form 3 Jun 24.pdf · uploaded 18 Jun 2025Source
- OthersForm 2A M24.pdf · uploaded 18 Jun 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of INventory.pdf · uploaded 18 Jun 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of INventory.pdf · uploaded 18 Jun 2025Source
- Form 101 Form 1 Mar 24.pdf · uploaded 18 Jun 2025Source
- Form 201 Form 2 Mar 24.pdf · uploaded 18 Jun 2025Source
- Form 301 Form 3 Mar 24.pdf · uploaded 18 Jun 2025Source
- Form 1FORM 1 Arch March 25.pdf · uploaded 17 Nov 2025Source
- Form 2FORM 2 Engg March 25.pdf · uploaded 17 Nov 2025Source
- Form 3FORM 3 CA Certificate March 2025.pdf · uploaded 17 Nov 2025Source
- Disclosure of Sold and Booked InventoryDiscolsure of sold-book inventory March 2025.pdf · uploaded 17 Nov 2025Source
- Withdrawal Update Form 1Form 1 Arch June 2025.pdf · uploaded 20 Nov 2025Source
- Withdrawal Update Form 2Form 2 Engg June 2025.pdf · uploaded 20 Nov 2025Source
- Withdrawal Update Form 3FORM 3 CA Certificate June 2025_11zon.pdf · uploaded 20 Nov 2025Source
- Form 5 (FY 2024-2025)From 5 2024-25.pdf · uploaded 20 Nov 2025Source
- Withdrawal Update Form 104 FORM 1 - Architect Sept 2025.pdf · uploaded 25 Dec 2025Source
- Withdrawal Update Form 204 FORM 2 - Engineer Certificate Sept 2025.pdf · uploaded 25 Dec 2025Source
- Withdrawal Update Form 304 FORM 3 - CA Certificate Sept 2025.pdf · uploaded 25 Dec 2025Source
- Completion CertificateProject Completion Certificate.pdf · uploaded 25 Dec 2025Source
Technical
- DocumentBlue Print.pdf · uploaded 8 Jan 2022Source
- Documentभोर NA ऑर्डर_.pdf · uploaded 10 Jan 2022Source
- DocumentFinal NA Order_19102023.pdf · uploaded 17 Nov 2025Source
- DocumentFinal Blue Print_22122021.pdf · uploaded 17 Nov 2025Source
- DocumentFinal NA Order_19102023.pdf · uploaded 20 Nov 2025Source
- DocumentFinal Blue Print_22122021.pdf · uploaded 20 Nov 2025Source
- OthersForm 2A 2024-25.pdf · uploaded 20 Nov 2025Source
Technical (Architect)
- Document04 FORM 1 - Architect Sept 2025.pdf · uploaded 25 Dec 2025Source
Technical (Engineer)
- Document04 FORM 2 - Engineer Certificate Sept 2025.pdf · uploaded 25 Dec 2025Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Shind, Bhor taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- Property of Mr Sunil Khutwad of Gat No 74
- South
- Property of Mr Rajershirke of same Gat
- East
- Govt Road Shind - Subedarwadi
- West
- Propery of Mr Rajershirke of Gat No 75
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Umesh D Kumbhar | — |
| Chartered accountant | Amol Totala | — |
| Chartered accountant | Kishor Pandharinath Kale | — |
| Chartered accountant | Yogesh Pandurang Bhagat | — |
| Engineer | K K HOLE and Associates | — |
| Engineer | Suman Narayanconstruction Company | — |
| Engineer | Umesh D Kumbhar | — |
Source: MahaRERA project page. Contact details are not shown.