8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects1,568
Registrations1,648some projects hold several
Completion still due826669 past their date
Median extension4 months61% of registrations extended
Regulatory cases24on 22 projects

8 in 10 registrations run late here

1,648 MahaRERA registrations in Vasai and the places within it

189 not yet due637 extended, not yet due669 past even the latest date153 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Vasai

1,568 projects registered with MahaRERA in this taluka and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Casa SerenaChetan Buildtech LLPDue Nov 2029, extended 4 mo——
Avenue HeightsAvenue RealtorsDue Apr 2031, extended 4 mo——
Imperial Indrapuram D & EImperial Global InfraDue Apr 2031, extended 4 mo——
Samata Co-Operative Housing Society LtdShree Ganesh Builders & DevelopersDue Apr 2029, extended 4 mo——
Shripal SupremeShripal Buildwell Pvt LtdDue Apr 2030, extended 4 mo——
Cloud Nine Wing A & BNine Realcon Infra Pvt LtdDue Apr 2032, extended 4 mo——
Av Pearl Bldg No.4, Wing AAvm Buildcon LLPDue Apr 2031, extended 4 mo——
Urban HomesUrban DevelopersDue Oct 2027, extended 4 mo——
Megh MalharY K Nagar Development CorporationDue Apr 2028, extended 4 mo——
Gokul Hari AnantaMehta VenturesDue Apr 2031, extended 4 mo——
Imperial Indrapuram B & CImperial Global InfraDue Apr 2031, extended 4 mo——
Jay shree Laxmi Chslom Jivdani ConstructionDue Apr 2028, extended 4 mo——
Deep VaibhavDeep LifespaceDue Apr 2031, extended 4 mo——
Star ParadiseStar Builders And DevelopersDue Apr 2032, extended 4 mo——
New Mandar Co-operative Housing Society Ltd.S. P. DevelopersDue Oct 2030, extended 4 mo——
Tania WillowsTania RealtorsDue Jul 2028, extended 4 mo——
Tulip ResidencyKohinoor BuildconDue Apr 2030, extended 4 mo——
Sky Aura Building No 2Divine Mercy RealtorsDue Jul 2030, extended 4 mo——
Ashoka HillsShree Ashoka Builders & DevelopersDue Jan 2030, extended 4 mo——
Guru Govind Singh Nagar Chs LtdOm Sai DevelopersDue Apr 2031, extended 4 mo——
Ruturaj HomesRuturaj HomesDue Apr 2031, extended 4 mo——
Mangal DeepSushma Vivek SinghDue Apr 2030, extended 4 mo——
Shalibhadra HeightsShree Nakoda DevelopersDue Apr 2028, extended 4 mo——
SK HeightsS.s Buildcare Private LimitedDue Apr 2031, extended 4 mo——
Jivdani PrideJivdani Krupa Builders & DevelopersDue Apr 2030, extended 4 mo——
Vasai market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Jsb Homemakers Private Limited9 projects
  2. Shantee Housing8 projects
  3. Shantee Homes Realty Llp6 projects
  4. Shantee Realty And Life Space6 projects
  5. Sunteck Realty Limited6 projects
  6. Viva Winner Venture Relators Llp6 projects
  7. Ameya Builders & Property Developers5 projects
  8. Kawali Builders5 projects
  9. Sanskruti Builder & Developer5 projects
  10. Shree Mahavir Builders And Developers5 projects

Vasai, in questions

How many projects in Vasai run late?

8 in 10 MahaRERA registrations (1,306 of 1,648): their completion date was extended or has passed, data through 22 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Vasai by Deedo. Medians on fewer than 3 deeds are not shown.

Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology