Skip to content
Residential / Group Housing · 1 building · 44 unitsRERA PR1240002502430

Avenue Heights

Deedo IDDP-PAL-0XXS

Completion was pushed back 4 months, to Apr 2031; no MahaRERA orders on record; 0% of its units are booked.

Nilemore, Palghar 401203 · by Avenue Realtors

DeliveryExtended 4 moPromised Dec 2030 · now due Apr 2031RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 44 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2031

  • This projectRegistered 23 Feb 2026, completion promised 31 Dec 2030, revised to 30 Apr 2031.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationPR1240002502430
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PR124000250243023 Feb 202631 Dec 203030 Apr 2031Avenue RealtorsProject page
Documents21

1 document held by Deedo, 20 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Cardcompany.pdf · uploaded 30 Dec 2025Source

Legal

  • Otherssatbara.pdf · uploaded 26 Dec 2025Source
  • Othersannexure a AJSAD.pdf · uploaded 26 Dec 2025Source
  • Othersannexure a NAMIR.pdf · uploaded 26 Dec 2025Source
  • Declaration Form BTitle.pdf · uploaded 26 Dec 2025Source
  • Declaration Form Bform b promoter.pdf · uploaded 26 Dec 2025Source
  • Declaration Form Bsatbara.pdf · uploaded 26 Dec 2025Source
Show all 21 documentsShow fewer documents

Migrated

  • Withdrawal Update Form 1Form 1 Jan to Mar.pdf · uploaded 4 Aug 2026Source
  • Withdrawal Update Form 1Form 1 April to June 2026 (1).pdf · uploaded 4 Aug 2026Source
  • Withdrawal Update Form 2FORM-2 jan to Mar.pdf · uploaded 4 Aug 2026Source
  • Withdrawal Update Form 2FORM-2 April to june.pdf · uploaded 4 Aug 2026Source
  • Withdrawal Update Form 3Form 3 AVENUE REALTORS jan to Mar.pdf · uploaded 4 Aug 2026Source
  • Withdrawal Update Form 3AVENUE HEIGHTS FORM 3 April to june.pdf · uploaded 4 Aug 2026Source

Technical

  • Documentlayout plan.pdf · uploaded 26 Dec 2025Source
  • DocumentDEC-CUM UNDERTAKING.pdf · uploaded 30 Dec 2025Source
  • OthersCC DEC.pdf · uploaded 30 Dec 2025Source
  • OthersAffidavit-No.pdf · uploaded 14 Feb 2026Source
  • OthersCC Confirmation.pdf · uploaded 14 Feb 2026Source

Technical (Architect)

  • DocumentForm 1 April to June 2026 (1).pdf · uploaded 4 Aug 2026Source

Technical (Engineer)

  • DocumentFORM-2 April to june.pdf · uploaded 4 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel S. No. 86/2/pt Plot No. 2, S. No. 86/2/pt Plot No. 3

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
—103 units in all
Address
NilemorePIN 401203
Village
Nilemore, Vasai taluka
Land area for this project
769 sq m (8,277 sq ft)
Permissible built-up area
4,349 sq m (46,817 sq ft)
Sanctioned built-up area
4,349 sq m (46,817 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
19
Developed in phases
No

Survey, CTS, gat or plot numbers

S. No. 86/2/pt Plot No. 2S. No. 86/2/pt Plot No. 3

Land as published on MahaRERA's project page

S. No. 86/2/pt Plot No. 2 & S. No. 86/2/pt Plot No. 3, Pin Code:401203

Boundaries

North
Society
South
Society
East
Society
West
Dp Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking103 units

103 units registered

— · 103 units
TypeCarpet areaUnits
——103

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals1

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
Chartered accountantRamesh Lukad—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Nilemore

All 44 projects in Nilemore · Compare Avenue Heights with another project