Vasai, Palghar
Deedo IDDL-PAL-VASAI8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects1,568
Registrations1,648some projects hold several
Completion still due826669 past their date
Median extension4 months61% of registrations extended
Regulatory cases24on 22 projects
8 in 10 registrations run late here
1,648 MahaRERA registrations in Vasai and the places within it
189 not yet due637 extended, not yet due669 past even the latest date153 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Vasai
1,568 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Hira Apartment Co Operative Housing SocietySai Baba Builders And Developers | Due Jul 2029 | — | — |
| New Gokul Co-Operative Housing Society LtdNew Gokul Developers | Due Dec 2030 | — | — |
| Yashwant PrideRaj Enterprises | Due May 2031 | — | — |
| Dixit EnclavesShivansh Builders & Developers | Due Dec 2029 | — | — |
| New Raj Palace ChslHigh Castle Realtors | Due Jun 2028 | — | — |
| Jas ApartmentVastu Vision Developers | Due Dec 2029 | — | — |
| Dhruv TaraL P Developers | Due Mar 2030 | — | — |
| Abhinandan TowerVeer Global Infraconstruction Limited | Due Dec 2031 | — | — |
| Shajhan SignatureDsquare Signature | Due Aug 2031 | — | — |
| New Leena ChsSai Siddhi Builders And Developers | Due Dec 2030 | — | — |
| Rg HeightsSai Enterprises | Due Dec 2028 | — | — |
| ShamShree Shakti Infra | Due Dec 2029 | — | — |
| Nakshatra DhaamJSB Homemakers Private Limited | Due Jun 2030 | — | — |
| Shripal SignatureShripal Buildwell Pvt Ltd | Due Dec 2029 | — | — |
| Kanti Arvat SkyArvat Realty | Due Dec 2028 | — | — |
| Star LegacyShadab Karari | Due Dec 2029 | — | — |
| Carpentry HeightsOlive Horizon Private Limited | Due Dec 2030 | — | — |
| Comfort AaradhyaComfort Infrastructure & Developers Private Limited | Due Dec 2031 | — | — |
| Dhananjay IconShree Ashoka Realty | Due Dec 2030 | — | — |
| Realtech ValenciaRealtech Lifespace Developers | Due Jun 2031 | — | — |
| ShivneriChintamani Enterprises | Due Dec 2029 | — | — |
| Shri Sai Prasad ChslShiv Shakti Builders And Developers | Due Dec 2031 | — | — |
| Suraksha Smart City - Phase IIConceptual Advisory Services LLP | Due Dec 2031 | — | — |
| PhileshiaVedit Enterprises | Due Mar 2032 | — | — |
| Ananta OneSetuone Infra LLP | Due Dec 2029 | — | — |
Nearby: other talukas in Palghar
Most active promoters
- Jsb Homemakers Private Limited9 projects
- Shantee Housing8 projects
- Shantee Homes Realty Llp6 projects
- Shantee Realty And Life Space6 projects
- Sunteck Realty Limited6 projects
- Viva Winner Venture Relators Llp6 projects
- Ameya Builders & Property Developers5 projects
- Kawali Builders5 projects
- Sanskruti Builder & Developer5 projects
- Shree Mahavir Builders And Developers5 projects
Vasai, in questions
How many projects in Vasai run late?
8 in 10 MahaRERA registrations (1,306 of 1,648): their completion date was extended or has passed, data through 22 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Vasai by Deedo. Medians on fewer than 3 deeds are not shown.
Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology