Residential / Group Housing · 1 building · 16 unitsRERA P99000078085

Dosti Heights

Deedo IDDP-PAL-FRTZ

Completion was pushed back 4 months, to Jul 2027; no MahaRERA orders on record; 0% of its units are booked.

Bandate, Palghar 401401 · by Sai Crystal Builders

DeliveryExtended 4 moPromised Mar 2027 · now due Jul 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 16 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Jul 2027

  • This projectRegistered 25 Nov 2024, completion promised 31 Mar 2027, revised to 31 Jul 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP99000078085
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P9900007808525 Nov 202431 Mar 202731 Jul 2027Sai Crystal BuildersProject page
Documents67

1 document held by Deedo, 66 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardSAI CRYSTAL BUILDERS PANCARD.pdf · uploaded 13 Oct 2024Source
  • Other – FinanceCC Collector to MahaRERA.pdf · uploaded 22 Nov 2024Source

Legal

  • Declaration Form BAffidavit Cum Declaration in Form B.pdf · uploaded 13 Oct 2024Source
  • Legal Title reportSAI CRYSTAL BUILDERS LEGAL SEARCH REPORT.pdf · uploaded 15 Oct 2024Source
  • Other – Legalबंदाठे_40_ब_62_4_Satbara.pdf · uploaded 17 Nov 2024Source
  • Other – LegalLand Purchase Agreement.pdf · uploaded 17 Nov 2024Source

Migrated

  • 1 PAN CardSAI CRYSTAL BUILDERS PANCARD.pdf · uploaded 13 Oct 2024Source
Show all 67 documentsShow fewer documents

Migrated

  • 1 Copy of Layout Approval (in case of layout)Sai Crystal Builders Blue Print.pdf · uploaded 13 Oct 2024Source
  • 1 Declaration in FORM BAffidavit Cum Declaration in Form B.pdf · uploaded 13 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Architect Certificate.pdf · uploaded 13 Oct 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Engineer Certificate.pdf · uploaded 13 Oct 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentSai Crystal Builders CC.pdf · uploaded 13 Oct 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentSai Crystal Builders Blue Print.pdf · uploaded 13 Oct 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure Of Interest Ashirwad Nandivkar.pdf · uploaded 13 Oct 2024Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsDisclosure Of Interest Vijay Khatale.pdf · uploaded 13 Oct 2024Source
  • 1 Copy of the legal title reportSAI CRYSTAL BUILDERS LEGAL SEARCH REPORT.pdf · uploaded 15 Oct 2024Source
  • 1 a Details of encumbrances concerned to FinanceNo Finance Encumbrance Certificate.pdf · uploaded 15 Oct 2024Source
  • 1 Declaration about Commencement CertificateDeclaration about CC.pdf · uploaded 15 Oct 2024Source
  • 1 CERSAI detailsCERSAI Declaration.pdf · uploaded 15 Oct 2024Source
  • 1 Deviation Report with respect to Allotment letterDeviation for allotment.pdf · uploaded 15 Oct 2024Source
  • 1 b Details of encumbrances concerned to LegalNo Finance Encumbrance Certificate.pdf · uploaded 15 Oct 2024Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation for agreement.pdf · uploaded 15 Oct 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - CA Certificate-1.pdf · uploaded 18 Oct 2024Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)Declaration About Rera Designated Bank Accounts Format A.pdf · uploaded 4 Nov 2024Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Kotak Bank Letter Format B.pdf · uploaded 4 Nov 2024Source
  • 1 Disclosure for secured/unsecured finance availed for the projectDisclosure for Secured Unsecured Finance.pdf · uploaded 4 Nov 2024Source
  • 1 Other – TechnicalAnnexure A Final.pdf · uploaded 7 Nov 2024Source
  • 2 Other – Legalबंदाठे_40_ब_62_4_Satbara.pdf · uploaded 17 Nov 2024Source
  • 1 Other – LegalLand Purchase Agreement.pdf · uploaded 17 Nov 2024Source
  • 1 Proforma of Allotment letterAllotment Letter Format Sai Crystal Builders.pdf · uploaded 22 Nov 2024Source
  • 1 Other – FinanceCC Collector to MahaRERA.pdf · uploaded 22 Nov 2024Source
  • 1 Proforma of Agreement for saleAgreement Format Sai Crystal Builders.pdf · uploaded 22 Nov 2024Source
  • Form 1Form 1 Architect 31 12 2024.pdf · uploaded 23 May 2026Source
  • Form 2Form 2 Engineer 31 12 2024.pdf · uploaded 23 May 2026Source
  • Form 3Form 3 CA 31 12 2024.pdf · uploaded 23 May 2026Source
  • Disclosure of Sold and Booked InventorySold Unsold Disclosure 31 12 2024.pdf · uploaded 23 May 2026Source
  • Form 1Form 1 Architect 31 03 2025.pdf · uploaded 23 May 2026Source
  • Form 2Form 2 Engineer 31 03 2025.pdf · uploaded 23 May 2026Source
  • Form 3Form 3 CA 31 03 2025.pdf · uploaded 23 May 2026Source
  • Disclosure of Sold and Booked InventorySold Unsold Disclosure 31 03 2025.pdf · uploaded 23 May 2026Source
  • Withdrawal Update Form 1Form 1 Architect 31 12 2024.pdf · uploaded 23 May 2026Source
  • Withdrawal Update Form 1Form 1 Architect 31 03 2025.pdf · uploaded 23 May 2026Source
  • Withdrawal Update Form 1Form 1 Architect 30 06 2025.pdf · uploaded 23 May 2026Source
  • Withdrawal Update Form 1Form 1 Architect 30 09 2025.pdf · uploaded 23 May 2026Source
  • Withdrawal Update Form 1Form 1 Architect 31 12 2025.pdf · uploaded 23 May 2026Source
  • Withdrawal Update Form 1Form 1 Architect 31 03 2026.pdf · uploaded 23 May 2026Source
  • Withdrawal Update Form 2Form 2 Engineer 31 12 2024.pdf · uploaded 23 May 2026Source
  • Withdrawal Update Form 2Form 2 Engineer 31 03 2025.pdf · uploaded 23 May 2026Source
  • Withdrawal Update Form 2Form 2 Engineer 30 06 2025.pdf · uploaded 23 May 2026Source
  • Withdrawal Update Form 2Form 2 Engineer 30 09 2025.pdf · uploaded 23 May 2026Source
  • Withdrawal Update Form 2Form 2 Engineer 31 12 2025.pdf · uploaded 23 May 2026Source
  • Withdrawal Update Form 2Form 2 Engineer 31 03 2026.pdf · uploaded 23 May 2026Source
  • Withdrawal Update Form 3Form 3 CA 31 12 2024.pdf · uploaded 23 May 2026Source
  • Withdrawal Update Form 3Form 3 CA 31 03 2025.pdf · uploaded 23 May 2026Source
  • Withdrawal Update Form 3Form 3 CA 30 06 2025.pdf · uploaded 23 May 2026Source
  • Withdrawal Update Form 3Form 3 CA 30 09 2025.pdf · uploaded 23 May 2026Source
  • Withdrawal Update Form 3Form 3 CA 31 12 2025.pdf · uploaded 23 May 2026Source
  • Withdrawal Update Form 3Form 3 CA 31 03 2026.pdf · uploaded 23 May 2026Source
  • Withdrawal Update Form 1Form 1 Architect 30 06 2026.pdf · uploaded 21 Jul 2026Source
  • Withdrawal Update Form 2Form 2 Architect 30 06 2026.pdf · uploaded 21 Jul 2026Source
  • Withdrawal Update Form 3Form 3 Architect 30 06 2026.pdf · uploaded 21 Jul 2026Source

Technical

  • DocumentSai Crystal Builders Blue Print.pdf · uploaded 13 Oct 2024Source
  • DocumentSai Crystal Builders Blue Print.pdf · uploaded 13 Oct 2024Source
  • Other – TechnicalAnnexure A Final.pdf · uploaded 7 Nov 2024Source

Technical (Architect)

  • DocumentForm 1 Architect 30 06 2026.pdf · uploaded 21 Jul 2026Source

Technical (Engineer)

  • DocumentForm 2 Architect 30 06 2026.pdf · uploaded 21 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Plot No.4 Gut No.40/B/62/4

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, Shop16 units in all
Address
Plot No.4 Gut No.40/B/62/4, Bandathe, Kelve RoadPIN 401401
Village
Bandate, Palghar taluka
Land area for this project
357 sq m (3,837 sq ft)
Permissible built-up area
606 sq m (6,525 sq ft)
Sanctioned built-up area
606 sq m (6,525 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
109
Developed in phases
No

Survey, CTS, gat or plot numbers

Plot No.4 Gut No.40/B/62/4

Land as published on MahaRERA's project page

Plot No.4 Gut No.40/B/62/4

Boundaries

North
Crystal Park
South
Crystal Park C Wing
East
Internal Road
West
Dirk Allams Plot

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking16 units

0 of 16 units booked (0%), as the promoter reported to MahaRERA

1BHK · 12 unitsShop · 4 units
TypeCarpet areaUnitsBooked
1BHK29.97 sq m · 323 sq ft30
1BHK29.98 sq m · 323 sq ft30
1BHK31.38 sq m · 338 sq ft60
Shop10.05 sq m · 108 sq ft20
Shop10.24 sq m · 110 sq ft20

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSiddhivinayak Associates—
Chartered accountantVirendra K Tare & Co—
EngineerVastu Gaurav Associates—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Bandate

All 4 projects in Bandate · Compare Dosti Heights with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology