Its promised completion date, Dec 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 0% of its units are booked.

Bandate, Palghar 401404 · by Shree Ashapura Realty

Delivery11 mo past duePromised Dec 2025 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 148 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Dec 2025, has passed and MahaRERA does not show it completed

  • This projectRegistered 3 Jan 2020, completion promised 30 Dec 2025, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

6 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP99000023747
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P990000237473 Jan 202030 Dec 202530 Dec 2025M/S Shree Ashapura RealtyProject page
Documents28

1 document held by Deedo, 27 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN CARD.pdf · uploaded 14 Nov 2019Source

Legal

  • Declaration Form BFORM B.pdf · uploaded 9 Nov 2019Source
  • Legal Title reportTITLE REPORT.pdf · uploaded 16 Nov 2019Source
  • OtherOTHERS LETTER.pdf · uploaded 30 Dec 2019Source

Migrated

  • 1 Details of encumbrancesNO ENCUMBRANCE.pdf · uploaded 9 Nov 2019Source
  • 1 Copy of Layout Approval (in case of layout)PLANS.pdf · uploaded 9 Nov 2019Source
  • 1 Building Plan Approval / NA Order for plotted developmentA1.pdf · uploaded 9 Nov 2019Source
Show all 28 documentsShow fewer documents

Migrated

  • 2 Building Plan Approval / NA Order for plotted developmentA3.pdf · uploaded 9 Nov 2019Source
  • 3 Building Plan Approval / NA Order for plotted developmentA5.pdf · uploaded 9 Nov 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 9 Nov 2019Source
  • 1 Declaration in FORM BFORM B.pdf · uploaded 9 Nov 2019Source
  • 1 PAN CardPAN CARD.pdf · uploaded 14 Nov 2019Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT_compressed.pdf · uploaded 14 Nov 2019Source
  • 1 Copy of the legal title reportTITLE REPORT.pdf · uploaded 16 Nov 2019Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA ASHAPURA.pdf · uploaded 22 Nov 2019Source
  • 1 Proforma of Allotment letterAgreement Draft.pdf · uploaded 27 Nov 2019Source
  • 1 OtherOTHERS LETTER.pdf · uploaded 30 Dec 2019Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCH.pdf · uploaded 15 Sep 2020Source
  • 1 Details of Restarting of Construction work post lockdownCOVID-19.pdf · uploaded 15 Sep 2020Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)ASHAPURA LETTER.pdf · uploaded 25 Nov 2020Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)16 No Progress Letter MahaRERA Copy.pdf · uploaded 29 Jun 2021Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)No Progress Letter MahaRERA.pdf · uploaded 12 Jul 2021Source

Technical

  • DocumentPLANS.pdf · uploaded 9 Nov 2019Source
  • DocumentA1.pdf · uploaded 9 Nov 2019Source
  • DocumentA3.pdf · uploaded 9 Nov 2019Source
  • DocumentA5.pdf · uploaded 9 Nov 2019Source

Technical (Architect)

  • DocumentNo Progress Letter MahaRERA.pdf · uploaded 12 Jul 2021Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel GUT NO 54

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1.5 BHK, 1BHK, 1RK, Shop no 1, Shop no 2, Shop no 3, Shop no 4, Shop no 5, Shop no 6, Shiop no 2, Shop no 7148 units in all
Address
Gut No 54, Palghar, PalgharPIN 401404
Village
Bandate, Palghar taluka
Land area for this project
5,300 sq m (57,049 sq ft)
Permissible built-up area
6,193 sq m (66,661 sq ft)
Sanctioned built-up area
5,193 sq m (55,897 sq ft)
Designated bank account
109
Developed in phases
Yes

Survey, CTS, gat or plot numbers

GUT NO 54

Land as published on MahaRERA's project page

GUT NO 54

Boundaries

North
G No 53
South
Gut No 55
East
Gut No 56
West
Gut No 57

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking148 units

0 of 148 units booked (0%), as the promoter reported to MahaRERA

1.5 BHK · 20 units1BHK · 75 units1RK · 36 unitsShop no 1 · 3 unitsShop no 2 · 2 unitsShop no 3 · 3 unitsShop no 4 · 3 unitsShop no 5 · 2 unitsShop no 6 · 2 unitsShiop no 2 · 1 unitShop no 7 · 1 unit
BuildingTypeCarpet areaUnitsBooked
Type A11.5 BHK38.35 sq m · 413 sq ft40
Type A11BHK24.6 sq m · 265 sq ft40
Type A11BHK25.17 sq m · 271 sq ft40
Type A11RK16.47 sq m · 177 sq ft40
Type A11RK18.94 sq m · 204 sq ft80
Type A1Shop no 111.31 sq m · 122 sq ft10
Type A1Shop no 214.44 sq m · 155 sq ft10
Type A1Shop no 310.5 sq m · 113 sq ft10
Show all 49 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Type A1Shop no 414.44 sq m · 155 sq ft10
Type A1Shop no 514.44 sq m · 155 sq ft10
Type A1Shop no 610.29 sq m · 111 sq ft10
Type A21.5 BHK38.49 sq m · 414 sq ft40
Type A21BHK29.79 sq m · 321 sq ft40
Type A21RK26.55 sq m · 286 sq ft160
Type A2Shiop no 210.35 sq m · 111 sq ft10
Type A2Shop no 112.38 sq m · 133 sq ft10
Type A2Shop no 314.44 sq m · 155 sq ft10
Type A2Shop no 414.44 sq m · 155 sq ft10
Type A2Shop no 510.5 sq m · 113 sq ft10
Type A2Shop no 614.44 sq m · 155 sq ft10
Type A2Shop no 711.31 sq m · 122 sq ft10
Type A31BHK23.2 sq m · 250 sq ft30
Type A31BHK23.52 sq m · 253 sq ft30
Type A31BHK24.27 sq m · 261 sq ft30
Type A31BHK25.36 sq m · 273 sq ft30
Type A31BHK26.98 sq m · 290 sq ft10
Type A31BHK27.77 sq m · 299 sq ft10
Type A31BHK30.19 sq m · 325 sq ft10
Type A31RK17.16 sq m · 185 sq ft60
Type A31RK20.32 sq m · 219 sq ft10
Type A31RK20.6 sq m · 222 sq ft10
Type A41.5 BHK36.86 sq m · 397 sq ft40
Type A41BHK23.89 sq m · 257 sq ft40
Type A41BHK24.22 sq m · 261 sq ft40
Type A41BHK25.6 sq m · 276 sq ft40
Type A41BHK27.07 sq m · 291 sq ft40
Type A41BHK27.76 sq m · 299 sq ft40
Type A4Shop no 129.86 sq m · 321 sq ft10
Type A4Shop no 230.83 sq m · 332 sq ft10
Type A4Shop no 330.51 sq m · 328 sq ft10
Type A4Shop no 442.49 sq m · 457 sq ft10
Type A51.5 BHK29.19 sq m · 314 sq ft40
Type A51BHK26.83 sq m · 289 sq ft120
Type A51BHK31.8 sq m · 342 sq ft10
Type A51BHK32.47 sq m · 350 sq ft10
Type A61.5 BHK29.19 sq m · 314 sq ft40
Type A61BHK26.83 sq m · 289 sq ft120
Type A61BHK31.8 sq m · 342 sq ft10
Type A61BHK32.47 sq m · 350 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectRender Point—
Chartered accountantNehali & Company—
EngineerHemant Pathak—
OtherK N Pandey—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology