Sai Crystal Builders
Deedo IDDD-V63VNone of 1 registration has reached its promised completion date yet.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Dosti HeightsP99000078085 | Bandate | Certificate Signed | 31 Mar 2027 | 31 Jul 2027 | +4 mo |
Sai Crystal Builders, in questions
Does Sai Crystal Builders finish projects on time?
None of its 1 MahaRERA registration has reached its promised completion date yet.
How many projects has Sai Crystal Builders registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Sai Crystal Builders have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.