Takali, Nagpur
Deedo IDDL-NGP-TAKALI9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects8
Registrations8
Completion still due44 past their date
Median extension12 months63% of registrations extended
Regulatory cases0none on MahaRERA's lists
9 in 10 registrations run late here
8 MahaRERA registrations in Takali
1 not yet due3 extended, not yet due4 past even the latest date
Extended registrations moved their completion date by a median of 12 months.
Projects in Takali
8 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Silver EstateTirupati Developers | Due Oct 2031, extended 4 mo | — | — |
| Swarneem Keshavam CityKeshavam - Infra | Due Jul 2031, extended 4 mo | — | — |
| Keshavam City 8Keshavam - Infra | Completed | — | — |
| Vijaya AanganVijaya Ghanshyam Hatwar | Completed | — | — |
| Aaditya Premium 5Aaditya Infrastructures | Completed | — | — |
Nearby: other villages in Hingna
Most active promoters
- Aaditya Infrastructures2 projects
- Keshavam Infra2 projects
- Parkland Lifestyle1 project
- R S Enterprises1 project
- Tirupati Developers1 project
- Vijaya Ghanshyam Hatwar1 project
Takali, in questions
How many projects in Takali run late?
9 in 10 MahaRERA registrations (7 of 8): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Takali by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology