RERA projects in Raipur
7 projects under 7 MahaRERA registrations, registered 2020–2026. 86% have a completion date extended beyond the one promised.
Locality
7RERA projects
7Registrations
7Completion still due0 past their completion date
4 monthsMedian extension beyond promised date86% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2020 | 1 |
| 2021 | 0 |
| 2022 | 1 |
| 2023 | 0 |
| 2024 | 1 |
| 2025 | 1 |
| 2026 | 3 |
Projects in Raipur
7 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Varsha NagariAngad Milaji kale | PP1190002600942 | 25 Jun 2026 | 31 May 2031 | 30 Sep 2031 | Extended 4 mo | 0 |
| Crown ValleyCrown Valley | PP1190002502893 | 18 Mar 2026 | 31 Mar 2031 | 31 Jul 2031 | Extended 4 mo | 0 |
| Kanchan Nagari 10 (Part)Laxman Krushnarao Dalal | PP1190002502754 | 12 Mar 2026 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Janki ParkPrime Infrastructure | P50500080600 | 19 Jun 2025 | 31 Mar 2030 | 31 Jul 2030 | Extended 4 mo | 0 |
| Raja Bhoj NagarJiyalal Sharnagat, Dilip Kawale, Daliram Sharnagat, Sou. Alka Sharnagat, Sampatiprasad Patle | P50500056417 | 31 May 2024 | 31 Mar 2029 | 31 Jul 2029 | Extended 4 mo | 0 |
| Kanchan Nagari - 2Narendra Uttam Larokar | P50500047415 | 27 Oct 2022 | 31 Dec 2026 | 31 Dec 2026 | Not yet due | 0 |
| Shakuntala ParkPrime Properties | P50500025835 | 19 Jul 2020 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
Other localities in Hingna
Most active promoters
By projects registered here, as named on MahaRERA.
- Angad Milaji kale1 project
- Crown Valley1 project
- Jiyalal Sharnagat, Dilip Kawale, Daliram Sharnagat, Sou. Alka Sharnagat, Sampatiprasad Patle1 project
- Laxman Krushnarao Dalal1 project
- Narendra Uttam Larokar1 project
- Prime Infrastructure1 project
- Prime Properties1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology