5 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects10
Registrations10
Completion still due82 past their date
Median extension4 months40% of registrations extended
Regulatory cases2on 1 project

5 in 10 registrations run late here

10 MahaRERA registrations in Sondapar

1 completed4 not yet due4 extended, not yet due1 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Sondapar

10 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Mahalaxmi Nagar-49 AyanaMahalaxmi Infraventures LLPDue Mar 2031, extended 4 mo——
Vijaya SaraswatiThe Squarefeet CompanyCompleted——
Karamchand GreensNeerja Realtors Private LimitedCompleted——
Mahalaxmi Nagar 28 Sector - 1Ara Habitats LLPCompleted——
Mahalaxmi Nagar 28 Sector - 2Ara Habitats LLPCompleted——
All 10 projects →
Sondapar market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Ara Habitats Llp2 projects
  2. Om Shivam Buildcon Private Limited2 projects
  3. Mahalaxmi Infraventures LLP1 project
  4. Neerja Realtors Private Limited1 project
  5. Ravindra Jaydeo Ashtankar1 project
  6. Royal Fort Developers1 project
  7. The Squarefeet Company1 project
  8. Vijaya Hatwar And 1 Others1 project

Sondapar, in questions

How many projects in Sondapar run late?

5 in 10 MahaRERA registrations (5 of 10): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Sondapar by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology