RERA projects in Wanadongri

47 projects under 51 MahaRERA registrations, registered 2017–2026. 35% have a completion date extended beyond the one promised.

Locality
47RERA projects
51Registrationssome projects hold several
34Completion still due17 past their completion date
4 monthsMedian extension beyond promised date35% of registrations extended
0Regulatory casesnone on MahaRERA's lists
28Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20172
20181
20192
20201
20216
202212
20236
20248
20256
20267

Projects in Wanadongri

47 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Radhika Vihar - Braj BhoomiM & R Infra Pavers Private LimitedPP119000260244819 Oct 202631 Dec 2031—Not yet due0
Kanchan Nagari 16Shubh Infraventures LLPPP119000260233515 Oct 202631 Mar 2030—Not yet due0
Artham OneArtham InfrastructurePR119000260195517 Sep 202631 Dec 203031 Dec 2030Not yet due0
KosaladhishParth DevelopersPM11900026000337 Apr 202631 Mar 203031 Jul 2030Extended 4 mo0
Kanchan Nagari - 7 (Part)Deshmukh Trading Company Private LimitedPP119000250306127 Mar 202631 Dec 202930 Apr 2030Extended 4 mo0
Galaxy 5Konark InfraPR119000250210820 Jan 202631 Mar 202731 Jul 2027Extended 4 mo0
Raghukul ParkSanjay Ramkrushna JagtapPP1190002500922, PP119000250295924 Sep 202531 Jan 203131 Jan 2031Not yet due0
Raghukul Park-4Sanjay Ramkrushna JagtapPP119000250082917 Sep 202515 Jul 203015 Jul 2030Not yet due0
Tulsi Nagari-ITarasingh Bhimsingh Rajput Hanumansingh Bhimsingh Rajput and Bhaiyyalal Singh Bhimsingh RajputPP11900025002307 Jul 202531 Mar 202831 Jul 2028Extended 4 mo0
Greenfield-5L G Developers And BuildersP5050008060619 Jun 202531 Mar 202731 Jul 2027Extended 4 mo0
Maa Narmada Nagari-4Nareshkumar Sureshrao DevgadeP505000794326 Mar 202531 Dec 202830 Apr 2029Extended 4 mo0
Moreshwar Park-9Prasanna PlannersP5050007900131 Jan 202531 Dec 2029—Not yet due0
Kanchan Nagari-12M/s. Shubh InfrastructureP5050007862027 Dec 202431 Dec 202831 Dec 2028Not yet due0
Silver WindsTirupati DevelopersP5050007720329 Jul 202431 Jul 202930 Nov 2029Extended 4 mo0
Narmada Vihar-8Ritesh R. Sharma, Aditya R. Sharma, Raghav R. SharmaP505000769539 Jul 202431 Dec 202931 Dec 2029Not yet due0
Maa Narmada Nagari-3Nareshkumar Sureshrao DevgadeP5050007681528 Jun 202431 Dec 2027—Not yet due0
Narmada ResidencyAnil Radheshyam SharmaP5050007663918 Jun 202431 Dec 203131 Dec 2031Not yet due0
Elite HomesElite Construction Co.P5050005574416 Apr 202431 Aug 202731 Aug 2027Not yet due0
Abhay Residency IIModokar Infra Private LimitedP5050005442219 Jan 202431 Dec 202630 Apr 2027Extended 4 mo0
Samarth NagarSamartha DevelopersP505000541983 Jan 202430 Jun 202830 Oct 2028Extended 4 mo0
Narmada Vihar - 5Shree Krishna AssociatesP5050005301410 Oct 202331 Dec 202731 Dec 2027Not yet due0
Kh. No. 362, Wanadongri, NagpurRohan Sunil PedgaonkarP505000511941 Jun 202311 Oct 202711 Feb 2028Extended 4 mo0
Shree Balaji HeightsGayatri BuildconP5050005103122 May 202331 Mar 203331 Jul 2033Extended 4 mo0
Raghukul Park IBhagiratha AssociatesP505000500176 Mar 202310 Jan 202810 Jan 2028Not yet due0
Chaitanya Vihar-2Chaitanya Gruhanirman Sahakari SansthaP505000493027 Feb 202331 Dec 202631 Dec 2026Not yet due0

Other localities in Hingna

Most active promoters

By projects registered here, as named on MahaRERA.

  1. L G Developers And Builders3 projects
  2. Anil Radheshyam Sharma2 projects
  3. Konark Builders & Develoepers2 projects
  4. Nareshkumar Sureshrao Devgade2 projects
  5. Sanjay Ramkrushna Jagtap2 projects
  6. Artham Infrastructure1 project
  7. Bhagiratha Associates1 project
  8. Chaitanya Gruhanirman Sahakari Sanstha1 project
  9. Deshmukh Trading Company Private Limited1 project
  10. Devikar Land Developer1 project
Data through19 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology