23 projects under 23 MahaRERA registrations, registered 2017–2026. 22% have a completion date extended beyond the one promised.

23RERA projects
23Registrations
17Completion still due6 past their completion date, 2 marked completed
18 monthsMedian extension beyond promised date22% of registrations extended
0Regulatory casesnone on MahaRERA's lists
7Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20174
20180
20190
20200
20210
20221
20235
20245
20256
20262

Projects in Isasani (Ct)

23 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Aaditya Premium 10Balaji DevlopersPP119000260113213 Jul 202623 Jan 2029—Not yet due0
Sumangal Vihar Phase 02Sunil Laddhad And Nimish LaddhadPR119101260082917 Jun 202631 Mar 2031—Not yet due0
Anandam Elite - Isasani 87Rajesh Amrutlal VasaniPP119000250185123 Dec 202531 Dec 2027—Not yet due0
Harbans Park Phase 3Harbans Creation (Aop)PR119000250179515 Dec 202531 Dec 2027—Not yet due0
Shreenidhi Estate-VIShri Sai Builders And DevelopersPP119000250131820 Oct 202531 Dec 2030—Not yet due0
Elite Enclave 1Harbans Creation (Aop)P5050007957917 Mar 202531 Dec 2028—Not yet due0
Oasis 32Vivek HusukaleP5050007923018 Feb 202531 Dec 2025—Promised date passed0
Oasis 33Nagorao Shankarrao JaikarP5050007923318 Feb 202531 Dec 2027—Not yet due0
A2 UniversalAditya Anagha Multi State Credit Co-Operative Society LimitedP5050007823029 Nov 202431 Dec 2036—Not yet due0
Narmada Vihar-7Sharma DevelopersP5050007747216 Aug 202431 Dec 2028—Completed0
Sunrise ParkDariyana Gurmukhdas RohraP505000564965 Jun 202431 Mar 2029—Not yet due0
Aadhar Nagri - IIIRevati Construction And DevelopersP5050005495821 Feb 202431 Jul 2026—Promised date passed0
Narmada Vihar-6Ritesh Radheshyam SharmaP5050005425510 Jan 202431 Dec 2028—Not yet due0
Neel CityNeilgagaan ConsttructionP5050005395318 Dec 20235 Oct 2029—Not yet due0
Kanchan Nagari-13Shubh BuildconP5050005391411 Dec 202331 Dec 2027—Not yet due0
Shubhlaxmi NagriM/s. Shubhlaxmi DevelopersP5050005370522 Nov 202331 Dec 2027—Not yet due0
Kamal NagarSachin Madhavrao Ganvir and Sumant Madhaorao GanvirP5050005325823 Oct 202331 Mar 2027—Not yet due0
Atharva ResidencyVitthal Ramchandra Rao BajiraoP5050005150523 Jun 202330 Jun 2026—Promised date passed0
Harbans ParkSatpal Singh Sethi And OthersP5050004698526 Sep 202231 Jul 202431 Jul 2027Extended 36 mo0
Shrieenidhi Estate IsasaniShri Sai Builders And DevelopersP5050001443530 Nov 201730 Sep 202030 Mar 2022Extended 18 mo0
FlorenceBalaji InfraP505000141289 Nov 201730 Mar 202130 Jun 2024Extended 39 mo0
Sumangal ViharSunil Laddhad & Nimish Laddhad (AOP)P5050000704217 Aug 201730 Mar 202631 Mar 2027Extended 12 mo0
Radhe GreensHBK InfrastructuresP5050000658714 Aug 201731 Jul 201831 Jul 2019Completed0

Other localities in Hingna

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Harbans Creation (Aop)2 projects
  2. Shri Sai Builders And Developers2 projects
  3. Aditya Anagha Multi State Credit Co-Operative Society Limited1 project
  4. Balaji Devlopers1 project
  5. Balaji Infra1 project
  6. Dariyana Gurmukhdas Rohra1 project
  7. HBK Infrastructures1 project
  8. M/s. Shubhlaxmi Developers1 project
  9. Nagorao Shankarrao Jaikar1 project
  10. Neilgagaan Consttruction1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology