RERA projects in Isasani (Ct)
23 projects under 23 MahaRERA registrations, registered 2017–2026. 22% have a completion date extended beyond the one promised.
23RERA projects
23Registrations
17Completion still due6 past their completion date, 2 marked completed
18 monthsMedian extension beyond promised date22% of registrations extended
0Regulatory casesnone on MahaRERA's lists
7Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 4 |
| 2018 | 0 |
| 2019 | 0 |
| 2020 | 0 |
| 2021 | 0 |
| 2022 | 1 |
| 2023 | 5 |
| 2024 | 5 |
| 2025 | 6 |
| 2026 | 2 |
Projects in Isasani (Ct)
23 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Aaditya Premium 10Balaji Devlopers | PP1190002601132 | 13 Jul 2026 | 23 Jan 2029 | — | Not yet due | 0 |
| Sumangal Vihar Phase 02Sunil Laddhad And Nimish Laddhad | PR1191012600829 | 17 Jun 2026 | 31 Mar 2031 | — | Not yet due | 0 |
| Anandam Elite - Isasani 87Rajesh Amrutlal Vasani | PP1190002501851 | 23 Dec 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Harbans Park Phase 3Harbans Creation (Aop) | PR1190002501795 | 15 Dec 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Shreenidhi Estate-VIShri Sai Builders And Developers | PP1190002501318 | 20 Oct 2025 | 31 Dec 2030 | — | Not yet due | 0 |
| Elite Enclave 1Harbans Creation (Aop) | P50500079579 | 17 Mar 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| Oasis 32Vivek Husukale | P50500079230 | 18 Feb 2025 | 31 Dec 2025 | — | Promised date passed | 0 |
| Oasis 33Nagorao Shankarrao Jaikar | P50500079233 | 18 Feb 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| A2 UniversalAditya Anagha Multi State Credit Co-Operative Society Limited | P50500078230 | 29 Nov 2024 | 31 Dec 2036 | — | Not yet due | 0 |
| Narmada Vihar-7Sharma Developers | P50500077472 | 16 Aug 2024 | 31 Dec 2028 | — | Completed | 0 |
| Sunrise ParkDariyana Gurmukhdas Rohra | P50500056496 | 5 Jun 2024 | 31 Mar 2029 | — | Not yet due | 0 |
| Aadhar Nagri - IIIRevati Construction And Developers | P50500054958 | 21 Feb 2024 | 31 Jul 2026 | — | Promised date passed | 0 |
| Narmada Vihar-6Ritesh Radheshyam Sharma | P50500054255 | 10 Jan 2024 | 31 Dec 2028 | — | Not yet due | 0 |
| Neel CityNeilgagaan Consttruction | P50500053953 | 18 Dec 2023 | 5 Oct 2029 | — | Not yet due | 0 |
| Kanchan Nagari-13Shubh Buildcon | P50500053914 | 11 Dec 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Shubhlaxmi NagriM/s. Shubhlaxmi Developers | P50500053705 | 22 Nov 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Kamal NagarSachin Madhavrao Ganvir and Sumant Madhaorao Ganvir | P50500053258 | 23 Oct 2023 | 31 Mar 2027 | — | Not yet due | 0 |
| Atharva ResidencyVitthal Ramchandra Rao Bajirao | P50500051505 | 23 Jun 2023 | 30 Jun 2026 | — | Promised date passed | 0 |
| Harbans ParkSatpal Singh Sethi And Others | P50500046985 | 26 Sep 2022 | 31 Jul 2024 | 31 Jul 2027 | Extended 36 mo | 0 |
| Shrieenidhi Estate IsasaniShri Sai Builders And Developers | P50500014435 | 30 Nov 2017 | 30 Sep 2020 | 30 Mar 2022 | Extended 18 mo | 0 |
| FlorenceBalaji Infra | P50500014128 | 9 Nov 2017 | 30 Mar 2021 | 30 Jun 2024 | Extended 39 mo | 0 |
| Sumangal ViharSunil Laddhad & Nimish Laddhad (AOP) | P50500007042 | 17 Aug 2017 | 30 Mar 2026 | 31 Mar 2027 | Extended 12 mo | 0 |
| Radhe GreensHBK Infrastructures | P50500006587 | 14 Aug 2017 | 31 Jul 2018 | 31 Jul 2019 | Completed | 0 |
Other localities in Hingna
- Wanadongri45 projects
- Hingna42 projects
- Kothewada21 projects
- Nagalwadi (Ct)14 projects
- Waddhamna12 projects
- Sondapar10 projects
- Sukali(Gupchup)10 projects
- Takali8 projects
- Kanholi7 projects
- Mondha7 projects
- Raipur7 projects
- Salaidabha6 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- Harbans Creation (Aop)2 projects
- Shri Sai Builders And Developers2 projects
- Aditya Anagha Multi State Credit Co-Operative Society Limited1 project
- Balaji Devlopers1 project
- Balaji Infra1 project
- Dariyana Gurmukhdas Rohra1 project
- HBK Infrastructures1 project
- M/s. Shubhlaxmi Developers1 project
- Nagorao Shankarrao Jaikar1 project
- Neilgagaan Consttruction1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology