8 projects under 8 MahaRERA registrations, registered 2017–2024. 13% have a completion date extended beyond the one promised.

8RERA projects
8Registrations
3Completion still due5 past their completion date, 4 marked completed
12 monthsMedian extension beyond promised date13% of registrations extended
0Regulatory casesnone on MahaRERA's lists
7Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20172
20181
20191
20200
20210
20221
20231
20242

Projects in Narsala

8 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Nand Yashoda HighrriseNandiish Builders And DevelopersP505000773256 Aug 202430 Dec 2030—Not yet due0
Rai Galaxy - IIIR Rai Udyog Builders LLPP505000564905 Jun 202431 Mar 2027—Not yet due0
Nitika ResidencyGurmukh Singh BhasinP505000508223 May 202331 Mar 2026—Promised date passed0
Dhanshree 2Dhanshree HomesP5050004739727 Oct 202231 Dec 2026—Not yet due0
Neel Vihar 1Neelgagan DeevelopersP5050001991813 Mar 201930 Mar 2025—Completed0
Siddhi Vinayak RegencyArjun ShahaneP5050001707611 Jul 201831 Dec 2019—Completed0
Ramkrishna NagariRamkrishna DevelopersP5050000667416 Aug 201731 Dec 201731 Dec 2018Completed0
Neel Vihar Wing cNeel Gagan DevelopersP505000037146 Aug 201730 Jun 2018—Completed0

Other localities in Nagpur (Rural)

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Arjun Shahane1 project
  2. Dhanshree Homes1 project
  3. Gurmukh Singh Bhasin1 project
  4. Nandiish Builders And Developers1 project
  5. Neelgagan Deevelopers1 project
  6. Neel Gagan Developers1 project
  7. Ramkrishna Developers1 project
  8. R Rai Udyog Builders LLP1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology