Nari, Nagpur

Deedo IDDL-NGP-NARI

6 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects9
Registrations11some projects hold several
Completion still due83 past their date
Median extension4 months36% of registrations extended
Regulatory cases0none on MahaRERA's lists

6 in 10 registrations run late here

11 MahaRERA registrations in Nari

5 not yet due3 extended, not yet due3 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Nari

9 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Swapnapurtee - A Project by NMCSandeep Dwellers Pvt. Ltd.Due Jul 2030——
Rai CrestRai Udyog Unity Mediscience Private LimitedDue Mar 2030——
Ashadeep EliteAshadeepbuilders & Developers LLPDue Sep 2030——
Kdr PlatinumKdr BuilderDue Apr 2029, extended 4 mo——
Leverage Green Parks Phase-IILeverage Realtors Private LimitedDue Apr 2027, extended 4 mo——
All 9 projects →
Nari market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Ashadeepbuilders & Developers LLP1 project
  2. Bhavya Infraventures Private Limited1 project
  3. Jarry Profits1 project
  4. Kdr Builder1 project
  5. Kdr Builders1 project
  6. Leverage Realtors Private Limited1 project
  7. Rai Udyog Unity Mediscience Private Limited1 project
  8. Raj Sakhare1 project
  9. Sandeep Dwellers Pvt. Ltd1 project
  10. Shrivas Realties1 project

Nari, in questions

How many projects in Nari run late?

6 in 10 MahaRERA registrations (6 of 11): their completion date was extended or has passed, data through 6 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nari by Deedo. Medians on fewer than 3 deeds are not shown.

Data through6 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology