RERA projects in Khamla
8 projects under 8 MahaRERA registrations, registered 2025–2026. 75% have a completion date extended beyond the one promised.
Locality
8RERA projects
8Registrations
8Completion still due0 past their completion date
4 monthsMedian extension beyond promised date75% of registrations extended
0Regulatory casesnone on MahaRERA's lists
12Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2025 | 1 |
| 2026 | 7 |
Projects in Khamla
8 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Vivek ApartmentR L Infraventure | PR1190002602318 | 15 Oct 2026 | 30 Sep 2030 | — | Not yet due | 0 |
| Shri Ameya ApartmentsK.k. Associates | PR1190002602310 | 14 Oct 2026 | 31 Aug 2031 | — | Not yet due | 0 |
| Sayalee ApartmentVaijnath Associates | PR1190002601108 | 9 Jul 2026 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Shrinivas ApartmentsUrban Terraces | PR1190002600586 | 1 Jun 2026 | 28 Feb 2029 | 28 Jun 2029 | Extended 4 mo | 0 |
| Shiv-Sudha LifestyleLifestyle Infrastructure | PR1190002503025 | 23 Mar 2026 | 30 Sep 2029 | 30 Jan 2030 | Extended 4 mo | 0 |
| Shreekrishna HemprabhaShree Krishna Infraventures | PR1190002502981 | 18 Mar 2026 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| Sukh SagarOmkara Buildcon | PR1190002502631 | 6 Mar 2026 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Prajakta La MaisonMadhuprabha Constructions Private Limited | PR1190002501195 | 13 Oct 2025 | 31 Aug 2028 | 31 Dec 2028 | Extended 4 mo | 0 |
Other localities in Nagpur (Urban)
Most active promoters
By projects registered here, as named on MahaRERA.
- K.k. Associates1 project
- Lifestyle Infrastructure1 project
- Madhuprabha Constructions Private Limited1 project
- Omkara Buildcon1 project
- R L Infraventure1 project
- Shree Krishna Infraventures1 project
- Urban Terraces1 project
- Vaijnath Associates1 project
Data through15 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology