Skip to content

Ajni, Nagpur

Deedo IDDL-NGP-AJNI

7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects9
Registrations9
Completion still due72 past their date
Median extension4 months44% of registrations extended
Regulatory cases0none on MahaRERA's lists

7 in 10 registrations run late here

9 MahaRERA registrations in Ajni

3 not yet due4 extended, not yet due2 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Ajni

9 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Vrindavan ApartmentsDelta DevelopersDue Dec 2030——
Mahendra SkywalkMahendra RedevelopersDue Dec 2030——
Shiv Shaurya By MahendraMahendra Shyamrao TaywadeDue Apr 2029, extended 4 mo——
Poorvi HeightsSrikant PARTHASARTHY SampathDue Apr 2027, extended 4 mo——
Mithila ApartmentA B InfrastructureDue Apr 2028, extended 4 mo——
All 9 projects →
Ajni market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. A B Infrastructure1 project
  2. Atharvashree Infrastructure1 project
  3. Delta Developers1 project
  4. Mahendra Redevelopers1 project
  5. Mahendra Shyamrao Taywade1 project
  6. Sachin Ashok Khare1 project
  7. Sanskruti Infra1 project
  8. Srikant PARTHASARTHY Sampath1 project
  9. Tg Puri Infraventures Private Limited1 project

Ajni, in questions

How many projects in Ajni run late?

7 in 10 MahaRERA registrations (6 of 9): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Ajni by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology