5 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects19
Registrations19
Completion still due118 past their date
Median extension4 months21% of registrations extended
Regulatory cases2on 2 projects

5 in 10 registrations run late here

19 MahaRERA registrations in Somalwada

2 completed7 not yet due4 extended, not yet due6 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Somalwada

19 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Pebbles 21Space AssociatesDue Mar 2029——
Trident ParkShantanu Vinod RautDue Jul 2029——
One RiseMahalaxmi Infraprojects Private LimitedDue Nov 2031, extended 4 mo——
Shree Gajanan Vihar VShri Gajanan InfraDue Oct 2030, extended 4 mo——
Galaxy Mansion- 18Galaxy AssociatesDue Jul 2027, extended 4 mo——
All 19 projects →
Somalwada market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Abhay Haridas Jinde1 project
  2. Ankit Construction1 project
  3. Galaxy Associates1 project
  4. Gulab Tulsiram Wanjari1 project
  5. Landmarks Orchid Homes Infraventures1 project
  6. Mahalaxmi Infraprojects Private Limited1 project
  7. Mangala Kashinathji Dhage1 project
  8. M K Patil Constructions1 project
  9. Niraj Madhukar Rahate1 project
  10. Parth Developers1 project

Somalwada, in questions

How many projects in Somalwada run late?

5 in 10 MahaRERA registrations (10 of 19): their completion date was extended or has passed, data through 22 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Somalwada by Deedo. Medians on fewer than 3 deeds are not shown.

Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology