Niraj Pralhadrao Padgilwar
Deedo IDDD-EK7WOf 3 registrations whose promised date has arrived, 3 kept it (100%).
Delivery record
None of 3 registrations with dates has moved or missed its RERA date
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Saidwarka AppartmentP50900002432 | Kosara | Certificate Signed | 30 Dec 2018 | 30 Dec 2018 | On date |
| Saivilla AppartmentP50900005775 | Chandrapur (M Cl) | Completed | 30 Dec 2018 | — | On date |
| Sai Awas ApartmentP50900020406 | Datala | Completed | 30 Dec 2021 | — | On date |
Niraj Pralhadrao Padgilwar, in questions
Does Niraj Pralhadrao Padgilwar finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 3 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Niraj Pralhadrao Padgilwar registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 3 completed on MahaRERA.
Does Niraj Pralhadrao Padgilwar have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.