Mangesh Dashrath Gaikar

Deedo IDDD-FAT5

Of 12 registrations whose promised date has arrived, 9 kept it (75%). The rest ran a median 4 mo late.

Projects1919 RERA registrations
Kept RERA date75%Maharashtra: 73%
Median delay4 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases2no insolvency

Delivery record

5 of 19 registrations with dates moved or missed their RERA date · months late against the original promise

Show all 19 registrations

19 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

CaseProjectDate
DeregisteredMangeshi NeptuneDeregistered: Mangeshi NeptuneNot on record
DeregisteredMangeshi EarthDeregistered: Mangeshi EarthNot on record

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Mangeshi SanskarP51700008382KhadegolavaliCertificate Signed30 Jun 201830 Jun 2018On date
Mangeshi CrystalP51700009923ChikangharCertificate Signed30 Jun 201830 Jun 2018On date
Ussh KiranP51600012292Nashik (M Corp.)Certificate Signed30 Jun 201830 Jun 2018On date
Mangeshi City IIIP51700016947Kalyandombivali (M Corp.)Certificate Signed30 May 202230 May 2022On date
Mangeshi JupiterP51700024517Vadavali Bk.Certificate Signed30 Dec 202430 Dec 2024On date
Mangeshi ImperialP51700034115ChikangharCertificate Signed31 May 202631 May 2026+6 mo*
Mangeshi MarvelP51700034332ChikangharCertificate Signed31 May 202631 May 2026On date
Mangeshi WoodsP51700034351ChikangharCertificate Signed30 Nov 202530 Nov 2025On date
Mangeshi RoyaleP51700034444ChikangharCertificate Signed31 May 202631 May 2026On date
Mangeshi TulipP51700047949GandhareCertificate Signed30 Jul 202630 Jul 2026On date
Mangeshi Arcade IIP51700047988KalyanCertificate Signed28 Feb 202728 Feb 2027On date
Mangeshi AmbarP51700047989GandhareCertificate Signed30 Jul 202630 Jul 2026+4 mo*
Mangeshi DharaP51700047990KalyanCertificate Signed30 Jun 202630 Oct 2026+5 mo*
Mangeshi GeminiP51700049445Vadavali Kh.Certificate Signed31 Dec 202731 Dec 2027On date
Mangeshi StarP51700049605Vadavali Kh.Certificate Signed31 Dec 202730 Apr 2028+4 mo
Mangeshi HeavenP51700049701Vadavali Kh.Certificate Signed31 Dec 202730 Apr 2028+4 mo
Mangeshi NeptuneP51700049741Vadavali Kh.Certificate Signed31 Dec 202731 Dec 2027On date
Mangeshi EarthP51700050038Vadavali Kh.Certificate Signed31 Dec 202731 Dec 2027On date
Mangeshi heightsP51700080264BalkumCertificate Signed31 Mar 203131 Mar 2031On date
Show all 19 registrationsShow fewer

Mangesh Dashrath Gaikar, in questions

Does Mangesh Dashrath Gaikar finish projects on time?

Of 12 MahaRERA registrations whose promised completion date has arrived, 9 kept it (75%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.

How many projects has Mangesh Dashrath Gaikar registered with MahaRERA?

19 projects under 19 MahaRERA registrations; 10 completed on MahaRERA.

Does Mangesh Dashrath Gaikar have MahaRERA regulatory cases?

2 regulatory cases name its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology