Delayed projects in Mumbai Suburban

995 MahaRERA projects in Mumbai Suburban are past their promised completion date, and MahaRERA shows no completion for them.

Most overdue first

Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 2 of 20.

ProjectLocalityPromisedRevisedDelivery
M M SpectraM. M. Developers - ShramjiviKurlaOct 2018Oct 20198 yrs 1 mo late
The NestHousing Development And Infrastructure LtdKurlaOct 2018Oct 20198 yrs 1 mo late
Ventures ALTA MONTEVentures Kuber Reality LLPAndheriDec 2018May 20267 yrs 11 mo late
Andheri Indira Nagar Chs LimitedJaspal Singh SuriAndheriDec 2018Jun 20247 yrs 11 mo late
Blue SapphireBlue Canyon Realty Pvt LtdAndheriDec 2018Feb 20247 yrs 11 mo late
Dahisar Udayraj ChslMitesh B ShahMumbaiDec 2018Nov 20237 yrs 11 mo late
Dev AshishCity Estate Developers LimitedKurlaDec 2018Dec 20187 yrs 11 mo late
Fatima Arch And DevelopersFatima Arch & DevelopersKurlaDec 2018Dec 20197 yrs 11 mo late
Haritara Residency / Haritara Co-operative Housing Society LimitedHaritara Construction CompanyBorivaliDec 2018Dec 20217 yrs 11 mo late
Jangid AnnexeJangid Home pvt LtdAndheriDec 2018Jun 20247 yrs 11 mo late
Jawahar Milan CHSLandmark Corporation Pvt. Ltd.BorivaliDec 2018Dec 20237 yrs 11 mo late
Kandivali Satyam Apartment Chs LtdJinam K2 RealtorsBorivaliDec 2018Dec 20247 yrs 11 mo late
Neelkanth Smruti Chs LimitedKshatriya Parshvanath Ventures Private LimitedBorivaliDec 2018Dec 20207 yrs 11 mo late
Neev GalaxyNeev Infrastructure Pvt. Ltd.BorivaliDec 2018Sep 20257 yrs 11 mo late
Neelgagan CHS LtdSwastik Realty Pvt LtdAndheriDec 2018Jun 20257 yrs 11 mo late
Poonam HeightsShah & Mehta AssociatesBorivaliDec 2018Jun 20257 yrs 11 mo late
Redevelopment Of Deep Sunderlane ChslPranav Constructions LimitedBorivaliDec 2018Dec 20187 yrs 11 mo late
Raj ShivgangaRaj Arcades & Enclaves Private LimitedBorivaliDec 2018Dec 20197 yrs 11 mo late
Redevelopment of OB swarganga chsl CTS no 154 pt survey no 383 pt chaitanya ngr santacruz e mum 55A A Estates Pvt LtdKurlaDec 2018Dec 20217 yrs 11 mo late
Shanta Mangesh ApartmentShanta Mangesh Developers Private LimitedAndheriDec 2018Dec 20197 yrs 11 mo late
Sheetal KrupaD.g.land Developers Private LimitedBorivaliDec 2018Jun 20247 yrs 11 mo late
Shree Santosh AppartmentBharat Navinchandra GalaBorivaliDec 2018Jun 20267 yrs 11 mo late
ShreyaBharat Navinchandra GalaBorivaliDec 2018Jun 20267 yrs 11 mo late
Siddhi GarimaNha Infraprojects Private LimitedKurlaDec 2018Dec 20257 yrs 11 mo late
Siddhi SamarpanNeha Hemant AgrawalBorivaliDec 2018Oct 20207 yrs 11 mo late
Silver ParkSilvex Constructions Pvt LtdKurlaDec 2018Oct 20207 yrs 11 mo late
Skyline viha Wing BAnkit OverseasKurlaDec 2018Jun 20247 yrs 11 mo late
Sun-Vision Heritage-SwatiS.S.Primespace Pvt. Ltd.AndheriDec 2018Oct 20207 yrs 11 mo late
TatvaGitanjali Infratech LimitedBorivaliDec 2018Dec 20197 yrs 11 mo late
Victory PlatinumPrashanti Land Developers Private LimitedMumbaiDec 2018Dec 20197 yrs 11 mo late
Wagheshwari DarshanUttam Ramji NisharKurlaDec 2018Dec 20197 yrs 11 mo late
Western WoodsKarmvir Mumbai Housing Private LimitedBorivaliDec 2018Dec 20197 yrs 11 mo late
Proposed Redevelopment of Sugam ApartmentJay BuildersKurlaJan 2019Dec 20227 yrs 10 mo late
Aditya ApartmentTejas Dinesh ShahBorivaliJan 2019Jan 20197 yrs 10 mo late
Balaji EnclaveBalaji EnterpriseBorivaliJan 2019Jul 20247 yrs 10 mo late
Kavya ResidencyPragati Infrasquare LLPAndheriJan 2019Jun 20227 yrs 10 mo late
Swarup NiketanSun-Vision Estates LtdAndheriFeb 2019Feb 20207 yrs 9 mo late
Ashoka Co-Op Hsg Society LimitedDesign Builders Pvt LtdBorivaliMar 2019Mar 20267 yrs 8 mo late
C And J Corporate ParkAnil AroraKurlaMar 2019Apr 20227 yrs 8 mo late
Casa PalazzoParadigm Real Estates LLPBorivaliMar 2019Feb 20227 yrs 8 mo late
Casa RareGeopreneur Corp Pvt LtdBorivaliMar 2019Sep 20227 yrs 8 mo late
Chintamani GloryChintamani RealtyMumbaiMar 2019Jun 20227 yrs 8 mo late
Ekta Apartment Upto 17th FloorAditya Enterprise Project EktaBorivaliMar 2019Feb 20267 yrs 8 mo late
Neumec VinayakNeumec VentureAndheriMar 2019Sep 20207 yrs 8 mo late
Nirmal Lifestyle-AmethystNirmal Lifestyle LtdKurlaMar 2019Jun 20267 yrs 8 mo late
OdinaRajyog EnterpriseKurlaMar 2019Sep 20207 yrs 8 mo late
Parijat TowersBetter Builders And Infrastructure Private LtdAndheriMar 2019Jun 20237 yrs 8 mo late
Shakuntala Silver BlissOswal RealtorsKurlaMar 2019Mar 20227 yrs 8 mo late
VishramJeevandeep DevelopersBorivaliMar 2019Jun 20267 yrs 8 mo late
Dsk MadhukoshD S Kulkarni Developers LimitedKurlaApr 2019Apr 20197 yrs 7 mo late

Delayed projects by district

SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology