2 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects228
Registrations228
Completion still due56144 past their date
Median extension4 months24% of registrations extended
Regulatory cases2on 2 projects
Nagar market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

8 in 10 registrations run late here

228 MahaRERA registrations in Nagar and the places within it

18 not yet due38 extended, not yet due144 past even the latest date28 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nagar

228 projects registered with MahaRERA in this taluka and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Crystal Tower Phase 2Maharaja DevelopersDue Apr 2028, extended 4 mo—17%
Saraswati TowerSaraswati DevelopersDue Dec 2026—0%
Parth VillaAshok Babanrao KhokaraleDue Dec 2027—22%
BluestoneMakarand Madhav KulkarniDue Mar 2027——
Parth Heights Phase 3Rajendra Ramchandra PawarDue Apr 2027, extended 4 mo—0%
Anand Vihar ResidencyGanga Developers10 mo late—14%
Sham Sunder PalaceKrushna Construction And Land DevelopersDue Jul 2028, extended 4 mo—0%
Adesh Heights Phase 11Suresh Namdev Lagad10 mo late—0%
Crown PlazaMahavir Infra Plus LLPDue Jul 2027, extended 4 mo—32%
Shobha HeritageNilesh Vasantrao Chavan7 mo late—10%
RegentRiselife SpacesDue Apr 2028, extended 4 mo—0%
PasaydanAdiraj DevelopersDue Jul 2027, extended 4 mo—0%
Mauli TowerMayur Anand Shinde10 mo late—0%
Shivganga PrideAjit Kundlik Ghodake5 mo late—20%
Alpha 1Nanda Raju Jadhav1 yr 7 mo late—0%
Sky CourtPranali InfraDue Oct 2026, extended 4 mo——
D R PrideD R BuildconDue Oct 2026—0%
Vivekanand Row-BungalowRahul Balasaheb BhosaleDue Dec 2026—50%
Anand VistaShubh Anand Realty3 mo late—0%
AbhiramMakarand Madhav Kulkarni7 mo late——
VivantaB And G Ventures1 yr 10 mo late—42%
Saffron EliteDhanraj Lalchand SanchetiDue Apr 2028, extended 4 mo——
Aai ResidencyVinod Dilip Pacharne1 yr 3 mo late—0%
ArabellaMarc DevelopersDue Mar 2027——
Sky HeightPranali InfrastructureDue Jan 2027—0%

Most active promoters

  1. Madhumalti Costruction Pvt Ltd7 projects
  2. Makarand Madhav Kulkarni6 projects
  3. Prasad Babanrao Andhale6 projects
  4. Kamath Associates5 projects
  5. Akash Construction4 projects
  6. Marc Developers4 projects
  7. Rajendra Ramchandra Pawar3 projects
  8. Suresh Namdev Lagad3 projects
  9. Ambadas Bhagwat Kadam2 projects
  10. Amit Ashok Mutha2 projects
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology