RERA projects in Nagar
227 projects under 227 MahaRERA registrations, registered 2017–2026. 5% have a completion date extended beyond the one promised.
227RERA projects
227Registrations
54Completion still due145 past their completion date
21 monthsMedian extension beyond promised date5% of registrations extended
1Regulatory caseson 1 project
19Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 43 |
| 2018 | 19 |
| 2019 | 22 |
| 2020 | 19 |
| 2021 | 22 |
| 2022 | 28 |
| 2023 | 24 |
| 2024 | 9 |
| 2025 | 8 |
| 2026 | 5 |
Projects in Nagar
227 projects registered with MahaRERA in this taluka and the places within it.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| RainflowerMadhumalti Costruction Pvt Ltd | PR1010002601300 | 24 Jul 2026 | 31 Dec 2031 | — | Not yet due | 0 |
| Platinum PlazaSpy Developers Builders And Suppliers | PC1010002502945 | 18 Mar 2026 | 31 Dec 2030 | — | Not yet due | 0 |
| Meher GalaxyGlorious Construction Company | PR1010002502501 | 26 Feb 2026 | 30 Nov 2030 | — | Not yet due | 0 |
| Saitej ApartmentGdps Construction LLP | PM1010002502450 | 23 Feb 2026 | 2 Aug 2029 | — | Not yet due | 0 |
| Jaystu Elite ResidencesDeepak Haribhau Bangar | PR1010002502139 | 21 Jan 2026 | 31 Mar 2031 | — | Not yet due | 0 |
| Sunflower ResidencyAishwary Builders And Developers | PR1010002500996 | 29 Sep 2025 | 1 May 2028 | — | Not yet due | 0 |
| Royal Casa 70 A WingVenkatesh Reality | PR1010002500582 | 14 Aug 2025 | 31 Dec 2029 | — | Not yet due | 0 |
| Sairaj ParkSairaj Park | P52200080901 | 4 Aug 2025 | 31 Dec 2026 | — | Not yet due | 0 |
| Elite 18Nilaya Group | PR1010002500273 | 14 Jul 2025 | 31 Dec 2031 | — | Not yet due | 0 |
| Chhatrapati HeightsShri Sanskruti Developers | P52200080709 | 26 Jun 2025 | 31 Dec 2026 | — | Not yet due | 0 |
| Breeze CourtAnil Bankatlal Gandhi | P52200079932 | 3 Apr 2025 | 30 Jul 2027 | — | Not yet due | 0 |
| Kalyan Castle4k Realty | P52200079813 | 27 Mar 2025 | 30 Jun 2030 | — | Not yet due | 0 |
| Shaniraj HeightsSantosh Machindra Shinde | P52200079785 | 26 Mar 2025 | 31 Mar 2030 | — | Not yet due | 0 |
| Swami Vivekanand TowersNavnath Machindra Katore | P52200078136 | 25 Nov 2024 | 31 Mar 2029 | — | Not yet due | 0 |
| R K HeightsBalbhimrao Doke And Rahul Kulthe Developers | P52200078003 | 19 Nov 2024 | 31 Mar 2027 | — | Not yet due | 0 |
| SnowbellMadhumalti Costruction Pvt Ltd | P52200077943 | 13 Nov 2024 | 31 Dec 2028 | — | Not yet due | 0 |
| TridentMakarand Madhav Kulkarni | P52200077919 | 13 Nov 2024 | 31 Mar 2029 | — | Not yet due | 0 |
| Rudranil Business CentreNiranjan Developers | P52200077885 | 8 Nov 2024 | 31 Jul 2027 | — | Not yet due | 0 |
| Sundarmoti ResidencyDilip Motilalji Chordia | P52200077628 | 17 Oct 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Rajrajeshwari AppartmentShankarleela Developers | P52200056362 | 31 May 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Kamath IrinKamath Associates | P52200054983 | 21 Feb 2024 | 2 Jun 2026 | — | Promised date passed | 0 |
| Royal WoodsKPGC Ventures Private Ltd. | P52200054180 | 3 Jan 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Solitaire Business HubA To Z Construction | P52200053899 | 8 Dec 2023 | 31 Mar 2026 | — | Promised date passed | 0 |
| 7 SolitaireInfinity Realties | P52200053663 | 21 Nov 2023 | 31 Dec 2025 | — | Promised date passed | 0 |
| Mina ApartmentMina Mohan Lad | P52200053580 | 10 Nov 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Crystal Tower Phase 2Maharaja Developers | P52200053209 | 23 Oct 2023 | 1 Dec 2027 | — | Not yet due | 0 |
| Saraswati TowerSaraswati Developers | P52200053013 | 10 Oct 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Parth VillaAshok Babanrao Khokarale | P52200052722 | 22 Sep 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| BluestoneMakarand Madhav Kulkarni | P52200052558 | 11 Sep 2023 | 31 Mar 2027 | — | Not yet due | 0 |
| Parth Heights Phase 3Rajendra Ramchandra Pawar | P52200052158 | 24 Jul 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Anand Vihar ResidencyGanga Developers | P52200051484 | 23 Jun 2023 | 23 Dec 2025 | — | Promised date passed | 0 |
| Sham Sunder PalaceKrushna Construction And Land Developers | P52200051511 | 23 Jun 2023 | 31 Mar 2028 | — | Not yet due | 0 |
| Adesh Heights Phase 11Suresh Namdev Lagad | P52200051423 | 14 Jun 2023 | 31 Dec 2025 | — | Promised date passed | 0 |
| Crown PlazaMahavir Infra Plus LLP | P52200051129 | 30 May 2023 | 31 Mar 2027 | — | Not yet due | 0 |
| Shobha HeritageNilesh Vasantrao Chavan | P52200050972 | 16 May 2023 | 31 Mar 2026 | — | Promised date passed | 0 |
| RegentRiselife Spaces | P52200050913 | 15 May 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| PasaydanAdiraj Developers | P52200050766 | 3 May 2023 | 31 Mar 2027 | — | Not yet due | 0 |
| Mauli TowerMayur Anand Shinde | P52200050742 | 28 Apr 2023 | 31 Dec 2025 | — | Promised date passed | 0 |
| Shivganga PrideAjit Kundlik Ghodake | P52200050706 | 28 Apr 2023 | 25 May 2026 | — | Promised date passed | 0 |
| Sky CourtPranali Infra | P52200050501 | 17 Apr 2023 | 30 Jun 2026 | — | Promised date passed | 0 |
| D R PrideD R Buildcon | P52200050251 | 27 Mar 2023 | 30 Oct 2026 | — | Not yet due | 0 |
| Vivekanand Row-BungalowRahul Balasaheb Bhosale | P52200049896 | 6 Mar 2023 | 31 Dec 2026 | — | Not yet due | 1 |
| Anand VistaShubh Anand Realty | P52200049796 | 24 Feb 2023 | 31 Jul 2026 | — | Promised date passed | 0 |
| AbhiramMakarand Madhav Kulkarni | P52200049407 | 8 Feb 2023 | 31 Mar 2026 | — | Promised date passed | 0 |
| VivantaB And G Ventures | P52200048884 | 24 Jan 2023 | 1 Dec 2024 | — | Promised date passed | 0 |
| Saffron EliteDhanraj Lalchand Sancheti | P52200048618 | 10 Jan 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Aai ResidencyVinod Dilip Pacharne | P52200048158 | 15 Dec 2022 | 31 Jul 2025 | — | Promised date passed | 0 |
| ArabellaMarc Developers | P52200048057 | 8 Dec 2022 | 31 Mar 2027 | — | Not yet due | 0 |
| Sky HeightPranali Infrastructure | P52200048032 | 7 Dec 2022 | 31 Jan 2027 | — | Not yet due | 0 |
| Nakshatra HeightsShashikant Gopinath Bhambare | P52200047966 | 2 Dec 2022 | 31 Dec 2024 | — | Promised date passed | 0 |
| Nathkrupa PlazaNathkrupa Developers | P52200047969 | 2 Dec 2022 | 30 Jun 2025 | — | Promised date passed | 0 |
| Pink City-IIAmit Ashok Mutha | P52200047775 | 28 Nov 2022 | 29 Mar 2027 | — | Not yet due | 0 |
| Kritikka AarambhaKritikka Realty | P52200047724 | 21 Nov 2022 | 30 Jun 2027 | — | Not yet due | 0 |
| Classic AuraSanjay Shantilal Gugale | P52200046771 | 5 Sep 2022 | 31 Dec 2027 | — | Not yet due | 0 |
| Jlp Business TowerAditya Builders & Developers (Prop. Jalindar Laxman Palve HUF) | P52200046537 | 10 Aug 2022 | 1 Nov 2024 | — | Promised date passed | 0 |
| Kuber HeightsMula Pravara Corporation | P52200046496 | 6 Aug 2022 | 30 Apr 2023 | — | Promised date passed | 0 |
| Morya ApartmentsMangalmurti Constructions | P52200046460 | 4 Aug 2022 | 1 Dec 2025 | — | Promised date passed | 0 |
| Adesh Heights Phase 8Suresh Namdev Lagad | P52200046099 | 20 Jun 2022 | 31 Dec 2024 | — | Promised date passed | 0 |
| Ganesh PrideSanklecha Construction | P52200046160 | 20 Jun 2022 | 31 Dec 2024 | — | Promised date passed | 0 |
| Vivekanand Row BungalowYogesh Balasaheb Mustapure | P52200046161 | 20 Jun 2022 | 31 Dec 2026 | — | Not yet due | 0 |
| ArianaMarc Developers | P52200045983 | 15 Jun 2022 | 31 Mar 2027 | — | Not yet due | 0 |
| Bappa Residencyketan shrikrishna navle | P52200045823 | 15 Jun 2022 | 31 Mar 2025 | — | Promised date passed | 0 |
| Samairakamath and mulay associates | P52200045476 | 24 May 2022 | 6 Feb 2024 | — | Promised date passed | 0 |
| Team57prideAnand Construction | P52200035121 | 10 May 2022 | 31 Dec 2024 | — | Promised date passed | 0 |
| Kamath Mithilakamathdevelopers | P52200035026 | 29 Apr 2022 | 22 Dec 2023 | — | Promised date passed | 0 |
| Stellar HeightsVision Group | P52200034632 | 20 Apr 2022 | 31 Dec 2026 | — | Not yet due | 0 |
| Nova CasaAllied Realty | P52200034574 | 11 Apr 2022 | 31 Dec 2025 | — | Promised date passed | 0 |
| Kamath Shalomkamathdevelopers | P52200033769 | 8 Mar 2022 | 24 Dec 2024 | — | Promised date passed | 0 |
| Swami Vivekanand PalaceVivekanand Construction | P52200033694 | 2 Mar 2022 | 31 Dec 2026 | — | Not yet due | 0 |
| Anand AppartmentOm Sai Trimurti Buildcon LLP | P52200033296 | 15 Feb 2022 | 31 Dec 2024 | — | Promised date passed | 0 |
| Oro Residential SchemeImperio Towers | P52200033222 | 9 Feb 2022 | 31 Dec 2027 | — | Not yet due | 0 |
| Shankar Parvati Park Phase 2Ganesh Shankarrao Fulari | P52200033213 | 9 Feb 2022 | 1 Oct 2025 | — | Promised date passed | 0 |
| Casa Row Colony Phase - 2Casa Developers | P52200032505 | 10 Jan 2022 | 1 Jan 2024 | — | Promised date passed | 0 |
| Urban RealtyJ G Enterprises | P52200032512 | 10 Jan 2022 | 27 Sep 2023 | — | Promised date passed | 0 |
| Bhagwati TowerBhagwati Enterprises | P52200032314 | 29 Dec 2021 | 31 Dec 2027 | — | Not yet due | 0 |
| Niramay ParkMonarch Properties | P52200032266 | 22 Dec 2021 | 31 Dec 2025 | — | Promised date passed | 0 |
| Borude EliteExtreme Properties | P52200032223 | 15 Dec 2021 | 31 Dec 2026 | — | Not yet due | 0 |
| Venkatesh PlazaPratibha Rajendra Joshi | P52200031717 | 8 Nov 2021 | 31 Oct 2025 | — | Promised date passed | 0 |
| Krushna HeightsKrishna Constructions | P52200031659 | 3 Nov 2021 | 31 Dec 2026 | — | Not yet due | 0 |
| Sky Bridge VillasManoj Madanlal Chhajed | P52200031527 | 25 Oct 2021 | 31 Dec 2023 | — | Promised date passed | 0 |
| Ulka SrushtiSai Associates | P52200031535 | 25 Oct 2021 | 31 Mar 2025 | — | Promised date passed | 0 |
| AarambhA To Z Construction | P52200031478 | 23 Oct 2021 | 31 Mar 2024 | — | Promised date passed | 0 |
| Ideal HomesSamarth Construction | P52200031154 | 11 Oct 2021 | 31 Mar 2025 | — | Promised date passed | 0 |
| Shri Swami Samarth ApartmentKavita Sanjay Baraskar | P52200031094 | 5 Oct 2021 | 30 Jun 2025 | — | Promised date passed | 0 |
| Kamath ElinaKamath Associates | P52200031030 | 1 Oct 2021 | 31 Dec 2025 | — | Promised date passed | 0 |
| Premium IconPremium Builders & Developers | P52200030905 | 29 Sep 2021 | 31 Aug 2027 | — | Not yet due | 0 |
| Trimurti ResidencyTrimurti Constructions | P52200030627 | 8 Sep 2021 | 30 Jun 2024 | — | Promised date passed | 0 |
| Tulsi ParkDevendra Babulal Patel | P52200030500 | 25 Aug 2021 | 31 Dec 2025 | — | Promised date passed | 0 |
| Adesh HeightsSuresh Namdev Lagad | P52200030368 | 17 Aug 2021 | 31 Dec 2023 | — | Promised date passed | 0 |
| Sadguru TowersBaba Developers | P52200029989 | 20 Jul 2021 | 31 Mar 2025 | — | Promised date passed | 0 |
| Kamath The OneKamath Associates | P52200029914 | 15 Jul 2021 | 30 Dec 2024 | — | Promised date passed | 0 |
| Sandeep PrideVenkatesh Buildcon | P52200028599 | 25 Mar 2021 | 30 Jun 2032 | — | Not yet due | 0 |
| Saraswati ResidencyPratap Gulab Bhogade | P52200028476 | 4 Mar 2021 | 30 Jun 2023 | — | Promised date passed | 0 |
| MagnoliaMadhumalti Costruction Pvt Ltd | P52200028201 | 10 Feb 2021 | 30 Jun 2026 | — | Promised date passed | 0 |
| Shree Ganesh ApartmentShree Ganesh Developers | P52200028175 | 10 Feb 2021 | 30 Oct 2022 | — | Promised date passed | 0 |
| Sukrutam ApartmentMakarand Krishnaji Deshpande | P52200028127 | 4 Feb 2021 | 30 Jun 2023 | — | Promised date passed | 0 |
| Meher BlissGlorious Construction Company | P52200027424 | 10 Dec 2020 | 30 Jun 2024 | — | Promised date passed | 0 |
| Sukriti Apartment Phase IIINitin Machindra Shewale | P52200027146 | 19 Nov 2020 | 7 Sep 2025 | — | Promised date passed | 0 |
| Siyaram Phase IIMadhumalti Costruction Pvt Ltd | P52200027000 | 10 Nov 2020 | 30 Jun 2024 | — | Promised date passed | 0 |
| Sai SurajRavindra Balasaheb Kharde | P52200026946 | 7 Nov 2020 | 30 Jun 2022 | — | Promised date passed | 0 |
Other talukas in Ahmednagar
Most active promoters
By projects registered here, as named on MahaRERA.
- Madhumalti Costruction Pvt Ltd7 projects
- Makarand Madhav Kulkarni6 projects
- Prasad Babanrao Andhale6 projects
- Kamath Associates5 projects
- Akash Construction4 projects
- Marc Developers4 projects
- Rajendra Ramchandra Pawar3 projects
- Suresh Namdev Lagad3 projects
- Ambadas Bhagwat Kadam2 projects
- Amit Ashok Mutha2 projects
Data through8 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology